Project File
ValorC3 St. George Data Center (STG-1)
St. George,Washington County,UtahOperatingFirst public 2008Filing entity: ValorC3 Data CentersLast checked Nov 8, 2026
ValorC3Operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
ValorC3 St. George Data Center (STG-1) is an operating data center project in St. George, Washington County, Utah. ValorC3 is named as operator. It was first public in 2008. No site capacity figure is published for this project.
ValorC3 St. George Data Center (STG-1) is an operating data center project in St. George, Washington County, Utah. ValorC3 is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in St. George, Washington County, Utah. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · New projectFirst public record of ValorC3 St. George Data Center (STG-1)Operating
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 507: Limits local incentives for large data centers outside development zones
The act covers large load data centers that are not located within a regionally significant development zone, for which a county or municipality may not offer an incentive, except project areas and agreements predating May 6, 2027; this project has 4 MW on record (not stated), but whether this project is a large load data center, whether it is located within such a zone, and whether a county or municipality offered it an incentive is not on record.
“Except as provided in Subsection (1)(b), a county or municipality may not offer an incentive for a large load data center that is not located within a zone.” (Utah Code Sec. 63N-3a-402(1)(a))
Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Utah HB 76: Requires data centers to report water use before and after building
The act covers large data centers, facilities with an annual water withdrawal of 75 acre feet per year or more whose buildings total at least 10,000 square feet; this project has 4 MW on record (not stated), but the project's annual water withdrawal and its building area is not on record.
“"Large data center" means a facility with an annual water withdrawal of 75 acre feet per year or more that: (i) houses a group of networked server computers in one physical location to disseminate, manage, and store data and information as the primary service of the facility; (ii) consists of one or more buildings that in total equals or exceeds 10,000 square feet;” (Utah Code Sec. 73-5-8.3(1)(d), as enacted by H.B. 76, Section 2)
Rule checks: Project is in Utah. Still to check: dates: not checked, who it covers: not checked
Bills and laws in Utah
- HB 76 · In effect · May 6, 2026Requires data centers to report water use before and after building
- HB 507 · Signed into law · Mar 25, 2026Limits local incentives for large data centers outside development zones
- SB 132 · In effect · May 7, 2025Sets cost and service rules for electric loads over 100 megawatts
Who's involved
- OperatorValorC3
Power
Capacity, as announced or filed
- 4 MW · Facility totalNov 2026 · what the figure measures is not stated
- 2 MW · Critical IT loadNov 2026 · it_load
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is ValorC3 St. George Data Center (STG-1)?
- ValorC3 St. George Data Center (STG-1) is a data center project in St. George, Washington County, Utah.
- Who operates ValorC3 St. George Data Center (STG-1)?
- ValorC3 is named as the operator of ValorC3 St. George Data Center (STG-1).
- What stage is ValorC3 St. George Data Center (STG-1)?
- ValorC3 St. George Data Center (STG-1) is operating. It was first public in 2008.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1St. George Data Center (STG-1), 1108 West 1600 South
ValorC3 Data CentersTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page