Project File

DataBank EWR1 Newark

Newark,Essex County,New JerseyOperatingLast checked Nov 10, 2026

DataBankDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Still to confirm: Electric utility
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

DataBank EWR1 Newark is an operating data center project in Newark, Essex County, New Jersey. DataBank is named as operator. It was announced at 1.7 MW.

DataBank EWR1 Newark is an operating data center project in Newark, Essex County, New Jersey. DataBank is named as operator. It was announced at 1.7 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Newark, Essex County, New Jersey. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

2 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Aerial view of DataBank EWR1 Newark in Newark, Essex County, New Jersey, captured 2023
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2023Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Aerial view of DataBank EWR1 Newark in Newark, Essex County, New Jersey, captured 2025
Aerial image, New Jersey 2025 orthophotography (NJOGIS), New Jersey Conditions of Use, Section F: State information is public domain unless a restriction is stated (none is stated for this imagery); copying and distribution allowed, acknowledgement requested, captured 2025Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: New Jersey 2025 orthophotography (NJOGIS)License: New Jersey Conditions of Use, Section F: State information is public domain unless a restriction is stated (none is stated for this imagery); copying and distribution allowed, acknowledgement requested
Site-level positionPin placed from the position we have on file, inside Essex County, New Jersey.See every project on the map

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026New Jersey S3379: Requires twice yearly water and energy reports from data centers

    The act requires the owner or operator of a data center in this state to prepare and submit a water and energy usage report to the Board of Public Utilities, and this project is a data center in New Jersey on record, so every condition the text sets is met by a fact on record. Status part: the bill's status (signed into law) makes its text operative. Text part: the decision rests on the bill's text quoted here, which covers every data center in the State.

    “No later than six months after the effective date of this section, or, for a data center that has been in operation for at least one year as of the effective date of this section, no later than three months after the effective date of this section, and on a semi-annual basis thereafter, the owner or operator of a data center in the State shall prepare and submit a water and energy usage report to the Board of Public Utilities” (S 3379 introduced text, section 1.b)

    Rule checks: Project is in New Jersey. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026New Jersey S3432: Creates tax credits for AI and data center investment

    The act covers AI data centers, facilities built to handle the computational needs of artificial intelligence applications such as machine learning training and deep learning, under the Next New Jersey Program; this project has 1.7 MW on record (IT load), but whether this project is an AI data center and whether it participates in the Next New Jersey Program is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “AI data center means a facility specifically to handle the demanding computational needs of artificial intelligence applications, designed for tasks like machine learning training, deep learning algorithms, and complex data analysis, whose services are the storage, management, and processing of digital data” (S 3432 introduced text, section 2)

    Rule checks: Project is in New Jersey. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026New Jersey S4390: Ends uncommitted tax credits for data center projects

    The act covers tax credits awarded under the Next New Jersey Program, for which no more than $250 million may be made available; this project has 1.7 MW on record (IT load), but whether this project holds or seeks a tax credit under the Next New Jersey Program is not on record. Status part: the bill's status (signed into law) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “for tax credits awarded under the "Next New Jersey Program Act," P.L.2024, c.49 (C.34:1B-394 et al.); an amount not to exceed [$500,000,000] $250,000,000 shall be made available” (S 4390 introduced text, section 1.b.(1)(k) (bracketed figure is the prior law omitted by the act))

    Rule checks: Project is in New Jersey. Still to check: who it covers: not checked

Bills and laws in New Jersey

All 8 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 1.7 MW · Nov 2026 · it_load

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is DataBank EWR1 Newark?
    DataBank EWR1 Newark is a data center project in Newark, Essex County, New Jersey.
    Who operates DataBank EWR1 Newark?
    DataBank is named as the operator of DataBank EWR1 Newark.
    How big is DataBank EWR1 Newark?
    DataBank EWR1 Newark was announced at 1.7 MW of capacity.
    What stage is DataBank EWR1 Newark?
    DataBank EWR1 Newark is operating.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Downtown Newark Data Center (EWR1), 165 Halsey Street
      DataBank
      Tier 4 · Captured 2026-11-10 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page