Project File
FirstLight Manchester Data Center
Manchester,Hillsborough County,New HampshireOperatingFiling entity: FirstLight Fiber, Inc.Last checked Nov 8, 2026
FirstLightOperator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Still to confirm: Capacity
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
FirstLight Manchester Data Center is an operating data center project in Manchester, Hillsborough County, New Hampshire. FirstLight is named as operator. No site capacity figure is published for this project.
FirstLight Manchester Data Center is an operating data center project in Manchester, Hillsborough County, New Hampshire. FirstLight is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Manchester, Hillsborough County, New Hampshire. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026New Hampshire HB 672: Lets large users buy power from off-grid providers
The act exempts an off-grid electricity provider, one not connected to any existing electric transmission or distribution system in the state for primary or backup supply, from RSA Title XXXIV when it begins operations on or after August 1, 2025; this project is an operating colocation data center in Hillsborough County, and whether it takes service from an off-grid electricity provider is not on record.
“"Off-grid electricity provider" means an entity, person, private company, electric cooperative, municipal agency, or otherwise, that engages in any combination of generating, transmitting, distributing, or selling electricity at retail to consumers; is not connected to any existing electric transmission or distribution system within the state for either primary or backup supply, operates independently of existing utilities and other regulated entities, is not located within or crosses any federal, state, or municipal roadway or right-of-way, or crosses state boundaries.” (Chapter 285, section 285:1 (new RSA 374:3-c, paragraph I(a)))
Rule checks: Project is in New Hampshire. Still to check: who it covers: not checked
Bills and laws in New Hampshire
- HB 672 · In effect · Aug 1, 2025Lets large users buy power from off-grid providers
Who's involved
- OperatorFirstLight
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is FirstLight Manchester Data Center?
- FirstLight Manchester Data Center is a data center project in Manchester, Hillsborough County, New Hampshire.
- Who operates FirstLight Manchester Data Center?
- FirstLight is named as the operator of FirstLight Manchester Data Center.
- What stage is FirstLight Manchester Data Center?
- FirstLight Manchester Data Center is operating.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1FirstLight Data Center - Manchester, NH Specifications
FirstLight Fiber, Inc.Tier 4 · Captured 2026-11-08 · Open the source - 2U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source - 3EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page