MontanaHouse of Representatives69th Legislature, 2025 Regular SessionBill

HB 424: Extends low property tax class for data centers and power plants

Official title: Revise taxes for class 17 data center property

Official text

Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.

Where it stands

In effect as of May 13, 2025. The official record says: Signed by Governor May 13, 2025; chapter assigned May 19, 2025.

  1. Filed (done)
  2. In committee (done)
  3. Passed one chamber (done)
  4. Passed both chambers (done)
  5. Signed into law (done)
  6. In effect (current stage)

What it does

  • Definition

    Applies to: Qualified data centers (class seventeen property) (Montana)

    Starts: 2025-05-13.

    “"Qualified data center" means the land, improvements, and personal property of a facility designed or modified to house networked computers or equipment supporting computing, networking, or data storage…”

    MCA 15-6-162(2)(a), as amended by the bill's authorized print version

  • Tax exemption

    Applies to: Class seventeen data center property, including associated generation (Montana)

    Starts: 2025-05-13.

    “AN ACT REVISING PROPERTY INCLUDED IN CLASS SEVENTEEN AS DATA CENTER PROPERTY; EXTENDING THE TIMEFRAME IN WHICH THE DATA CENTER PROPERTY MUST BE BUILT…”

    Act title, authorized print version

Who it touches (4)

Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Atlas Power Butte Data Center

    The act covers qualified data centers, facilities under single ownership on contiguous parcels that meet the act's building area and total cost floors, at least 300,000 square feet and $150 million, or 25,000 square feet of new or expanded area and $50 million invested in a 48-month period, with construction commencing after the stated dates; this project has 75 MW on record (grid connection), but the project's building area, total cost, and ownership structure is not on record.

    “"Qualified data center" means the land, improvements, and personal property of a facility designed or modified to house networked computers or equipment supporting computing, networking, or data storage” (MCA 15-6-162(2)(a), as amended by the bill's authorized print version)

    Rule checks: Project is in Montana. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Big Horn Data Hub (MARA Hardin)

    The act covers qualified data centers, facilities under single ownership on contiguous parcels that meet the act's building area and total cost floors, at least 300,000 square feet and $150 million, or 25,000 square feet of new or expanded area and $50 million invested in a 48-month period, with construction commencing after the stated dates; this project has no capacity figure on record, but the project's building area, total cost, and ownership structure is not on record.

    “"Qualified data center" means the land, improvements, and personal property of a facility designed or modified to house networked computers or equipment supporting computing, networking, or data storage” (MCA 15-6-162(2)(a), as amended by the bill's authorized print version)

    Rule checks: Project is in Montana. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Quantica Big Sky Campus

    The act covers qualified data centers, facilities under single ownership on contiguous parcels that meet the act's building area and total cost floors, at least 300,000 square feet and $150 million, or 25,000 square feet of new or expanded area and $50 million invested in a 48-month period, with construction commencing after the stated dates; this project has 500 MW on record (not stated), but the project's building area, total cost, and ownership structure is not on record.

    “"Qualified data center" means the land, improvements, and personal property of a facility designed or modified to house networked computers or equipment supporting computing, networking, or data storage” (MCA 15-6-162(2)(a), as amended by the bill's authorized print version)

    Rule checks: Project is in Montana. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Sabey Butte Data Center Campus

    The act covers qualified data centers, facilities under single ownership on contiguous parcels that meet the act's building area and total cost floors, at least 300,000 square feet and $150 million, or 25,000 square feet of new or expanded area and $50 million invested in a 48-month period, with construction commencing after the stated dates; this project has 250 MW on record (not stated), but the project's building area, total cost, and ownership structure is not on record.

    “"Qualified data center" means the land, improvements, and personal property of a facility designed or modified to house networked computers or equipment supporting computing, networking, or data storage” (MCA 15-6-162(2)(a), as amended by the bill's authorized print version)

    Rule checks: Project is in Montana. Still to check: dates: not checked, who it covers: not checked

Who acted

  • Primary sponsorK. ZolnikovHouse
  • SponsorD. FernHouse
  • SponsorD. HarveyHouse
  • SponsorG. HertzHouse
  • SponsorK. BognerHouse
  • SponsorM. BertoglioHouse
  • SponsorM. RegierHouse
  • SponsorS. FitzpatrickHouse

Timeline

Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.

  1. · HousePassed the HouseStage: Passed one chamber
  2. · GovernorSigned by GovernorStage: Signed into law

More from Montana

Sources

  1. 1
    HB 424 (2025) - Authorized print version (69th Legislature)
    Montana Legislature
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "HB 424: Extends low property tax class for data centers and power plants." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/mt-2025-hb-424

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page