Meta Richland Parish Data Center

Richland Parish,LouisianaUnder constructionFirst public 2024Filing entity: Laidley LLCLast checked Nov 8, 2026

MetaDeveloper and operatorDPR ConstructionBuilderTurner ConstructionBuilderMortensonBuilder

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: City or address
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Meta Richland Parish Data Center is a under-construction data center project in Richland Parish, Louisiana. Meta is named as operator. It was first public in 2024. It was announced at 5,000 MW.

Meta Richland Parish Data Center is an under-construction data center project in Richland Parish, Louisiana. Meta is named as operator. It was announced at 5,000 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Richland Parish, Louisiana. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

5,000 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    LED states Meta is paying tens of millions of dollars in taxes every year, and construction sales taxes have already funded record supplemental payments to Richland Parish teachers.

    Comes to the community
  2. Tax breaks

    The state expects Meta to use Louisiana’s Act 730 sales and use tax rebate on data center equipment and the Quality Jobs program.

    Comes to the community
  3. Money for schools and services

    Meta has committed more than $200 million to local infrastructure including roads and water systems, and has put more than $1 million directly into Richland Parish since 2024.

    Comes from the community
  4. Electricity bill

    Meta is paying the full cost of the infrastructure needed to serve the campus under its Entergy agreement, and Entergy states other customers’ bills will be lower than they otherwise would have been.

    Comes from the community
  5. Jobs

    LED’s July 2026 expansion release expects 7,500 construction jobs at peak and about 1,000 operational jobs, up from 500 or more direct jobs in the 2024 announcement.

    Comes from the community

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Richland Parish, Louisiana.See every project on the map

The land, to scale

One football field
2,250 acres, about 1,702 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Meta Richland Parish Data CenterUnder construction

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Louisiana SB 79: Adds data centers to industrial purposes for local agreements

    The act counts the construction and operation of data centers as industrial purposes, and this project is a data center in Louisiana on record, so every condition the text sets is met by a fact on record.

    “"Industrial purposes" shall include the construction and operation of data centers and commercial operations directly related thereto.” (Enrolled text, Section 1, amending R.S. 33:130.12)

    Rule checks: Project is in Louisiana. Still to check: who it covers: not checked

Bills and laws in Louisiana

Open Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 2,260 MW · Entergy Louisiana generation build (LPSC Docket U-37425)Dec 2024 · generator_capacity
  • 5,000 MW · Full campus expansion (announced Jul 2026)Jul 2026 · it_load
  • 5,000 MW · Full campus expansion (announced Jul 2026)Jul 2026 · what the figure measures is not stated

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Meta Richland Parish Data Center?
    Meta Richland Parish Data Center is a data center project in Richland Parish, Louisiana.
    Who operates Meta Richland Parish Data Center?
    Meta is named as the operator of Meta Richland Parish Data Center.
    How big is Meta Richland Parish Data Center?
    Meta Richland Parish Data Center was announced at 5,000 MW of capacity. The site covers 2,250 acres.
    What stage is Meta Richland Parish Data Center?
    Meta Richland Parish Data Center is under construction. It was first public in 2024.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Meta Selects Northeast Louisiana as Site of $10 Billion Artificial Intelligence-Optimized Data Center
      Louisiana Economic Development / Office of the Governor
      Tier 1 · Captured 2026-11-08 · Open the source
    2. 2
      Deepening Our Investment in Richland Parish, Louisiana
      Meta Data Centers
      Tier 4 · Captured 2026-11-08 · Open the source
    3. 3
      Meta Commits More Than $50 Billion for North Louisiana Project
      Louisiana Economic Development
      Tier 1 · Captured 2026-11-08 · Open the source
    4. 4
      Entergy Louisiana to Power Meta's Data Center in Richland Parish
      Entergy Louisiana (via PR Newswire)
      Tier 4 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page