Project File · Public records
Every public record we have for xAI Colossus (Memphis)
Memphis, Shelby County, TennesseeOperatingFirst public 2024Filing entity: CTC Property LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
10 of 10 records
2026
Development ruleIn effectOct 20, 2026Memphis
135-day pause on new data center development with directions for permanent rules
Memphis paused new data center development for 135 days and directed its planning division to draft permanent Unified Development Code amendments for data centers within 90 days with council guidelines for the permanent rules; existing facilities are not stopped. The separate 18-month moratorium (Ordinance No. 5982) failed on a 6-6 tie the same night.
Ordinance No. 5986 (substitute adopted 2026-10-20)
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
City Council regular agenda for 2026-10-20 items 18 (Ordinance 5986 third and final reading) and 19 (Ordinance 5982 moratorium)
Public decisionFiledMay 6, 2026Anthropic; xAI
Anthropic; xAI
Announced agreement under which Anthropic will use all of the compute capacity at Colossus 1
- Compute capacity access announced:
- 300 MW
- Gpu count announced:
- 220,000 GPUs
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Anthropic news post and xAI news post, both May 6, 2026
2025
Public decisionApprovedAug 19, 2025City of Memphis
City of Memphis, Ordinance No. 5953
Ordinance providing for the allocation of lawfully available funds of the city, in an artificial intelligence property, to certain public purposes within those areas of the city affected by the development, use and operation of such property; approved on third and final reading, as amended
- Ordinance subject:
- Allocation of lawfully available funds of the city, in an artificial intelligence property, to certain public purposes within those areas of the city affected by the development, use and operation of such property
- Final passage vote:
- Approved on third and final reading, as amended, with 11 ayes printed (Carlisle, Cooper-Sutton, Easter-Thomas, Green, Smiley, Spinosa, Swearengen-Washington, Walker, Warren, White, Chairman Canale); Ford did not cast a vote; Logan absent; no nays printed
- Amendment vote:
- Walker amendment to item 20 approved with 12 ayes printed (Carlisle, Cooper-Sutton, Easter-Thomas, Ford, Green, Smiley, Spinosa, Swearengen-Washington, Walker, Warren, White, Chairman Canale); Logan absent
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes of the Memphis City Council, August 19, 2025, item 20 (Ordinance No. 5953, sponsored by the Administration)
Recorded voteAug 19, 2025Memphis City Council
Ordinance No. 5953: allocation of lawfully available funds of the city, in an artificial intelligence property, to certain public purposes within the areas affected (third and final reading, as amended)
11 yes, 1 abstain, 1 absent. Chase Carlisle (Memphis City Councilmember): yes; Edmund Ford, Sr. (Memphis City Councilmember): abstain; Jana Swearengen-Washington (Memphis City Councilmember): yes; Janika White (Memphis City Councilmember): yes; JB Smiley, Jr. (Memphis City Councilmember): yes; Jeff Warren (Memphis City Councilmember): yes; Jerri Green (Memphis City Councilmember): yes; J. Ford Canale (Memphis City Council Chairman): yes; Michalyn Easter-Thomas (Memphis City Councilmember): yes; Pearl Eva Walker (Memphis City Councilmember): yes; Philip Spinosa (Memphis City Councilmember): yes; Rhonda Logan (Memphis City Councilmember): absent; Yolanda Cooper-Sutton (Memphis City Councilmember): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes of the Memphis City Council, August 19, 2025, item 20, final passage: "AYES: Carlisle, Cooper-Sutton, Easter-Thomas, Green, Smiley, Spinosa, Swearengen-Washington, Walker, Warren, White, and Chairman Canale. Ford did not cast a vote. Logan was absent. APPROVED, on Third and Final Reading, as amended"
Public decisionFiledMay 2, 2025Memphis Light, Gas and Water
Memphis Light, Gas and Water
- Recycled water plant capacity:
- 13 million_gallons_per_day
- Second increment status:
- Second 150 MW increment: studies complete and a second substation under construction at xAI expense; TVA Board decision then pending; MLGW projected delivery no later than December 2025
- Electric rate and curtailment:
- xAI pays the prevailing industrial rate and signed a curtailment agreement with TVA and MLGW for high-demand periods
- Total power requested:
- 300 MW
- Gas connection:
- Pre-existing 16-inch gas main serves the site; xAI paid for an 8-inch tap
- Facility history incentives:
- The former Electrolux plant on the site was built with a 2010 $97 million State of Tennessee grant and a $3.1 million state training grant, and carried a 15-year local property tax abatement of 75 percent
- Water connection:
- Connected to a pre-existing 20-inch water main on Paul Lowry Road; water billed at the prevailing commercial rate
