Project File
Meta Rosemount Data Center
Rosemount,Dakota County,MinnesotaUnder constructionFirst public 2024Filing entity: Meta Platforms, Inc.Last checked Nov 8, 2026
MetaDeveloper and operatorMortensonBuilderXcel EnergyElectric utility
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Meta Rosemount Data Center is a under-construction data center project in Rosemount, Dakota County, Minnesota. Meta is named as operator. It was first public in 2024. No site capacity figure is published for this project.
Meta Rosemount Data Center is an under-construction data center project in Rosemount, Dakota County, Minnesota. Meta is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Rosemount, Dakota County, Minnesota. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Meta Rosemount Data CenterUnder construction
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Minnesota HF 9: Tax bill ending the sales tax exemption on data center electricity
The act covers qualified data centers and qualified refurbished data centers, whose purchases of enterprise information technology equipment and computer software for use in the center are exempt; this project has no capacity figure on record, but whether this project is a qualified data center or a qualified refurbished data center under Minnesota Statutes Sec. 297A.68, subdivision 42 is not on record.
“Purchases of enterprise information technology equipment and computer software for use in a qualified data center, or a qualified refurbished data center, are exempt, except that computer software maintenance agreements are exempt for purchases made after June 30, 2013.” (Section 4, amending Minnesota Statutes section 297A.68, subdivision 42 (a))
Rule checks: Project is in Minnesota. Still to check: dates: not checked, who it covers: not checked
Bills and laws in Minnesota
- SF 4203 · Died or failedChanges to the data center sales and use tax exemption
- SF 4681 · Died or failedData center exemptions and provisions modified
- HF 2928 · Died or failedWater, environmental review, and energy rules for data centers
- SF 4298 · Died or failedMoratorium on new data centers; utility commission report
- HF 4153 · Died or failedWater criteria and tax exemptions for data centers
- SF 5231 · Died or failedRepeals the data center sales and use tax exemption
Who's involved
- Developer and operatorMeta
- BuilderMortenson
- Electric utilityXcel Energy
Public records
1 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Decided · May 15, 2026Northern States Power Company (Xcel Energy) very large customer tariff under Minn. Stat. 216B.1622
Questions people ask
- Where is Meta Rosemount Data Center?
- Meta Rosemount Data Center is a data center project in Rosemount, Dakota County, Minnesota.
- Who operates Meta Rosemount Data Center?
- Meta is named as the operator of Meta Rosemount Data Center.
- How big is Meta Rosemount Data Center?
- The site covers 280 acres.
- What stage is Meta Rosemount Data Center?
- Meta Rosemount Data Center is under construction. It was first public in 2024.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Very large electric customers and the PUC process
Minnesota Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 2Data Centers to Pay Fair Share: PUC enacts protections for Xcel customers
Citizens Utility Board of MinnesotaTier 4 · Captured 2026-11-08 · Open the source - 3Hello, Rosemount!
Meta Data Centers (datacenters.atmeta.com)Tier 4 · Captured 2026-11-08 · Open the source - 4Governor Walz Announces Meta Will Build New Data Center in Rosemount
Office of Governor Tim Walz and Lt. Governor Peggy Flanagan (mn.gov)Tier 1 · Captured 2026-11-08 · Open the source - 5Building the 21st-century economy: Xcel Energy to power new Meta data center
Xcel Energy StoriesTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page