Meta Beaver Dam Data Center
Beaver Dam,Dodge County,WisconsinUnder constructionFirst public 2025Filing entity: Degas LLCLast checked Nov 8, 2026
MetaDeveloper and operatorBalloonist LLCDeveloperMortensonBuilder
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: First public date
- Still to confirm: Capacity
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Meta Beaver Dam Data Center is a under-construction data center project in Beaver Dam, Dodge County, Wisconsin. Meta is named as operator. It was first public in 2025. No site capacity figure is published for this project.
Meta Beaver Dam Data Center is an under-construction data center project in Beaver Dam, Dodge County, Wisconsin. Meta is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Beaver Dam, Dodge County, Wisconsin. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · New projectFirst public record of Meta Beaver Dam Data CenterUnder construction
Bills and laws in Wisconsin
- SB 241 · Died or failed · Mar 23, 2026Tax incremental districts containing qualified data centers
- SB 843 · Died or failed · Mar 23, 2026Cost, water, and bonding requirements for data centers
- SB 244 · Died or failed · Mar 23, 2026Changes to the sales tax exemption for qualified data centers
- AB 245 · Died or failed · Mar 23, 2026Changes to the sales tax exemption for qualified data centers
- AB 840 · Died or failed · Mar 23, 2026Cost, water, and bonding requirements for data centers
- SB 969 · Died or failed · Mar 23, 2026Bans NDAs that conceal data center information from the public
Who's involved
- Developer and operatorMeta
- DeveloperBalloonist LLC
- BuilderMortenson
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Meta Beaver Dam Data Center?
- Meta Beaver Dam Data Center is a data center project in Beaver Dam, Dodge County, Wisconsin.
- Who operates Meta Beaver Dam Data Center?
- Meta is named as the operator of Meta Beaver Dam Data Center.
- What stage is Meta Beaver Dam Data Center?
- Meta Beaver Dam Data Center is under construction. It was first public in 2025.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Hello, Beaver Dam!
Meta Data Centers (datacenters.atmeta.com)Tier 4 · Captured 2026-11-08 · Open the source - 2Meta announces $1 billion Data Center Investment in Beaver Dam, Wisconsin Project
Alliant EnergyTier 4 · Captured 2026-11-08 · Open the source - 3Meta Hid Behind 'Balloonist LLC' to Plan a $1.6bn Datacenter in Menomonie (summary of The Guardian's investigation)
The Dingo Daily (summarizing The Guardian)Tier 3 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page