- First increment delivery:
- 150 MW delivered: 8 MW from the existing substation plus 142 MW from a new substation, both built or upgraded at xAI expense; TVA Board approved
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
"2025 xAI Update" PDF, file metadata May 2, 2025; Paul Lowry Road (Colossus 1) sections
Public decisionFiledMay 1, 2025Greater Memphis Chamber
Greater Memphis Chamber
Announcement that Phase I reached full operational capability, with substation #63 delivering 150 MW of grid power
- Grid power delivered phase 1:
- 150 MW
- Battery storage integrated:
- 150 MW
- Temporary turbine status:
- Temporary gas turbines being demobilized over the two months after May 1, 2025; about half to remain for Phase II until substation #22 (planned fall 2025), then a backup role
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Press release, May 1, 2025, "xAI Phase One Substation #63 Providing 150MW of Power to Facility"
Public decisionApprovedMar 25, 2025Shelby County Commission
Shelby County Commission
Resolution urging the Shelby County Health Department and elected officials to host a public hearing, and to delay approval, before approving or denying the air permit submitted by CTC Property LLC for long-term operation of 15 methane gas turbines
- Air permit application:
- CTC Property LLC applied for permits to operate 15 methane gas turbines 24 hours a day, 7 days a week, to power its operations long-term; application submitted January 2025
- Hearing request:
- Resolution urges the Health Department to delay the permit approval process until a public hearing is held under the Tennessee Open Meetings Act, with public notice and an opportunity for public comment
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution text "as amended in Hospitals and Health Committee on 3.25.2025", Commission agenda document
2024
Public decisionApprovedNov 7, 2024Tennessee Valley Authority
Tennessee Valley Authority, Exhibit 11/07/24G
Approved 150 MW of firm power supply to the new MLGW end-use customer (CTC Property LLC, an xAI subsidiary), contingent on the customer's agreement to demand response terms
- Demand response condition:
- Approval contingent on the customer's agreement to certain demand response terms offered for similar customer loads
- Operating load august 2024:
- 50 MW
- Contract demand initial phase:
- 150 MW
- Earliest full power date:
- 2024-12-01
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Board resolution and memorandum, Exhibit 11/07/24G, November 7, 2024 meeting
Public decisionFiledJun 5, 2024Greater Memphis Chamber
Greater Memphis Chamber
Announcement that xAI would locate its "Gigafactory of Compute" supercomputer in Memphis, occupying a former manufacturing facility; the project was stated as pending approval by EDGE, TVA, and governing authorities
- Announced investment scale:
- Largest capital investment by a new-to-market company in Memphis history (Chamber characterization); described as multi-billion-dollar, no figure stated
- Approvals pending at announcement:
- Project stated as pending approval by the Memphis Shelby County Economic Development Growth Engine (EDGE), Tennessee Valley Authority, and governing authorities
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Press release dated June 5, 2024, "Velocity Meets Potency: xAI Announces Memphis as New Home"
No date in the record(rules in force and undated records)
Utility proceedingIn effectNo date in the recordMemphis Light, Gas and Water Division, City of Memphis
Electric Service Schedule TDC, Time of Use Data Service
Retail data service schedule carrying TVA’s wholesale structure, effective October 1, 2026. It applies to firm power where the major use is NAICS subsector 518 or 519 (excluding 519210), NAICS 522320 or 541214, or, in TVA’s sole judgment, the operation of computational equipment; the customer must certify eligibility to both MLGW and TVA, and TVA has unrestricted remote and physical access to metering. Classes are set by the higher of on-peak or off-peak contract demand: TDCA over 1,000 to 5,000 kW, TDCB over 5,000 to 15,000 kW, TDCC over 15,000 to 25,000 kW, TDCD over 25,000 kW. Monthly charges include a $2,000 service charge per delivery point and a $350 TVA administrative charge; summer on-peak demand at transmission voltage is $14.13 to $14.16 per kW by class. Billing demand floors run from 30 percent of the first 5,000 kW to 85 percent of demand above 350,000 kW, on the higher of contract demand or the prior 12 months’ maximum. No facilities rental charge at 161 kV or above; $0.38 per kW-month below 161 kV and $0.97 (first 10,000 kW) and $0.76 (excess) below 46 kV. Reactive charges are $1.81 per kVAR lagging excess and $1.42 per kVAR leading. Contracts: TDCA at least 1 year, TDCB to TDCD at least 5 years for the initial term and each renewal. Rates are subject to TVA’s monthly Fuel Cost and Purchased Power Adjustment Rider.
