8 of 23 records · showing votes and minutes only ·

2026

  • Recorded voteJul 21, 2026Storey County Board of County Commissioners

    Approval of Special Use Permit 2026-018, natural gas fueled electrical generating facility at 2300 Peru Drive, McCarran (Fleet Data Centers)

    3 yes. Clay Mitchell (Commissioner): yes; Donald Gilman (Commissioner): yes; Jay Carmona (Commissioner): yes.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Item 17, July 21, 2026 minutes (motion by Commissioner Mitchell, seconded by Commissioner Gilman; Aye 3, Nay 0, Abstain 0, Absent 0, Recused 0; Voted For: Mitchell-Clay, Gilman-Donald, Carmona-Jay)

  • Recorded voteJul 21, 2026Storey County Board of County Commissioners

    Approval of the County Manager's letter of acknowledgment for Colovore Reno 1 LLC's GOED data center tax abatement application

    3 yes. Clay Mitchell (Commissioner): yes; Donald Gilman (Commissioner): yes; Jay Carmona (Commissioner): yes.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Item 25, July 21, 2026 minutes (motion by Commissioner Mitchell, seconded by Commissioner Gilman; Aye 3, Nay 0, Abstain 0, Absent 0, Recused 0; Voted For: Mitchell-Clay, Gilman-Donald, Carmona-Jay)

  • Recorded voteJul 21, 2026Storey County Board of County Commissioners

    Approval of Special Use Permit 2026-017, natural gas fueled electrical generating facility at 8990 USA Parkway, McCarran (Fleet Data Centers)

    3 yes. Clay Mitchell (Commissioner): yes; Donald Gilman (Commissioner): yes; Jay Carmona (Commissioner): yes.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Item 16, July 21, 2026 minutes (motion by Commissioner Mitchell, seconded by Commissioner Gilman; Aye 3, Nay 0, Abstain 0, Absent 0, Recused 0; Voted For: Mitchell-Clay, Gilman-Donald, Carmona-Jay)

2025

  • Public decisionUnder reviewDec 23, 2025Nevada Division of Environmental Protection, Bureau of Air Pollution Control

    Nevada Division of Environmental Protection, Bureau of Air Pollution Control, Director's Review and Preliminary Determination, revised Class I OPTC AP7375-3672 (FIN A1896A)

    Preliminary determination to issue the revised permit adding System 08 fire pump engines (S2.001, S2.002) and System 09 emergency generator (S2.003)

    Facility wide nox potential to emit:
    172.6 tons per year
    Units added by pending revision:
    S2.001 and S2.002: Clarke JU6H-UFADN0 emergency diesel fire pump engines, 197 hp each, year 2025; S2.003: Kohler/Rehlko 350REOZJC diesel emergency generator, 538 hp, year 2025
    Facility wide ghg potential to emit:
    22,951.6 tons per year CO2e
    Draft research, not yet verified
    Where it says this

    Director's Review dated December 23, 2025, pages 1-2 (project description and facility-wide potential-to-emit table)

  • Public decisionFiledMay 1, 2025Public Utilities Commission of Nevada

    Public Utilities Commission of Nevada, Docket No. 25-05001 (UEPA)

    Amended application of Switch Ltd. under UEPA for a permit to construct five 345 kV transmission lines totaling 11.90 miles, a substation, and associated facilities on private land in Storey County

    Draft research, not yet verified
    Where it says this

    PUCN docket information list, caption and filing date for Docket No. 25-05001, read firsthand 2026-11-09

2020

  • Public decisionFiledJan 21, 2020Public Utilities Commission of Nevada

    Public Utilities Commission of Nevada, Docket No. 20-01024 (UEPA)

    Application of CEI Switch Citadel OpCo, LLC under UEPA for a permit to construct the Citadel Solar Project: a 250 MW alternating current photovoltaic solar generating facility, two 120 kV generation-tie lines, and associated facilities, about 10 miles east of Reno in Storey County

    Draft research, not yet verified
    Where it says this

    PUCN docket information list, caption and filing date for Docket No. 20-01024, read firsthand 2026-11-09

2017

  • Public decisionFiledMay 8, 2017City of Sparks City Council

    City of Sparks City Council, General Business Item 9.4, meeting of May 8, 2017

    Consideration, discussion and potential direction on TRI GID's proposal to use up to 4,000 acre-feet of reclaimed water annually from the Truckee Meadows Water Reclamation Facility for the Tahoe Reno Industrial Center

