Switch Big Beaver Data Center (Switch PIT 01-03)

Big Beaver,Beaver County,PennsylvaniaIn permittingFirst public 2026Filing entity: Switch, Ltd.Last checked Nov 14, 2026

SwitchDeveloper

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: First public date
  • Still to confirm: Capacity
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Switch Big Beaver Data Center (Switch PIT 01-03) is a data center project in Big Beaver, Beaver County, Pennsylvania. Switch is named as developer. It is in permitting. It was first public in 2026. No site capacity figure is published for this project.

Switch Big Beaver Data Center (Switch PIT 01-03) is a data center project in Big Beaver, Beaver County, Pennsylvania. Switch is named as developer. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Big Beaver, Beaver County, Pennsylvania. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

1Public records we have found
215,750Floor area, sq ft
3Buildings

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Beaver County, Pennsylvania.See every project on the map

The land, to scale

One football field
384 acres, about 290 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · FilingFiled with Big Beaver Borough for Switch Big Beaver Data Center (Switch PIT 01-03)
  2. · New projectFirst public record of Switch Big Beaver Data Center (Switch PIT 01-03)In permitting

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Pennsylvania HB 1834: Regulates commercial data centers and their energy use

    The act covers commercial data centers in Pennsylvania, facilities used for processing, storing, retrieving, or transmitting data with a peak demand of 25 megawatts or greater that are interconnected to a public utility; this project is a data center in Beaver County, Pennsylvania, with a stage of in_permitting on record, but the project's peak demand is not on record.

    “A facility, campus of facilities or array of interconnected facilities in this Commonwealth that meets all of the following: (1) Is used by a business entity or other enterprise to operate, manage or maintain a computer, group of computers or other organized assembly of hardware and software for the primary purpose of processing, storing, retrieving or transmitting data. (2) Has a peak demand of 25 megawatts or greater. (3) Is interconnected to a public utility at a single point of interconnection or multiple points of interconnection or is interconnected to multiple public utilities within this Commonwealth through multiple points of interconnection.” (Section 2, definition of commercial data center)

    Rule checks: Project is in Pennsylvania. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Pennsylvania HB 2650: Requires state certification for data center tax benefits

    The act covers computer data centers in Pennsylvania, facilities predominantly used to house working servers or similar data storage systems, when an owner or operator seeks GRID certification and its tax benefits; this project is a data center in Beaver County, Pennsylvania, with a stage of in_permitting on record, but whether its owner or operator has applied for or holds GRID certification is not on record.

    “All or part of a facility that may be composed of one or more businesses, owners or tenants, that is or will be predominantly used to house working servers or similar data storage systems and that may have uninterruptible energy supply or generator backup power, or both closed-loop cooling systems, towers and other temperature control infrastructure.” (Section 2902-D.1, definition of computer data center)

    Rule checks: Project is in Pennsylvania. Still to check: who it covers: not checked

Bills and laws in Pennsylvania

All 12 in Bill Watch

Who's involved

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Big Beaver Borough

    Stated in the filing
    383.996 acres
    Buildings
    3
    Floor area
    215,750 sq ft

Public records

1 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Switch Big Beaver Data Center (Switch PIT 01-03)?
Switch Big Beaver Data Center (Switch PIT 01-03) is a data center project in Big Beaver, Beaver County, Pennsylvania.
Who is developing Switch Big Beaver Data Center (Switch PIT 01-03)?
Switch is named as the developer of Switch Big Beaver Data Center (Switch PIT 01-03).
How big is Switch Big Beaver Data Center (Switch PIT 01-03)?
The site covers 384 acres.
What stage is Switch Big Beaver Data Center (Switch PIT 01-03)?
Switch Big Beaver Data Center (Switch PIT 01-03) is in permitting. It was first public in 2026.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Big Beaver Borough Engineer's review of Switch, Ltd. Preliminary Land Development Plans, 201 Pendale Road
    Big Beaver Borough
    Tier 1 · Captured 2026-11-10 · Open the source