Project File · Public records
Every public record we have for Meta New Albany Data Center
New Albany, Licking County, OhioOperatingFirst public 2017Filing entity: Sidecat LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
7 of 12 records · showing votes and minutes only ·
2025
Public decisionApprovedJun 9, 2025Ohio Power Siting Board
Ohio Power Siting Board, 25-0185-EL-BLN
Authorized construction of the Socrates South Power Generation Project, a 200 MW natural gas-fired facility operating behind the meter to serve the adjacent Sidecat data center campus, not physically connected to the electric grid
- Campus acres:
- 740 acres
- Generator capacity:
- 200 MW
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
PUCO bulletin of June 9, 2025 summarizing the Board's authorization in case 25-0185-EL-BLN
Public decisionFiledJan 2025City of New Albany
City of New Albany
- Building floor area:
- 302,944 sq_ft
- Building floor area:
- 362,317 sq_ft
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Commercial Project Construction Status, January 2025: "Meta LCO DCB1", 1500 Beech Road, 362,317 sq ft, start September 2023; "Meta LCO DCB2", 1500 Beech Road, 302,944 sq ft, start September 2023
2019
Public decisionFiledNov 2019City of New Albany
City of New Albany
- Building floor area:
- 973,670 sq_ft
- Building floor area:
- 518,184 sq_ft
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Commercial Project Construction Status, November 2019: "Sidecat, LLC—NAO 1 & 2 Building 1", 1500 Beech Road, 973,670 sq ft, start Fall 2017; "Sidecat, LLC—NAO3 Building 2", 1500 Beech Rd, 518,184 sq ft, start March 2019
2017
Public decisionApprovedSep 5, 2017City of New Albany
City of New Albany, R-42-2017; R-43-2017
Authorized a packaged sanitary sewer lift station for the Beech Road corridor (R-42-2017) and contracts for the sanitary sewer, waterline, and roadway projects serving development south of SR-161 including the Sidecat site (R-43-2017)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Council minutes of September 5, 2017, Resolutions R-42-2017 and R-43-2017 items; each recorded as adopted with five yes votes (no member roll calls)
Public decisionFiledAug 15, 2017Facebook; JobsOhio; City of New Albany
Facebook; JobsOhio; City of New Albany
Joint announcement that Facebook would build its tenth data center in the New Albany International Business Park: a $750 million, 970,000 sq ft facility on a 345-acre site, powered by 100 percent renewable energy, delivering services from 2019
- Announced investment:
- $750 million
- Site acres:
- 345 acres
- Expected jobs:
- 100 jobs
- Building floor area:
- 970,000 sq_ft
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Announcement release as reproduced in full by Innovate New Albany (page dated August 21, 2017); announcement event August 15, 2017
Public decisionApprovedJul 31, 2017City of New Albany
City of New Albany, R-32-2017
Approved and authorized a Community Reinvestment Area Agreement, a Tax Increment Financing Agreement, and a Development Agreement, all with Sidecat LLC (Oak Grove II CRA)
- Tax exemption percent:
- 100 percent
- Exemption term years:
- 15 years
- Community benefits payment:
- $700,000 per year (minimum city revenue payment under the CRA agreement, from 2021)
- Expected jobs:
- 50 jobs
- Impact fees waived:
- $250,000
- Community benefits payment:
- $1.4 million per year (minimum city revenue payment under the CRA agreement, from 2023)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Resolution R-32-2017 text; council minutes of July 31, 2017 record the staff presentation of terms and adoption with six yes votes (no member roll call)
No date in the record(rules in force and undated records)
Public decisionFiledNo date in the recordMeta Platforms, Inc.
Meta Platforms, Inc.
- Construction peak workforce:
- 1,200 skilled trade workers on site at peak
- Community grant:
- $7.8 million
- Operational jobs:
- 300 jobs (stated as 300+)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Meta's New Albany Data Center community page (read 2026-11-09) and its October 19, 2026 New Albany post
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Community Development Department Monthly Report, November 2019
City of New AlbanyTier 1 · Captured 2026-11-09 · Open the source - 2Here is how the New Albany Data Center is supporting the long-term vitality of Ohio
Meta Platforms, Inc.Tier 1 · Captured 2026-11-09 · Open the source - 3New Albany: where Ohio's community spirit meets the frontier of AI
Meta Platforms, Inc.Tier 1 · Captured 2026-11-09 · Open the source - 4Ohio Data Center Tax Exemption Projects Summary (Last Updated 6/10/2026)
Ohio Department of DevelopmentTier 1 · Captured 2026-11-09 · Open the source · Archived copy - 5Ohio Revised Code Section 122.175, Tax exemption for sale, storage, use, or other consumption of computer data center equipment
Ohio Legislative Service Commission (Ohio Laws)Tier 1 · Captured 2026-11-08 · Open the source - 6Facebook to Build One of the World's Most Advanced Data Centers in New Albany
Innovate New AlbanyTier 1 · Captured 2026-11-09 · Open the source - 7New Albany City Council Meeting Minutes, July 31, 2017
City of New AlbanyTier 1 · Captured 2026-11-09 · Open the source - 8Resolution R-32-2017 (City of New Albany adopted legislation, July 31, 2017)
City of New AlbanyTier 1 · Captured 2026-11-09 · Open the source - 9Community Development Department Monthly Report, January 2025
City of New AlbanyTier 1 · Captured 2026-11-09 · Open the source - 10New Albany City Council Meeting Minutes, September 5, 2017
City of New AlbanyTier 1 · Captured 2026-11-09 · Open the source - 11OPSB approves construction of Licking County natural gas-fired power plant (Socrates South)
Public Utilities Commission of OhioTier 1 · Captured 2026-11-09 · Open the source - 12Data center frequently asked questions
City of New Albany OhioTier 1 · Captured 2026-11-08 · Open the source - 13City of New Albany Ohio Data Center Zoning information sheet (May 2026)
City of New Albany Community Development DepartmentTier 1 · Captured 2026-11-08 · Open the source - 14Data Center Costs, PUCO Case 24-0508-EL-ATA (case page and update)
Office of the Ohio Consumers' CounselTier 2 · Captured 2026-11-08 · Open the source - 15Follow in Facebook's Footsteps: Why Ohio is a Prime Location for Data Centers
AEPTier 1 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page