    Proposed reclaimed water supply:
    4,000 acre_feet per year
    Draft research, not yet verified
    Where it says this

    Item 9.4 staff report, Agenda Item Brief and preliminary agreement terms

No date in the record(rules in force and undated records)

  • Public decisionApprovedNo date in the recordNevada Legislature, Interim Finance Committee

    Nevada Legislature, Interim Finance Committee, Resolution approving Storey County's economic development financing proposal (Storey County Resolution No. 18-501)

    Approves state general obligation bonds (NRS 360.991) to purchase Storey County special assessment bonds of not more than $35,000,000 for the pipeline carrying treated effluent from the Truckee Meadows Water Reclamation Facility to the Tahoe Reno Industrial Center, repaid by special assessments on the benefited parcels

    Special assessment bond cap:
    $35 million
    Draft research, not yet verified
    Where it says this

    Resolution text, recitals (Storey County Resolution No. 18-501 adopted August 7, 2018; Board of Economic Development approval August 14, 2018) and numbered financing terms 1-4

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    GOED Biennial Report to the Legislature on Abatements from Taxation, FY2010-FY2022 (NRS 231.0685)
    Nevada Governor's Office of Economic Development
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    PUCN docket information list (all utilities)
    Public Utilities Commission of Nevada
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Draft Groundwater Discharge Permit NS2000502, TRI-GID Wastewater Treatment Plant, 145 Britain Way, McCarran, Nevada
    Nevada Division of Environmental Protection
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Class I Air Quality Operating Permit to Construct AP7375-3672, Facility ID A1896, issued to Switch, Ltd.
    Nevada Division of Environmental Protection, Bureau of Air Pollution Control
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Director's Review and Preliminary Determination of Permit Issuance for Switch, Ltd., Storey County, Nevada
    Nevada Division of Environmental Protection, Bureau of Air Pollution Control
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Interim Finance Committee resolution approving the Storey County economic development financing proposal for the TMWRF-to-TRIC effluent pipeline
    Nevada Legislature, Interim Finance Committee
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Sparks City Council meeting May 8, 2017, General Business Item 9.4: TRI GID proposal for use of reclaimed water from the Truckee Meadows Water Reclamation Facility
    City of Sparks, Nevada
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Opening Comments of the Alliance of Western Energy Consumers, Oregon PUC Docket UM 2024 (filed March 16, 2020)
    Public Utility Commission of Oregon (party filing of the Alliance of Western Energy Consumers)
    Tier 2 · Captured 2026-11-09 · Open the source
  9. 9
    The PUCN Connection newsletter, April 2026 edition
    Public Utilities Commission of Nevada
    Tier 1 · Captured 2026-11-08 · Open the source
  10. 10
    2026 Joint Integrated Resource Plan Volume 1 (Nevada Power and Sierra Pacific, Docket 26-05007)
    NV Energy
    Tier 2 · Captured 2026-11-08 · Open the source
  11. 11
    2026 Joint IRP, Volume 2 (Narrative), Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy
    NV Energy
    Tier 1 · Captured 2026-11-09 · Open the source
  12. 12
    Storey County Board of County Commissioners minutes, July 21, 2026 (as published in the September 1, 2026 meeting packet)
    Storey County
    Tier 1 · Captured 2026-11-09 · Open the source
  13. 13
    Switch filings reveal diesel expansion before NDEP's listed dates (Nevada DEP air permit applications, facility A1896A, October 2026)
    W4 News (reporting on NDEP public filings)
    Tier 3 · Captured 2026-11-08 · Open the source
  14. 14
    Switch Citadel Campus (Tahoe Reno) - announced vs energized capacity ledger
    DEPLOY registry
    Tier 3 · Captured 2026-11-08 · Open the source
  15. 15
    First Solar, NV Energy and Switch Partner on New 100 Percent Green, Renewable Energy Program (July 14, 2015)
    NV Energy (company newsroom)
    Tier 4 · Captured 2026-11-09 · Open the source
  16. 16
    The Citadel Campus, Tahoe Reno (Switch locations page)
    Switch
    Tier 4 · Captured 2026-11-09 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page