Project File
Microsoft Mount Pleasant data center campus (Fairwater)
Mount Pleasant,Racine County,WisconsinExpandingFirst public 2023Filing entity: Microsoft CorporationLast checked Nov 8, 2026
MicrosoftDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Microsoft Mount Pleasant data center campus (Fairwater) is an expanding data center project in Mount Pleasant, Racine County, Wisconsin. Microsoft is named as operator. It was first public in 2023. No site capacity figure is published for this project.
Microsoft Mount Pleasant data center campus (Fairwater) is an expanding data center project in Mount Pleasant, Racine County, Wisconsin. Microsoft is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Mount Pleasant, Racine County, Wisconsin. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Microsoft Mount Pleasant data center campus (Fairwater)Expanding
Bills and laws in Wisconsin
- SB 241 · Died or failed · Mar 23, 2026Tax incremental districts containing qualified data centers
- SB 843 · Died or failed · Mar 23, 2026Cost, water, and bonding requirements for data centers
- SB 244 · Died or failed · Mar 23, 2026Changes to the sales tax exemption for qualified data centers
- AB 245 · Died or failed · Mar 23, 2026Changes to the sales tax exemption for qualified data centers
- AB 840 · Died or failed · Mar 23, 2026Cost, water, and bonding requirements for data centers
- SB 969 · Died or failed · Mar 23, 2026Bans NDAs that conceal data center information from the public
Who's involved
- Developer and operatorMicrosoft
Public records
1 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Decided · Apr 24, 2026Application of Wisconsin Electric Power Company for approval of its Very Large Customer and Bespoke Resources Tariffs
Questions people ask
- Where is Microsoft Mount Pleasant data center campus (Fairwater)?
- Microsoft Mount Pleasant data center campus (Fairwater) is a data center project in Mount Pleasant, Racine County, Wisconsin.
- Who operates Microsoft Mount Pleasant data center campus (Fairwater)?
- Microsoft is named as the operator of Microsoft Mount Pleasant data center campus (Fairwater).
- How big is Microsoft Mount Pleasant data center campus (Fairwater)?
- The site covers 1,575 acres.
- What stage is Microsoft Mount Pleasant data center campus (Fairwater)?
- Microsoft Mount Pleasant data center campus (Fairwater) is expanding. It was first public in 2023.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1PSC Overhauls We Energies' Data Center Tariff, Makes Improvements (press release)
Public Service Commission of WisconsinTier 1 · Captured 2026-11-08 · Open the source - 2Final Decision, Docket 6630-TE-113 (Wisconsin Electric Power Company, Very Large Customer and Bespoke Resources Tariffs), PSC REF# 591873
Public Service Commission of WisconsinTier 1 · Captured 2026-11-08 · Open the source - 3Press Release: Gov. Evers, Microsoft Officials Announce New $4 Billion Investment in Mount Pleasant Datacenter
Office of Governor Tony Evers (Wisconsin)Tier 1 · Captured 2026-11-08 · Open the source - 4Understanding Microsoft datacenters in Racine County
Microsoft LocalTier 4 · Captured 2026-11-08 · Open the source - 5Microsoft in Racine County: News & Updates
Racine County Economic Development CorporationTier 2 · Captured 2026-11-08 · Open the source - 6EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page