Project File · Public records
Every public record we have for xAI Colossus (Memphis)
Memphis, Shelby County, TennesseeOperatingFirst public 2024Filing entity: CTC Property LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
1 of 10 records · showing land and zoning rules only ·
2026
Development ruleIn effectOct 20, 2026Memphis
135-day pause on new data center development with directions for permanent rules
Memphis paused new data center development for 135 days and directed its planning division to draft permanent Unified Development Code amendments for data centers within 90 days with council guidelines for the permanent rules; existing facilities are not stopped. The separate 18-month moratorium (Ordinance No. 5982) failed on a 6-6 tie the same night.
Ordinance No. 5986 (substitute adopted 2026-10-20)
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
City Council regular agenda for 2026-10-20 items 18 (Ordinance 5986 third and final reading) and 19 (Ordinance 5982 moratorium)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Velocity Meets Potency: xAI Announces Memphis as New Home (press release, June 5, 2024)
Greater Memphis ChamberTier 2 · Captured 2026-11-09 · Open the source - 22025 xAI Update (MLGW published briefing, May 2025)
Memphis Light, Gas and WaterTier 1 · Captured 2026-11-09 · Open the source - 3Minutes, Meeting of the City Council, City of Memphis, August 19, 2025
City of MemphisTier 1 · Captured 2026-11-09 · Open the source - 4Higher limits and a new compute partnership with SpaceX (Anthropic news post, May 6, 2026)
AnthropicTier 2 · Captured 2026-11-09 · Open the source - 5New Compute Partnership with Anthropic (xAI news post, May 6, 2026)
xAITier 2 · Captured 2026-11-09 · Open the source - 6xAI Phase One Substation #63 Providing 150MW of Power to Facility (press release, May 1, 2025)
Greater Memphis ChamberTier 2 · Captured 2026-11-09 · Open the source - 7TVA Board Resolution and Memorandum, Exhibit 11/07/24G: Greater than 100 MW firm power arrangement with CTC Property LLC (xAI)
Tennessee Valley AuthorityTier 1 · Captured 2026-11-09 · Open the source - 8Shelby County Commission resolution urging a public hearing before approval or denial of the permit submitted by CTC Property LLC (as amended in committee, March 25, 2025)
Shelby County CommissionTier 1 · Captured 2026-11-09 · Open the source - 9Memphis City Council regular agenda October 20 2026
City of MemphisTier 1 · Captured 2026-11-08 · Open the source - 10Electric Service Schedule TDC, Time of Use Data Service (rate effective October 1, 2026)
Memphis Light, Gas and Water Division, City of MemphisTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 11xAI - Greater Memphis Chamber (project page: Pidgeon Industrial Park, 552 acres, live 2024-08-08, about 300 MW)
Greater Memphis ChamberTier 1 · Captured 2026-11-08 · Open the source - 12xAI Colossus: the Memphis AI supercomputer explained (built from xAI, MLGW, and Chamber statements)
The Model PressTier 3 · Captured 2026-11-08 · Open the source - 13TVA Board Resolution (Power Availability), February 11, 2026, Exhibit 02/11/26E
Tennessee Valley AuthorityTier 1 · Captured 2026-11-09 · Open the source - 14Memphis City Council Regular Agenda, June 24, 2025 (council roster)
City of MemphisTier 1 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page