Every public record we have for Fermi Project Matador (Advanced Energy and Intelligence Campus)

Carson County, TexasUnder constructionFirst public 2025Last checked Nov 12, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

1 of 2 records · showing power and utility only ·

2026

  • Utility proceedingPending before the commissionSep 25, 2026Public Utility Commission of Texas

    Application of Southwestern Public Service Company for Approval of Large Load Customer Tariff Provisions

    Tariff provisions for large load additions of 75 MW or more (the SB 6 statutory size), covering new and incremental load including New Large Load Growth Facilities included in the Uncontested Stipulation in Docket No. 59586. Under the stipulation’s tariff terms: a minimum Electric Service Agreement term of 15 years for New Large Load Growth Customers; a minimum bill based on the customer’s contracted peak demand or availability agreement; a $120,000 non refundable application fee for studies; exit and termination fees at the conclusion of the initial term; and financial security in the form of a letter of credit, security deposit, surety bond, investment grade parent guarantee, or equivalent until the minimum initial term is fulfilled.

    Docket No. 60332

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Uncontested Stipulation (Exhibit A, September 25, 2026): 75 MW threshold and New Large Load Growth Facility definition; tariff provisions (15 year minimum ESA term, minimum bill, $120,000 application fee, exit fees, financial security); docket index (latest filing November 6, 2026)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Land and zoning rules

    Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Fermi America Project Matador Advanced Energy and Intelligence Campus AP1000 Units 1-4, Combined License Application
    U.S. Nuclear Regulatory Commission
    Tier 1 · Captured 2026-11-12 · Open the source · Archived copy
  2. 2
    PUCT Interchange filing index, Project or Docket No. 60332
    Public Utility Commission of Texas
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Fermi America and the Texas Tech University System First to Answer President Trump's Call for Global Energy and AI Dominance
    Fermi America (PR Newswire release on company site)
    Tier 4 · Captured 2026-11-08 · Open the source
  4. 4
    TTU System and Fermi America Announce Partnership (Advanced Energy and Intelligence Campus)
    Texas Tech University System
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    EIA Form 861, Service Territory file, 2025 (final)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page