city Card
Data centers in Muskogee, Oklahoma
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 1 data center project in Muskogee, Oklahoma as of November 2026, totaling about 1,500 MW announced where a figure is published.
Muskogee has 1 tracked data center project. Their announced capacity totals about 1,500 MW where a figure is published. The project here is Core Scientific data center campus, Muskogee (CoreWeave), expanding. Every figure comes from the public record linked on this page.
Data center projects in Muskogee
- Core Scientific data center campus, Muskogee (CoreWeave)
ExpandingMuskogee1,500 MW announced
Who serves this place
- Not collected yet.
More places in Muskogee County
Muskogee is part of Muskogee County.
Nearby places
- Council Hill1 data center project tracked
- Summit1 data center project tracked
Court cases and commission dockets in Oklahoma (2)
Bills and laws in Oklahoma
- HB 2992 · In effect · Jul 1, 2026Requires separate tariffs and long contracts for large load customers
- SB 259 · Signed into law · May 20, 2026Restricts groundwater cooling permits for data centers
- HB 3724 · Died or failed · Feb 17, 2026Bans subsidies and cost shifting for high-demand facilities
- HB 3392 · Died or failed · Feb 11, 2026Orders a state study of large load customer impacts
- HB 3917 · Died or failed · Feb 4, 2026Adds a peak demand surcharge for large data centers
- HB 4194 · Died or failed · Feb 3, 2026Requires financial assurance for data center decommissioning
- HB 3397 · Died or failed · Feb 3, 2026Creates a separate electricity rate class for large data centers
- SB 1488 · Died or failed · Feb 3, 2026Bans new data centers until November 2029 pending a study
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Muskogee?
- Data Center Fact Check tracks 1 data center project in Muskogee as of November 2026.
- What is the biggest data center in Muskogee?
- By announced capacity, the biggest data center in Muskogee is Core Scientific data center campus, Muskogee (CoreWeave), announced at 1,500 MW. It is expanding.
- How much power do data centers in Muskogee use?
- The 1 projects tracked in Muskogee have announced about 1,500 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Muskogee." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ok-muskogee-city
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page