3 of 3 records

2026

  • Development ruleIn effectOct 20, 2026Memphis

    135-day pause on new data center development with directions for permanent rules

    Memphis paused new data center development for 135 days and directed its planning division to draft permanent Unified Development Code amendments for data centers within 90 days with council guidelines for the permanent rules; existing facilities are not stopped. The separate 18-month moratorium (Ordinance No. 5982) failed on a 6-6 tie the same night.

    Ordinance No. 5986 (substitute adopted 2026-10-20)

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    City Council regular agenda for 2026-10-20 items 18 (Ordinance 5986 third and final reading) and 19 (Ordinance 5982 moratorium)

2025

  • Recorded voteAug 19, 2025Memphis City Council

    Ordinance No. 5953: allocation of lawfully available funds of the city, in an artificial intelligence property, to certain public purposes within the areas affected (third and final reading, as amended)

    11 yes, 1 abstain, 1 absent. Chase Carlisle (Memphis City Councilmember): yes; Edmund Ford, Sr. (Memphis City Councilmember): abstain; Jana Swearengen-Washington (Memphis City Councilmember): yes; Janika White (Memphis City Councilmember): yes; JB Smiley, Jr. (Memphis City Councilmember): yes; Jeff Warren (Memphis City Councilmember): yes; Jerri Green (Memphis City Councilmember): yes; J. Ford Canale (Memphis City Council Chairman): yes; Michalyn Easter-Thomas (Memphis City Councilmember): yes; Pearl Eva Walker (Memphis City Councilmember): yes; Philip Spinosa (Memphis City Councilmember): yes; Rhonda Logan (Memphis City Councilmember): absent; Yolanda Cooper-Sutton (Memphis City Councilmember): yes.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Minutes of the Memphis City Council, August 19, 2025, item 20, final passage: "AYES: Carlisle, Cooper-Sutton, Easter-Thomas, Green, Smiley, Spinosa, Swearengen-Washington, Walker, Warren, White, and Chairman Canale. Ford did not cast a vote. Logan was absent. APPROVED, on Third and Final Reading, as amended"

No date in the record(rules in force and undated records)

  • Utility proceedingIn effectNo date in the recordMemphis Light, Gas and Water Division, City of Memphis

    Electric Service Schedule TDC, Time of Use Data Service

    Retail data service schedule carrying TVA’s wholesale structure, effective October 1, 2026. It applies to firm power where the major use is NAICS subsector 518 or 519 (excluding 519210), NAICS 522320 or 541214, or, in TVA’s sole judgment, the operation of computational equipment; the customer must certify eligibility to both MLGW and TVA, and TVA has unrestricted remote and physical access to metering. Classes are set by the higher of on-peak or off-peak contract demand: TDCA over 1,000 to 5,000 kW, TDCB over 5,000 to 15,000 kW, TDCC over 15,000 to 25,000 kW, TDCD over 25,000 kW. Monthly charges include a $2,000 service charge per delivery point and a $350 TVA administrative charge; summer on-peak demand at transmission voltage is $14.13 to $14.16 per kW by class. Billing demand floors run from 30 percent of the first 5,000 kW to 85 percent of demand above 350,000 kW, on the higher of contract demand or the prior 12 months’ maximum. No facilities rental charge at 161 kV or above; $0.38 per kW-month below 161 kV and $0.97 (first 10,000 kW) and $0.76 (excess) below 46 kV. Reactive charges are $1.81 per kVAR lagging excess and $1.42 per kVAR leading. Contracts: TDCA at least 1 year, TDCB to TDCD at least 5 years for the initial term and each renewal. Rates are subject to TVA’s monthly Fuel Cost and Purchased Power Adjustment Rider.

    Draft research, not yet verifiedLast checked Nov 11, 2026
    Where it says this

    Schedule TDC (4 pages): Availability and Customers Class Description (page 1: NAICS classes, certification, TDCA to TDCD bands); Determination of On-Peak and Off-Peak Demands (page 2: the 30 to 85 percent billing demand floors); Facilities Rental and Reactive Demand Charges (page 2); Contract Requirement (page 3: 1-year and 5-year terms); rate tables (pages 3-4: service and administrative charges, demand and energy charges)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Memphis City Council regular agenda October 20 2026
    City of Memphis
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Electric Service Schedule TDC, Time of Use Data Service (rate effective October 1, 2026)
    Memphis Light, Gas and Water Division, City of Memphis
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy
  3. 3
    Minutes, Meeting of the City Council, City of Memphis, August 19, 2025
    City of Memphis
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Memphis Data Center (MEM1), 3180 Players Lane — Expedient facility page
    Expedient
    Tier 4 · Captured 2026-11-10 · Open the source
  5. 5
    Memphis (Germantown) Data Center sell sheet — Expedient
    Expedient
    Tier 4 · Captured 2026-11-10 · Open the source
  6. 6
    EIA Form 861, Service Territory file, 2025 (final)
    U.S. Energy Information Administration
    Tier 1 · Captured 2026-11-11 · Open the source · Archived copy