Every public record we have for Switch Citadel Campus (TAHOE RENO)
Storey County, NevadaOperatingFirst public 2015Filing entity: Switch, Ltd.Last checked Nov 8, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
3 of 23 records · showing tax breaks and payments only ·
2023
Public decisionIssuedJan 17, 2023Nevada Governor's Office of Economic Development
Nevada Governor's Office of Economic Development, Biennial Report to the Legislature on Abatements from Taxation, FY2010-FY2022 (NRS 231.0685)
- Approved employees:
- 50 employees
- Approved average wage:
- $29 per hour
- Approved capital investment:
- $1.39 billion
- Audit capital investment:
- $1.8 million
- Audit capital investment:
- $179.9 million
- Audit jobs found:
- 111 jobs
- Audit jobs found:
- 22 jobs
- Approved personal property tax abatement:
- $4.9 million
- Approved sales use tax abatement:
- $75.7 million
- Approved sales use tax abatement:
- $7.6 million
- Approved average wage:
- $31 per hour
- Approved employees:
- 10 employees
- Approved capital investment:
- $136.1 million
- Approved personal property tax abatement:
- $32.1 million
Draft research, not yet verifiedWhere it says this
Report dated January 17, 2023: FY2016 approval tables for NRS 360.750 (row 4) and NRS 360.754 (row 1), and the FY2016 audit results table (rows 4 and 16)
2015
Tax agreementJul 2015Storey County
Partial tax abatement for data centers (NRS 360.754)
GOED's published approval (July 2015, FY2016 table) for Switch, LTD #2 in Storey County under the data center program: approved partial sales and use tax abatement of $75,720,025 over a 20-year sales and use term, and a personal property tax abatement of $32,095,728, against a stated capital investment of $1,386,677,024, 50 projected employees, and a $28.98 average wage. GOED's audit results: the 2-year audit (2017-12-31) and 5-year audit (2020-12-31) both found the company compliant; audit findings were 111 jobs, a $50.97 average wage, and $179,943,184 of capital investment. Data center abatement under NRS 360.754 as published in GOED's biennial report; the executed agreement was not retrieved, so no further conditions are stated.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
GOED Biennial Report FY2010-FY2022 (January 17, 2023): FY2016 approved NRS 360.754 table, row 1; FY2016 audit results table, Switch, LTD #2
Tax agreementJul 2015Storey County
Partial tax abatement (NRS 360.750)
GOED's published approval (July 2015, FY2016 table) for Switch, LTD #1 in Storey County: approved partial sales and use tax abatement of $7,621,000 and an approved partial 10-year personal property tax abatement of $4,943,500, against a stated capital investment of $136,089,982, 10 projected employees, and a $31.45 average wage. GOED's audit results: the 2-year audit (2017-07-08) and 5-year audit (2020-07-08) both found the company compliant; audit findings were 22 jobs, a $50.97 average wage, and $1,799,432 of capital investment. Standard NRS 360.750 approval as published in GOED's biennial report; the executed agreement was not retrieved, so no further conditions are stated.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
GOED Biennial Report FY2010-FY2022 (January 17, 2023): FY2016 approved NRS 360.750 table, row 4; FY2016 audit results table, Switch, LTD #1
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1GOED Biennial Report to the Legislature on Abatements from Taxation, FY2010-FY2022 (NRS 231.0685)
Nevada Governor's Office of Economic DevelopmentTier 1 · Captured 2026-11-09 · Open the source - 2PUCN docket information list (all utilities)
Public Utilities Commission of NevadaTier 1 · Captured 2026-11-08 · Open the source - 3Draft Groundwater Discharge Permit NS2000502, TRI-GID Wastewater Treatment Plant, 145 Britain Way, McCarran, Nevada
Nevada Division of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 4Class I Air Quality Operating Permit to Construct AP7375-3672, Facility ID A1896, issued to Switch, Ltd.
Nevada Division of Environmental Protection, Bureau of Air Pollution ControlTier 1 · Captured 2026-11-09 · Open the source - 5Director's Review and Preliminary Determination of Permit Issuance for Switch, Ltd., Storey County, Nevada
Nevada Division of Environmental Protection, Bureau of Air Pollution ControlTier 1 · Captured 2026-11-09 · Open the source - 6Interim Finance Committee resolution approving the Storey County economic development financing proposal for the TMWRF-to-TRIC effluent pipeline
Nevada Legislature, Interim Finance CommitteeTier 1 · Captured 2026-11-09 · Open the source - 7Sparks City Council meeting May 8, 2017, General Business Item 9.4: TRI GID proposal for use of reclaimed water from the Truckee Meadows Water Reclamation Facility
City of Sparks, NevadaTier 1 · Captured 2026-11-09 · Open the source - 8Opening Comments of the Alliance of Western Energy Consumers, Oregon PUC Docket UM 2024 (filed March 16, 2020)
Public Utility Commission of Oregon (party filing of the Alliance of Western Energy Consumers)Tier 2 · Captured 2026-11-09 · Open the source - 9The PUCN Connection newsletter, April 2026 edition
Public Utilities Commission of NevadaTier 1 · Captured 2026-11-08 · Open the source - 102026 Joint Integrated Resource Plan Volume 1 (Nevada Power and Sierra Pacific, Docket 26-05007)
NV EnergyTier 2 · Captured 2026-11-08 · Open the source - 112026 Joint IRP, Volume 2 (Narrative), Nevada Power Company and Sierra Pacific Power Company d/b/a NV Energy
NV EnergyTier 1 · Captured 2026-11-09 · Open the source - 12Storey County Board of County Commissioners minutes, July 21, 2026 (as published in the September 1, 2026 meeting packet)
Storey CountyTier 1 · Captured 2026-11-09 · Open the source - 13Switch filings reveal diesel expansion before NDEP's listed dates (Nevada DEP air permit applications, facility A1896A, October 2026)
W4 News (reporting on NDEP public filings)Tier 3 · Captured 2026-11-08 · Open the source - 14Switch Citadel Campus (Tahoe Reno) - announced vs energized capacity ledger
DEPLOY registryTier 3 · Captured 2026-11-08 · Open the source - 15First Solar, NV Energy and Switch Partner on New 100 Percent Green, Renewable Energy Program (July 14, 2015)
NV Energy (company newsroom)Tier 4 · Captured 2026-11-09 · Open the source - 16The Citadel Campus, Tahoe Reno (Switch locations page)
SwitchTier 4 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page