WisconsinAssembly2025-2026 LegislatureBill
AB 722: Wage, renewable energy, and fee rules for large data centers
Official title: Relating to: large energy customer fees; electric utility very large customer class; a renewable resource tariff; building requirements for data centers; water usage by large customers; required pay rate on large-scale data center projects; and granting rule-making authority.
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Died or failed as of Mar 23, 2026. The official record says: Failed to pass pursuant to Senate Joint Resolution 1.
- Filed (done)
- In committee (not reached)
- Passed one chamber (not reached)
- Passed both chambers (not reached)
- Signed into law (not reached)
- In effect (not reached)
- Died or failed (current stage)
What it does
We have not quoted its provisions yet. The official text has them.
Who it touches
No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.
Other projects we track in Wisconsin (8), not affected
- Balloonist LLC Menomonie data centerPaused
- Meta Beaver Dam Data CenterUnder construction
- Microsoft Caledonia data centerCancelled
- Microsoft Kenosha data center siteProposed
- Microsoft Mount Pleasant data center campus (Fairwater)Expanding
- QTS DeForest / Vienna data center campusCancelled
- Vantage Data Centers Port Washington Campus (Port Washington)Operating
- Vantage Lighthouse campus (Stargate Port Washington)Under construction
Who acted
- SponsorRepresentative Stroud
More from Wisconsin
- SB 1061 · Died or failedMoratorium on operating data centers until state safeguards are in law
- AB 1099 · Died or failedMoratorium on operating data centers until state safeguards are in law
- SB 729 · Died or failedWage, renewable energy, and fee rules for large data centers
- SB 843 · Died or failedCost, water, and bonding requirements for data centers
- SB 241 · Died or failedTax incremental districts containing qualified data centers
- AB 228 · Died or failedTax incremental districts containing qualified data centers
Sources
- 1AB 722 (2025-2026 Legislature), introduced text (proposal page)
Wisconsin LegislatureTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "AB 722: Wage, renewable energy, and fee rules for large data centers." Bill Watch. Updated 2026-11-13. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/wi-2025-26-ab722
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page