EO 658: State permits for large data centers require community agreements

Official title: Establishing Requirements for Responsible Data Center Development and Operations in Massachusetts to Protect and Support Ratepayers, Communities, and the Environment

Official text

Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.

Where it stands

In effect as of Sep 8, 2026. The official record says: in effect.

  1. Issued (executive or agency action) (done)
  2. In effect (current stage)
  3. Ended or expired (not reached)

What it means for a household (draft rating)

Helps households. The order sets a payment on data centers that fall short on clean power and sends the money to a fund that cuts supply costs for ratepayers.

"Funds collected via the ACP mechanism shall be credited to a Ratepayer Protection Fund, with said funds used to mitigate electricity supply costs for all ratepayers."Section 5

We rate a bill as helping or costing households only when its own text says who pays or who is exempt. Otherwise it is unclear. This is a draft rating and has not been verified yet.

What it does

  • Certification · threshold 25 MW

    Applies to: data center projects

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement…”

    Executive Order No. 658, Section 1

  • Fee

    Applies to: data centers not procuring sufficient incremental clean electricity

    “By December 31, 2026, MassDEP shall take action to establish an alternative compliance payment ("ACP") mechanism for data centers that do not procure sufficient incremental clean electricity to meet their annual electric consumption.”

    Executive Order No. 658 (alternative compliance payment section)

  • Study or report

    Applies to: municipal governments evaluating data center projects

    “EEA, in coordination with the Executive Office of Economic Development ("EOED") and consistent with the Framework, shall publish, by December 31, 2026, a Municipal Guidance Document for Data Center Development ("Guide").”

    Executive Order No. 658 (municipal guidance section)

Who it touches (11)

Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Centersquare BOS4 (Boston)

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite BO1

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank BOS1 (Boston)

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty Bedford

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty Needham

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix BO2 (Boston)

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Markley Lowell

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Markley One Summer Street

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026TierPoint Andover

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026TierPoint Marlborough (MRL)

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Westfield Servistar Data Center Campus

    The act covers data center projects with peak electricity demand exceeding twenty-five megawatts, built or expanded after the order took effect, whose applicants must show conformance with the state Framework and submit a community benefits agreement before state permits or authorizations may issue; this project has no capacity figure on record, but the project's peak electricity demand and whether it was built or expanded after the order took effect is not on record.

    “The Department of Environmental Protection ("MassDEP"), the Energy Facilities Siting Board ("EFSB"), the Massachusetts Environmental Policy Act Office ("MEPA"), and other relevant permitting-related agencies shall not issue any permits or authorizations associated with any data center project with peak electricity demand exceeding twenty-five megawatts to any data center applicant unless that applicant has: (1) demonstrated conformance with the Statement of Expectations for Responsible Data Center Development and Operations in Massachusetts, published June 25, 2026 ("Framework") including those related to air quality and public health, water use, and community engagement” (Executive Order No. 658, Section 1)

    Rule checks: Project is in Massachusetts. Still to check: size: unknown, who it covers: not checked

Other projects we track in Massachusetts (2), not affected

Who acted

  • SponsorMaura Healey

Timeline

Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.

  1. · GovernorExecutive Order No. 658 signed by Governor HealeyStage: In effect

Sources

  1. 1
    Executive Order No. 658: Establishing Requirements for Responsible Data Center Development and Operations in Massachusetts
    Commonwealth of Massachusetts (mass.gov)
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "EO 658: State permits for large data centers require community agreements." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/ma-2026-eo-658

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page