Utility commission
Generic Proceeding to Establish a Process for Consideration of Contracts for Electric Service Between Alabama Power Company and Large Load Data Center Customers
Where it stands: Decided as of Oct 19, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
The Commission adopted a contract review process for Alabama Power contracts with data center customers at 150 MW or more, under Act 610 (Alabama Code Section 37-4-22.1). Contract prices must not be below the company incremental cost of serving the premises and must be expected to promote positive benefits to other retail customers. Alabama Power files a public petition naming the customer and its parent entities, the county or municipality, and the maximum contract capacity, and makes a confidential submission of the full contract and its cost analysis to the Commission Legal Division and the Attorney General. The Commission votes to approve or disapprove; if it does not vote within 90 days of the petition filing, the contract is deemed approved. The petition is filed at least 120 days before the date the contract would become void without Commission approval. The order sets no minimum contract term, minimum billing demand, collateral, or exit fee; the Commission reviews those terms contract by contract. The order directed Alabama Power to file a tariff reflecting the process within 10 days; Rate FCR-LLDC was filed October 21, 2026 and takes effect November 23, 2026.
The facts
- Regulator
- Alabama Public Service Commission
- Docket number
- 33709
- Type
- Large load tariff
- State
- Alabama
- Filed
- Jul 8, 2026
- Status date
- Oct 19, 2026
- Large-load rules
- Yes, for loads of 150 MW or more
Related cases and proceedings
- Utility commission · Pending before the commissionAlabama Power contracts for electric service with large load data center customers filed under Rate FCR during the Docket 33709 interim process (Dotier, LLC; Alabama ADC Holdings, LLC; Woostor, LLC and APLD BHM-01 LLC)
- Utility commission · Pending before the commissionAlabama Power 2025 Integrated Resource Plan (summary report filed with the Commission)
- Court case · PendingJohnson Contractors, Inc. v. Starbelt, LLC et al.
In the record
- Utility case, Jul 8, 2026. Utility case filed: Generic Proceeding to Establish a Process for Consideration of Contracts for Electric Service Between Alabama Power Company and Large Load Data Center Customers Alabama Public Service Commission, 33709
Sources
- 1Order, Generic Proceeding to Establish a Process for Consideration of Contracts for Electric Service Between Alabama Power Company and Large Load Data Center Customers (Docket 33709)
Alabama Public Service CommissionTier 1 · Order, Docket 33709, signed October 19, 2026: Act 610 definition at pages 2 to 3 (150 MW or greater); contract terms discussion at pages 30 to 31 (no minimums set); adopted procedures at pages 35 to 36 (public petition, confidential submission, vote or deemed approval within 90 days, filing at least 120 days ahead, compliance tariff within 10 days); Rate FCR-LLDC filing, October 21, 2026, tariff pages 1 to 3 (150 MW applicability, review criteria, 90 day deemed approval, effective November 23, 2026) · Open the source - 2Rate FCR-LLDC, Flexible Contract Rate, Large Load Data Centers (filed in Docket 33709)
Alabama Power CompanyTier 1 · Order, Docket 33709, signed October 19, 2026: Act 610 definition at pages 2 to 3 (150 MW or greater); contract terms discussion at pages 30 to 31 (no minimums set); adopted procedures at pages 35 to 36 (public petition, confidential submission, vote or deemed approval within 90 days, filing at least 120 days ahead, compliance tariff within 10 days); Rate FCR-LLDC filing, October 21, 2026, tariff pages 1 to 3 (150 MW applicability, review criteria, 90 day deemed approval, effective November 23, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Generic Proceeding to Establish a Process for Consideration of Contracts for Electric Service Between Alabama Power Company and Large Load Data Center Customers." Last activity 2026-10-19. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-alabama-power-fcr-lldc-33709