Skip to content

Project File

Digital Realty Bedford

Bedford,Middlesex County,MassachusettsOperatingFirst public 2009Filing entity: Digital Realty Trust, Inc.Last checked Nov 8, 2026

Digital RealtyOperator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: First public date
  • Still to confirm: Capacity
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Digital Realty Bedford is an operating data center project in Bedford, Middlesex County, Massachusetts. Digital Realty is named as operator. It was first public in 2009. No site capacity figure is published for this project.

Digital Realty Bedford is an operating data center project in Bedford, Middlesex County, Massachusetts. Digital Realty is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Bedford, Middlesex County, Massachusetts. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Middlesex County, Massachusetts.See every project on the map

Timeline

  1. · New projectFirst public record of Digital Realty BedfordOperating

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Massachusetts EO 658: State permits for large data centers require community agreements

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

Bills and laws in Massachusetts

Open Bill Watch

Who's involved

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Digital Realty Bedford?
    Digital Realty Bedford is a data center project in Bedford, Middlesex County, Massachusetts.
    Who operates Digital Realty Bedford?
    Digital Realty is named as the operator of Digital Realty Bedford.
    What stage is Digital Realty Bedford?
    Digital Realty Bedford is operating. It was first public in 2009.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Digital Realty Trust, Inc. Form 8-K (New England Portfolio purchase agreements)
      U.S. Securities and Exchange Commission (EDGAR)
      Tier 2 · Captured 2026-11-08 · Open the source
    2. 2
      Digital Realty Trust Completes Acquisition of Major Datacenter Portfolio in New England
      Digital Realty Trust, Inc. (PR Newswire release)
      Tier 4 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page