Project File · Public records
Every public record we have for CoreWeave data center (Lancaster)
Lancaster, Lancaster County, PennsylvaniaUnder constructionFirst public 2025Filing entity: Greenfield Road Owner, LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
1 of 7 records · showing land and zoning rules only ·
No date in the record(rules in force and undated records)
Development agreementApprovedNo date in the recordCity of Lancaster
City of Lancaster
Executed: Community Benefits Agreement among LPE 01 Propco LLC, Greenfield Road Owner, LLC, Harrisburg Place Owner, LLC, and the City of Lancaster
- Building floor area:
- 1,000,000 square feet (DC Building, Lancaster AI Hub West, targeted construction start November 2026)
- Building floor area:
- 400,000 square feet (initial DC Building, Lancaster AI Hub East, targeted construction start January 2026)
- Community foundation contribution:
- $10 million total Section 8.1 contributions to the Lancaster County Community Foundation: $2,500,000 at construction financing and $2,500,000 within 30 days of operations, for each of LPE Unit 1 and LPE Unit 2
- Article 8 letter of credit:
- $20 million letter of credit, or a corporate guarantee from an entity with net worth of $100 million or more, securing the Article 8 contribution obligations
- Planning contribution:
- $250,000 contribution to the Lancaster County Community Foundation within 30 days of the Effective Date, for the strategic planning process; credited against Section 8.1.1
- Municipal water cap:
- 20,000 gallons per day at either Campus (covenant maximum on municipal water use)
- Data center buildings:
- 3 DC Buildings across the two campuses
- Campus acres:
- 75 acres per campus (approximate, as recited)
- Contingent clean energy letter of credit:
- $10 million letter of credit for the Contingent Clean Energy Fund, delivered for the first DC Building; reduced $2,500,000 per DC Building that commences operations in compliance with Section 3.3.2, floor $5,000,000 until all three buildings comply
- Building floor area:
- 650,000 square feet (second DC Building, Lancaster AI Hub East, targeted construction start August 2026)
- Expected jobs:
- 150 people per Campus (expected employment to operate the facilities, as recited)
- Clean energy fund contribution:
- $10 million total Section 8.2 contributions to the City’s Sustainable Development and Clean Energy Fund: $2,500,000 at construction financing and $2,500,000 within 30 days of operations, for each of LPE Unit 1 and LPE Unit 2
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Executed CBA: Preamble and Background (parties, campuses, buildings); Article 3 (performance commitments); Article 8 (financial contributions); Section 10.1 (20-year term); Section 12.1 (zoning opinions)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Plan Approval 36-05169A, Greenfield Rd Owner LLC/Lancaster (issued December 29, 2025)
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 2Pennsylvania Bulletin, Vol. 56, No. 3 (January 17, 2026)
Commonwealth of PennsylvaniaTier 1 · Captured 2026-11-09 · Open the source - 3Community Benefits Agreement (executed November 2025): LPE 01 Propco LLC, Greenfield Road Owner, LLC, Harrisburg Place Owner, LLC, and the City of Lancaster
City of Lancaster, PATier 1 · Captured 2026-11-09 · Open the source - 4Data Center Frequently Asked Questions
City of Lancaster, PATier 1 · Captured 2026-11-09 · Open the source - 5Pennsylvania Bulletin, Vol. 56, No. 39 (September 26, 2026)
Commonwealth of PennsylvaniaTier 1 · Captured 2026-11-09 · Open the source - 6Administrative Ordinance No. 07-2026 (Administration Bill No. 10-2025): Amending Chapter 300 of the Code of the City of Lancaster to regulate data centers
City of Lancaster, PATier 1 · Captured 2026-11-09 · Open the source - 7Data Center Community Benefits Agreement
City of Lancaster, PATier 1 · Captured 2026-11-09 · Open the source - 8PUC docket page, P-2026-3065185 (PPL Customer Protection Transmission Rider petition)
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source - 9RESA Prehearing Memorandum, P-2026-3065185
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 10PUC docket page, C-2026-3065756 (Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation)
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 11PPLICA Petition to Intervene, C-2026-3065756
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 12CoreWeave Announces Multi-Billion Dollar Commitment to AI Infrastructure in Pennsylvania
CoreWeave, Inc. (via Business Wire)Tier 4 · Captured 2026-11-08 · Open the source - 13U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page