Louisville,Jefferson County,KentuckyApprovedFirst public 2025Filing entity: PowerHouse Data Centers and Poe Companies joint ventureLast checked Nov 8, 2026
PowerHouse Data CentersDeveloperPoe CompaniesDeveloperLG&E and KUElectric utility
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
PowerHouse and Poe Companies data center campus (Louisville) is an approved data center project in Louisville, Jefferson County, Kentucky. PowerHouse Data Centers is named as developer. It was first public in 2025. It was announced at 400 MW.
PowerHouse and Poe Companies data center campus (Louisville) is an approved data center project in Louisville, Jefferson County, Kentucky. PowerHouse Data Centers is named as developer. It was announced at 400 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Louisville, Jefferson County, Kentucky. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of PowerHouse and Poe Companies data center campus (Louisville)Approved
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Kentucky HB 775: Extends data center tax incentives to counties statewide by population
The act covers owners, operators, or colocation tenants of a qualified data center project that meet the capital investment tier for their county's population, from $25 million in counties of 50,000 or fewer people to $450 million in counties of 100,000 or more; this project has 402 MW on record (grid connection), but the project's capital investment and the population tier of its county is not on record.
“For an owner, operator, or colocation tenant, at least: Four hundred fifty million dollars ($450,000,000) if located in a county having a population equal to or greater than one hundred thousand (100,000); One hundred million dollars ($100,000,000) if located in a county having a population greater than fifty thousand (50,000) but less than one hundred thousand (100,000); or Twenty-five million dollar ($25,000,000) if located in a county having a population of not more than fifty thousand (50,000).” (Section 34, KRS 154.20-220(17)(b)1)
Rule checks: Project is in Kentucky. Still to check: who it covers: not checked
Bills and laws in Kentucky
- HB 593 · Died or failed · Mar 31, 2026Requires data center power contracts that protect other customers
- HB 856 · Died or failed · Mar 10, 2026Requires water feasibility studies and annual water reports
- SB 319 · Died or failed · Mar 2, 2026Requires decommissioning plans for data centers on farmland
- HB 544 · Died or failed · Feb 10, 2026Requires commission approval for power service over 100 megawatts
- HB 775 · In effect · Mar 27, 2025Extends data center tax incentives to counties statewide by population
Who's involved
- DeveloperPowerHouse Data Centers
- DeveloperPoe Companies
- Electric utilityLG&E and KU
Power
Capacity, as announced or filed
- 400 MW · Full campusJan 2025 · what the figure measures is not stated
- 335 MW · Initial power capacityJan 2025 · grid connection
- 402 MW · Near-term expansionJan 2025 · grid connection
- 130 MW · First phaseJan 2025 · what the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is PowerHouse and Poe Companies data center campus (Louisville)?
- PowerHouse and Poe Companies data center campus (Louisville) is a data center project in Louisville, Jefferson County, Kentucky.
- Who is developing PowerHouse and Poe Companies data center campus (Louisville)?
- PowerHouse Data Centers is named as the developer of PowerHouse and Poe Companies data center campus (Louisville).
- How big is PowerHouse and Poe Companies data center campus (Louisville)?
- PowerHouse and Poe Companies data center campus (Louisville) was announced at 400 MW of capacity. The site covers 150 acres.
- What stage is PowerHouse and Poe Companies data center campus (Louisville)?
- PowerHouse and Poe Companies data center campus (Louisville) is approved. It was first public in 2025.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1PowerHouse Data Centers and Poe Companies Partner to Develop Kentucky's First Hyperscale Data Center Campus
PowerHouse Data Centers (American Real Estate Partners)Tier 4 · Captured 2026-11-08 · Open the source - 2LG&E announces first major data center electric customer
Louisville Gas and Electric Company (PPL Corporation)Tier 4 · Captured 2026-11-08 · Open the source - 3Data Centers in Kentucky: Policy Analysis for the General Assembly, EPIC Report No. 2026-001
Kentucky Energy Planning and Inventory CommissionTier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page