Project File

Amazon Web Services Clinton Data Center

Clinton,Hinds County,MississippiUnder constructionFirst public 2026Last checked Nov 8, 2026

AmazonDeveloper and operatorEntergy MississippiElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: Capacity
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Amazon Web Services Clinton Data Center is a under-construction data center project in Clinton, Hinds County, Mississippi. Amazon is named as operator. It was first public in 2026. No site capacity figure is published for this project.

Amazon Web Services Clinton Data Center is an under-construction data center project in Clinton, Hinds County, Mississippi. Amazon is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Clinton, Hinds County, Mississippi. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Hinds County, Mississippi.See every project on the map

Timeline

  1. · New projectFirst public record of Amazon Web Services Clinton Data CenterUnder construction

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Mississippi HB 1393: Creates an energy infrastructure fund open to data center projects

    The act covers approved projects, including data centers, for which the Mississippi Energy Infrastructure Fund may give grants, loans, or other financial assistance to local entities; this project has no capacity figure on record, but whether the authority has approved this project is not on record.

    “The authority shall establish a program to make grants, loans or provide any other financial assistance as determined by the authority from the Mississippi Energy Infrastructure Fund to local entities to construct, equip an approved project or otherwise provide facilities related to the approved project.” (Senate amendment text to HB 1393, Section 57-39-39)

    Rule checks: Project is in Mississippi. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Mississippi SB 3410: Lets Brandon contract with a data center for water infrastructure

    The act authorizes contracts only between a data center developer or operator and the City of Brandon or the West Rankin Utility Authority, and this project is in Hinds County, outside the city and the authority area the act names, so the text does not reach it.

    “the governing body and the board, in their discretion, are authorized to jointly or independently enter into one or more contracts or agreements with a developer or operator of a data center or related technology facility, and with each other, for the planning, design, construction, installation, operation, and maintenance of water and wastewater infrastructure, including, but not limited to, pipelines, pump stations, and related appurtenances, where such developer or operator agrees to reimburse the city and/or the authority, from the developer's or operator's own funds on a progress payment basis” (Enrolled text, Section 2)

    Rule checks: Project is in Mississippi. Still to check: who it covers: not checked

Bills and laws in Mississippi

All 7 in Bill Watch

Who's involved

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Amazon Web Services Clinton Data Center?
    Amazon Web Services Clinton Data Center is a data center project in Clinton, Hinds County, Mississippi.
    Who operates Amazon Web Services Clinton Data Center?
    Amazon is named as the operator of Amazon Web Services Clinton Data Center.
    What stage is Amazon Web Services Clinton Data Center?
    Amazon Web Services Clinton Data Center is under construction. It was first public in 2026.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Amazon's Data Center Investments in Mississippi (fact sheet)
      Amazon
      Tier 4 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page