Project Jupiter

Santa Teresa,Doña Ana County,New MexicoUnder constructionFirst public 2025Filing entity: BorderPlex Digital AssetsLast checked Nov 8, 2026

STACK InfrastructureDeveloperBorderPlex Digital AssetsDeveloperClaycoBuilderKiewit New MexicoBuilder

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Project Jupiter is a under-construction data center project in Santa Teresa, Doña Ana County, New Mexico. Oracle is named as operator. It was first public in 2025. It was announced at 2,450 MW.

Project Jupiter is an under-construction data center project in Santa Teresa, Doña Ana County, New Mexico. Oracle is named as operator. It was announced at 2,450 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Santa Teresa, Doña Ana County, New Mexico. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

2,450 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Doña Ana County, New Mexico.See every project on the map

The land, to scale

One football field
1,400 acres, about 1,059 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Project JupiterUnder construction

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026New Mexico HB 93: Lets utilities recover grid technology costs and microgrids sell power

    The act covers qualified microgrids, self-source power systems with a generation resource capable of generating not less than twenty megawatts, and the persons who receive electricity service using one; this project has 2,450 MW on record (generator capacity), but whether this project receives electricity service using a qualified microgrid is not on record.

    “"qualified microgrid" means a permanent or temporary electrical system that: (a) incorporates a microgrid controller; (b) includes a self-source generation resource that is capable of generating not less than twenty megawatts” (Definition of qualified microgrid, chaptered text)

    Rule checks: Project is in New Mexico; 2,450 MW on record (announced), threshold 20 MW (Definition of qualified microgrid, chaptered text). Still to check: dates: not checked, who it covers: not checked

Bills and laws in New Mexico

Open Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 2,450 MW · Bloom fuel cell microgridApr 2026 · generator_capacity

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Project Jupiter?
    Project Jupiter is a data center project in Santa Teresa, Doña Ana County, New Mexico.
    Who operates Project Jupiter?
    Oracle is named as the operator of Project Jupiter.
    How big is Project Jupiter?
    Project Jupiter was announced at 2,450 MW of capacity. The site covers 1,400 acres.
    What stage is Project Jupiter?
    Project Jupiter is under construction. It was first public in 2025.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      STACK Infrastructure Reinforces Responsible Development Principles through Project Jupiter in New Mexico
      STACK Infrastructure via GlobeNewswire
      Tier 4 · Captured 2026-11-08 · Open the source
    2. 2
      Oracle, BorderPlex, and Bloom Energy to Power Project Jupiter with Cleaner, Water-Efficient Fuel Cell Technology
      Oracle
      Tier 4 · Captured 2026-11-08 · Open the source
    3. 3
      OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites
      OpenAI
      Tier 4 · Captured 2026-11-08 · Open the source
    4. 4
      Clayco and Kiewit Top Out First Building at Project Jupiter in New Mexico
      Clayco (announcement as republished by Baxtel)
      Tier 4 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page