Meta data center, Tulsa (Project Anthem)

Tulsa,Tulsa County,OklahomaUnder constructionFirst public 2026Last checked Nov 8, 2026

MetaDeveloper and operatorFortis ConstructionBuilder

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: First public date
  • Still to confirm: Capacity
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Meta data center, Tulsa (Project Anthem) is a under-construction data center project in Tulsa, Tulsa County, Oklahoma. Meta is named as operator. It was first public in 2026. No site capacity figure is published for this project.

Meta data center, Tulsa (Project Anthem) is an under-construction data center project in Tulsa, Tulsa County, Oklahoma. Meta is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Tulsa, Tulsa County, Oklahoma. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Tulsa County, Oklahoma.See every project on the map

The land, to scale

One football field
340 acres, about 257 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Meta data center, Tulsa (Project Anthem)Under construction

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Oklahoma SB 259: Restricts groundwater cooling permits for data centers

    The act covers data processing facilities and data centers that use groundwater for cooling, whose groundwater permits may issue only for closed-loop, dielectric immersion, or comparably low-consumptive cooling technologies; this project has no capacity figure on record, but whether this project uses groundwater for cooling and which cooling technology it uses is not on record.

    “Using groundwater for cooling purposes at a data processing facility or data center through open-air evaporative cooling systems or any other cooling technology that consumes groundwater through evaporation or discharge without recirculation. Groundwater permits for such facilities shall only be issued if the applicant demonstrates that the cooling system utilizes closed-loop, dielectric immersion, or other comparably low-consumptive cooling technologies that substantially recirculate groundwater and minimize consumptive loss as determined by the Board” (Enrolled text, amended 82 O.S. Section 1020.15, permitting exclusions list, item 11)

    Rule checks: Project is in Oklahoma. Still to check: dates: not checked, who it covers: not checked

Bills and laws in Oklahoma

All 10 in Bill Watch

Who's involved

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Meta data center, Tulsa (Project Anthem)?
    Meta data center, Tulsa (Project Anthem) is a data center project in Tulsa, Tulsa County, Oklahoma.
    Who operates Meta data center, Tulsa (Project Anthem)?
    Meta is named as the operator of Meta data center, Tulsa (Project Anthem).
    How big is Meta data center, Tulsa (Project Anthem)?
    The site covers 340 acres.
    What stage is Meta data center, Tulsa (Project Anthem)?
    Meta data center, Tulsa (Project Anthem) is under construction. It was first public in 2026.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Project Anthem: Meta Breaks Ground on $1B AI Data Center in Tulsa
      Construction Review
      Tier 3 · Captured 2026-11-08 · Open the source
    2. 2
      Where are data centers being built across Oklahoma?
      News 9 (KWTV)
      Tier 3 · Captured 2026-11-08 · Open the source