Cases and proceedings

  1. Utility commissionDecidedLarge loads

    Northern States Power Company (Xcel Energy) very large customer tariff under Minn. Stat. 216B.1622

    Minnesota Public Utilities Commission · Docket 25-289 · Xcel Energy (Northern States Power Company, Minnesota) · Minnesota

  2. Utility commissionDecidedLarge loads

    Dakota Electric Association, modified Extension of Service Tariff for extraordinarily large and system-intensive members

    Minnesota Public Utilities Commission · Docket 25-178 · Dakota Electric Association · Minnesota

  3. Utility commissionPending before the commissionLarge loads

    Dakota Electric Association, proposed Very Large Member Contract Rate Service tariff

    Minnesota Public Utilities Commission · Docket 26-243 · Dakota Electric Association · Minnesota

  4. Utility commissionPending before the commissionLarge loads

    Minnesota Power petition for a very large customer tariff under Minn. Stat. 216B.1622

    Minnesota Public Utilities Commission · Docket 26-126 · Minnesota Power · Minnesota

  5. Utility commissionPending before the commissionLarge loads

    Otter Tail Power Company petition for a very large customer class and a data center rate schedule

    Minnesota Public Utilities Commission · Docket 26-211 · Otter Tail Power Company · Minnesota

Sources on this page

  1. 1
    Very large electric customers and the PUC process
    Minnesota Public Utilities Commission
    Tier 1 · Draft research, not yet verified · Open the source
  2. 2
    Data Centers to Pay Fair Share: PUC enacts protections for Xcel customers
    Citizens Utility Board of Minnesota
    Tier 4 · Draft research, not yet verified · Open the source