Draft research, not yet verifiedLast checked Nov 11, 2026Where it says this
Schedule TDC (4 pages): Availability and Customers Class Description (page 1: NAICS classes, certification, TDCA to TDCD bands); Determination of On-Peak and Off-Peak Demands (page 2: the 30 to 85 percent billing demand floors); Facilities Rental and Reactive Demand Charges (page 2); Contract Requirement (page 3: 1-year and 5-year terms); rate tables (pages 3-4: service and administrative charges, demand and energy charges)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Velocity Meets Potency: xAI Announces Memphis as New Home (press release, June 5, 2024)
Greater Memphis ChamberTier 2 · Captured 2026-11-09 · Open the source - 22025 xAI Update (MLGW published briefing, May 2025)
Memphis Light, Gas and WaterTier 1 · Captured 2026-11-09 · Open the source - 3Minutes, Meeting of the City Council, City of Memphis, August 19, 2025
City of MemphisTier 1 · Captured 2026-11-09 · Open the source - 4Higher limits and a new compute partnership with SpaceX (Anthropic news post, May 6, 2026)
AnthropicTier 2 · Captured 2026-11-09 · Open the source - 5New Compute Partnership with Anthropic (xAI news post, May 6, 2026)
xAITier 2 · Captured 2026-11-09 · Open the source - 6xAI Phase One Substation #63 Providing 150MW of Power to Facility (press release, May 1, 2025)
Greater Memphis ChamberTier 2 · Captured 2026-11-09 · Open the source - 7TVA Board Resolution and Memorandum, Exhibit 11/07/24G: Greater than 100 MW firm power arrangement with CTC Property LLC (xAI)
Tennessee Valley AuthorityTier 1 · Captured 2026-11-09 · Open the source - 8Shelby County Commission resolution urging a public hearing before approval or denial of the permit submitted by CTC Property LLC (as amended in committee, March 25, 2025)
Shelby County CommissionTier 1 · Captured 2026-11-09 · Open the source - 9Memphis City Council regular agenda October 20 2026
City of MemphisTier 1 · Captured 2026-11-08 · Open the source - 10Electric Service Schedule TDC, Time of Use Data Service (rate effective October 1, 2026)
Memphis Light, Gas and Water Division, City of MemphisTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 11xAI - Greater Memphis Chamber (project page: Pidgeon Industrial Park, 552 acres, live 2024-08-08, about 300 MW)
Greater Memphis ChamberTier 1 · Captured 2026-11-08 · Open the source - 12xAI Colossus: the Memphis AI supercomputer explained (built from xAI, MLGW, and Chamber statements)
The Model PressTier 3 · Captured 2026-11-08 · Open the source - 13TVA Board Resolution (Power Availability), February 11, 2026, Exhibit 02/11/26E
Tennessee Valley AuthorityTier 1 · Captured 2026-11-09 · Open the source - 14Memphis City Council Regular Agenda, June 24, 2025 (council roster)
City of MemphisTier 1 · Captured 2026-11-09 · Open the source