Skip to content

Project File

LightEdge Chaska data center

Chaska,Carver County,MinnesotaOperatingFiling entity: LightEdge Solutions, Inc.Last checked Nov 8, 2026

Stream Data CentersDeveloperLightEdgeOperator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Still to confirm: Electric utility
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

LightEdge Chaska data center is an operating data center project in Chaska, Carver County, Minnesota. LightEdge is named as operator. It was announced at 3.6 MW.

LightEdge Chaska data center is an operating data center project in Chaska, Carver County, Minnesota. LightEdge is named as operator. It was announced at 3.6 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Chaska, Carver County, Minnesota. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

4 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Aerial view of LightEdge Chaska data center in Chaska, Carver County, Minnesota, captured 2021
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2021Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Carver County, Minnesota.See every project on the map

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Minnesota HF 9: Tax bill ending the sales tax exemption on data center electricity

    The act covers qualified data centers and qualified refurbished data centers, whose purchases of enterprise information technology equipment and computer software for use in the center are exempt; this project has 3.6 MW on record (IT load), but whether this project is a qualified data center or a qualified refurbished data center under Minnesota Statutes Sec. 297A.68, subdivision 42 is not on record.

    “Purchases of enterprise information technology equipment and computer software for use in a qualified data center, or a qualified refurbished data center, are exempt, except that computer software maintenance agreements are exempt for purchases made after June 30, 2013.” (Section 4, amending Minnesota Statutes section 297A.68, subdivision 42 (a))

    Rule checks: Project is in Minnesota. Still to check: dates: not checked, who it covers: not checked

Bills and laws in Minnesota

All 17 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 3.6 MW · it_load

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is LightEdge Chaska data center?
    LightEdge Chaska data center is a data center project in Chaska, Carver County, Minnesota.
    Who operates LightEdge Chaska data center?
    LightEdge is named as the operator of LightEdge Chaska data center.
    How big is LightEdge Chaska data center?
    LightEdge Chaska data center was announced at 3.6 MW of capacity.
    What stage is LightEdge Chaska data center?
    LightEdge Chaska data center is operating.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      GI Partners' LightEdge acquires Stream DC data center in Minneapolis, Minnesota
      DataCenterDynamics
      Tier 3 · Captured 2026-11-08 · Open the source
    2. 2
      LightEdge Acquires Top-Tier High Density Data Center in Minneapolis
      LightEdge (release republished by CIOReview)
      Tier 4 · Captured 2026-11-08 · Open the source
    3. 3
      Data Center Specifications: Minnesota
      LightEdge
      Tier 4 · Captured 2026-11-14 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page