Project File
CloudHQ Chaska campus (MSP1)
Chaska,Carver County,MinnesotaUnder constructionFirst public 2022Filing entity: CloudHQLast checked Nov 8, 2026
CloudHQDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
CloudHQ Chaska campus (MSP1) is a under-construction data center project in Chaska, Carver County, Minnesota. CloudHQ is named as operator. It was first public in 2022. No site capacity figure is published for this project.
CloudHQ Chaska campus (MSP1) is an under-construction data center project in Chaska, Carver County, Minnesota. CloudHQ is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Chaska, Carver County, Minnesota. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of CloudHQ Chaska campus (MSP1)Under construction
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Minnesota HF 9: Tax bill ending the sales tax exemption on data center electricity
The act covers qualified data centers and qualified refurbished data centers, whose purchases of enterprise information technology equipment and computer software for use in the center are exempt; this project has 180 MW on record (not stated), but whether this project is a qualified data center or a qualified refurbished data center under Minnesota Statutes Sec. 297A.68, subdivision 42 is not on record.
“Purchases of enterprise information technology equipment and computer software for use in a qualified data center, or a qualified refurbished data center, are exempt, except that computer software maintenance agreements are exempt for purchases made after June 30, 2013.” (Section 4, amending Minnesota Statutes section 297A.68, subdivision 42 (a))
Rule checks: Project is in Minnesota. Still to check: dates: not checked, who it covers: not checked
Bills and laws in Minnesota
- SF 4203 · Died or failedChanges to the data center sales and use tax exemption
- SF 4681 · Died or failedData center exemptions and provisions modified
- HF 2928 · Died or failedWater, environmental review, and energy rules for data centers
- SF 4298 · Died or failedMoratorium on new data centers; utility commission report
- HF 4153 · Died or failedWater criteria and tax exemptions for data centers
- SF 5231 · Died or failedRepeals the data center sales and use tax exemption
Who's involved
- Developer and operatorCloudHQ
Power
Capacity, as announced or filed
- 180 MW · Full campus as presented to the City CouncilJan 2022 · what the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is CloudHQ Chaska campus (MSP1)?
- CloudHQ Chaska campus (MSP1) is a data center project in Chaska, Carver County, Minnesota.
- Who operates CloudHQ Chaska campus (MSP1)?
- CloudHQ is named as the operator of CloudHQ Chaska campus (MSP1).
- How big is CloudHQ Chaska campus (MSP1)?
- The site covers 72 acres.
- What stage is CloudHQ Chaska campus (MSP1)?
- CloudHQ Chaska campus (MSP1) is under construction. It was first public in 2022.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1CloudHQ planning 180MW data center campus in Minneapolis, Minnesota
DataCenterDynamicsTier 3 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page