Project File · Public records
Every public record we have for Amazon data center campus (Falls Township)
Falls Township, Bucks County, PennsylvaniaUnder constructionFirst public 2025Filing entity: Amazon Data Services, Inc.Last checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
10 of 10 records
2026
Zoning ruleIn effectJul 27, 2026Falls Township
Curative amendment process for data center zoning
Adopted under Section 609.2 of the Pennsylvania Municipalities Planning Code, the resolution declares part of the township zoning ordinance substantially invalid as it applies to data centers and opens a 180-day curative amendment process. It covers future data centers; the township states it does not affect the approved Amazon campus at the Keystone Trade Center.
Resolution 2026-11
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Board of Supervisors meeting, July 27, 2026
Air permitUnder reviewApr 2026Pennsylvania Department of Environmental Protection
Pennsylvania Department of Environmental Protection, Proposed Plan Approval 09-0261A
- Backup generators:
- 3 diesel-fired ancillary emergency generator engines (one 2,360 hp Tier 2, one 609 hp Tier 3, one 398 hp Tier 3)
- Backup generators:
- 280 natural gas-fired critical back-up generator engines rated 4,287 hp each (NGG1 through NGG280)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Section (b) (p. 1): installation of two-hundred and eighty (280) 4,287 hp natural gas-fired critical back-up power generator engines, one (1) 2,360 hp diesel-fired ancillary emergency generator engine (Tier 2), one (1) 609 hp diesel-fired ancillary emergency generator engine (Tier 3), and one (1) 398 hp diesel-fired ancillary emergency generator engine (Tier 3); DEP Auth ID 1565874; document watermarked PROPOSED with blank dates
2025
Air permitIssuedNov 24, 2025Pennsylvania Department of Environmental Protection
Pennsylvania Department of Environmental Protection, Minor Plan Approval Modification of 09-0261
Minor modification revising the minimum SCR catalyst bed temperature required prior to planned startup of any engine listed in Source ID 101 from 572 degrees Fahrenheit to 430 degrees Fahrenheit
- Stated in the filing:
- 430 degrees Fahrenheit (minimum SCR catalyst bed temperature required before planned startup of any Source ID 101 engine, revised down from 572 degrees Fahrenheit)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Header block (p. 1): Revision Date November 24, 2025, Effective Date November 24, 2025, Expiration Date January 25, 2027; modification description (p. 1); DEP Auth ID 1541156
Water agreementIssuedAug 29, 2025Pennsylvania Department of Environmental Protection
Pennsylvania Department of Environmental Protection, NPDES Permit PAD090088 A-3 (Amendment No. 2)
Amendment No. 2 to the individual NPDES permit for discharges of stormwater associated with construction activities, authorizing NP Falls Township Ind LLC to discharge from the facility known as Keystone Trade Center-Area 3 Development Part A.3, in Falls Township, Bucks County, to the Delaware River
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Permit face: NPDES Permit No. PAD090088 Amendment No. 2; permittee NP Falls Township Ind LLC, 3315 N. Oak Trafficway, Kansas City, MO; effective August 29, 2025; expires midnight April 27, 2028; Authorization ID 1526945
Air permitIssuedJul 25, 2025Pennsylvania Department of Environmental Protection
Pennsylvania Department of Environmental Protection, Plan Approval 09-0261
Issued to Amazon Data Services Inc for the installation and operation of seventy-two (72) 2.75-megawatt (MW) diesel-fired critical emergency generator engines, two (2) 1,000-kilowatt (kW) diesel-fired house emergency generator engines, and two (2) 750-kW diesel-fired house emergency generator engines at a new data center in Falls Township, Bucks County
- Generator capacity:
- 198 MW (72 engines at 2.75 MW each; backup generator capacity, not campus IT load)
- Backup generators:
- 72 diesel-fired critical emergency generator engines rated 2.75 MW each (CEG1 through CEG72)
- Backup generators:
- 4 diesel-fired house emergency generator engines (two at 1,000 kW and two at 750 kW)
- Generator capacity:
- 3.5 MW (2 x 1,000 kW plus 2 x 750 kW house emergency engines)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Header block (p. 1): Issue Date July 25, 2025, Effective Date July 25, 2025, Expiration Date January 25, 2027; Plan Approval Description (p. 1); DEP Auth ID 1526061, PF ID 883491
Public decisionApprovedMar 24, 2025Falls Township Board of Supervisors
Falls Township Board of Supervisors, Resolution 2025-12
Approval of NP Falls Township Industrial, LLC, Phase 2, Building 6, amended final land development, 1 Ben Fairless Drive, TMP 13-051-001: the previously approved 1,035,000 sq. ft. distribution facility is redesigned for data center use
- Floor area:
- 1,035,000 sq. ft. (Building 6 facility previously approved for distribution use, converted to data center use)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes Item # 6 (p. 5): Member Galloway moved to approve Resolution # 2025-12; Member Palmer seconded; all board members were in favor (3-0)
Public decisionApprovedMar 24, 2025Falls Township Board of Supervisors
Falls Township Board of Supervisors, Resolution 2025-11
Approval of NP Falls Township Industrial, LLC, Phase 3 preliminary and final land development, 700 S Port Road, TMP 13-051-001: a reconceptualized plan replacing four distribution facilities on approximately 247 acres with ten principal structures of 112,000 to 217,000 sq. ft. forming a digital infrastructure campus
- Buildings:
- 10 principal structures proposed for the digital infrastructure campus (112,000 to 217,000 sq. ft. each, one or two stories)
- Acres:
- 247 acres (Phase 3 site area, approximate)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes Item # 5 (pp. 4-5): Chairman Dence moved to approve Resolution # 2025-11; Member Galloway seconded; all board members were in favor (3-0)
Recorded voteMar 24, 2025Falls Township Board of Supervisors
Resolution 2025-11: NP Falls Township Industrial, LLC, Phase 3 preliminary and final land development, 700 S Port Road, TMP 13-051-001
3 yes, 2 absent. Brian M. Galloway (Secretary): yes; Erin M. Mullen (Vice-Chairperson): absent; Jeffrey M. Boraski (Supervisor): absent; