Utility commission
Alabama Power 2025 Integrated Resource Plan (summary report filed with the Commission)
Where it stands: Pending before the commission
Draft research, not yet verified. Open a source to check any detail.
What it is
Alabama Power's long-term load forecast treats data centers as the driver of new large load growth: 'anticipated additions of large load customers (e.g., data centers) are forecasted to drive an overall increase in Commercial class electricity consumption' over the forecast horizon. The all-load peak forecast grows slowly (average annual summer peak growth about 0.10 percent 2025-2030; winter about 0.19 percent) because data center and other large load additions sit inside a largely flat residential and commercial base. These are system forecast figures, not any project's capacity, and no data-center-only megawatt figure is published in the summary report.
The facts
- Regulator
- Alabama Public Service Commission
- Type
- Other
- State
- Alabama
- Filed
- Jan 1, 2025
- Large-load rules
- Yes
Related cases and proceedings
- Utility commission · DecidedGeneric Proceeding to Establish a Process for Consideration of Contracts for Electric Service Between Alabama Power Company and Large Load Data Center Customers
- Utility commission · Pending before the commissionAlabama Power contracts for electric service with large load data center customers filed under Rate FCR during the Docket 33709 interim process (Dotier, LLC; Alabama ADC Holdings, LLC; Woostor, LLC and APLD BHM-01 LLC)
- Court case · PendingJohnson Contractors, Inc. v. Starbelt, LLC et al.
In the record
- Utility case, 2025. Utility case filed: Alabama Power 2025 Integrated Resource Plan (summary report filed with the Commission) Alabama Public Service Commission
Sources
- 12025 Integrated Resource Plan, Summary Report
Alabama Power CompanyTier 2 · 2025 IRP Summary Report, Section IV.B Load Forecast (pp. 16-18): large load / data center passage at p. 16; peak demand forecast discussion and growth rates at pp. 17-18 · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Alabama Power 2025 Integrated Resource Plan (summary report filed with the Commission)." Last activity 2025-01-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-alabama-power-irp-2025