Project File
Applied Digital Delta Forge 1
Boyce,Rapides Parish,LouisianaUnder constructionFirst public 2026Last checked Nov 8, 2026
Applied DigitalDeveloper and operatorClecoElectric utility
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Applied Digital Delta Forge 1 is a under-construction data center project in Boyce, Rapides Parish, Louisiana. Applied Digital is named as operator. It was first public in 2026. It was announced at 430 MW.
Applied Digital Delta Forge 1 is an under-construction data center project in Boyce, Rapides Parish, Louisiana. Applied Digital is named as operator. It was announced at 430 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Boyce, Rapides Parish, Louisiana. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Applied Digital Delta Forge 1Under construction
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Louisiana SB 79: Adds data centers to industrial purposes for local agreements
The act counts the construction and operation of data centers as industrial purposes, and this project is a data center in Louisiana on record, so every condition the text sets is met by a fact on record.
“"Industrial purposes" shall include the construction and operation of data centers and commercial operations directly related thereto.” (Enrolled text, Section 1, amending R.S. 33:130.12)
Rule checks: Project is in Louisiana. Still to check: who it covers: not checked
Bills and laws in Louisiana
- EO 26-058 · In effect · Jun 25, 2026Sets ratepayer and community conditions data centers must meet for the state sales tax exemption
- SB 490 · Died or failed · May 18, 2026Lets private power networks serve data centers off the grid
- HB 1206 · Died or failed · Apr 28, 2026Requires permits and reporting for large data center water use
- HB 922 · Died or failed · Mar 9, 2026Bars household rate increases caused by data center demand
- SB 79 · Signed into law · Jun 4, 2025Adds data centers to industrial purposes for local agreements
Who's involved
- Developer and operatorApplied Digital
- Electric utilityCleco
Power
Capacity, as announced or filed
- 430 MW · Initial build (two facilities)Jan 2026 · grid connection
- 300 MW · Initial build (two facilities)Jan 2026 · it_load
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Applied Digital Delta Forge 1?
- Applied Digital Delta Forge 1 is a data center project in Boyce, Rapides Parish, Louisiana.
- Who operates Applied Digital Delta Forge 1?
- Applied Digital is named as the operator of Applied Digital Delta Forge 1.
- How big is Applied Digital Delta Forge 1?
- Applied Digital Delta Forge 1 was announced at 430 MW of capacity. The site covers 500 acres.
- What stage is Applied Digital Delta Forge 1?
- Applied Digital Delta Forge 1 is under construction. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Applied Digital Breaks Ground on Delta Forge 1, a 430 MW AI Factory Campus in a Southern U.S. State
Applied Digital Corporation (GlobeNewswire)Tier 4 · Captured 2026-11-08 · Open the source - 2Central Louisiana Secures $3.6 Billion Applied Digital AI Factory Campus
Louisiana Economic DevelopmentTier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page