Hut 8 River Bend Campus

West Feliciana Parish,LouisianaUnder constructionFirst public 2025Last checked Nov 13, 2026

Hut 8Developer and operatorJacobsBuilderEntergy LouisianaElectric utilityFluidstackEnd user

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: City or address
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Hut 8 River Bend Campus is a under-construction data center project in West Feliciana Parish, Louisiana. Hut 8 is named as operator. It was first public in 2025. It was announced at 245 MW.

Hut 8 River Bend Campus is an under-construction data center project in West Feliciana Parish, Louisiana. Hut 8 is named as operator. It was announced at 245 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in West Feliciana Parish, Louisiana. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

245 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows West Feliciana Parish, Louisiana.See every project on the map

Timeline

  1. · New projectFirst public record of Hut 8 River Bend CampusUnder construction

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Louisiana SB 79: Adds data centers to industrial purposes for local agreements

    The act counts the construction and operation of data centers as industrial purposes, and this project is a data center in Louisiana on record, so every condition the text sets is met by a fact on record.

    “"Industrial purposes" shall include the construction and operation of data centers and commercial operations directly related thereto.” (Enrolled text, Section 1, amending R.S. 33:130.12)

    Rule checks: Project is in Louisiana. Still to check: who it covers: not checked

Bills and laws in Louisiana

Open Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 330 MW · Initial utility capacity (Entergy Louisiana)Dec 2025 · grid connection
  • 245 MW · Initial lease (Fluidstack)Dec 2025 · it_load

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Hut 8 River Bend Campus?
    Hut 8 River Bend Campus is a data center project in West Feliciana Parish, Louisiana.
    Who operates Hut 8 River Bend Campus?
    Hut 8 is named as the operator of Hut 8 River Bend Campus.
    How big is Hut 8 River Bend Campus?
    Hut 8 River Bend Campus was announced at 245 MW of capacity.
    What stage is Hut 8 River Bend Campus?
    Hut 8 River Bend Campus is under construction. It was first public in 2025.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Hut 8 Signs 15-Year, 245 MW AI Data Center Lease at River Bend Campus with Total Contract Value of USD $7.0 Billion
      Hut 8 Corp.
      Tier 4 · Captured 2026-11-08 · Open the source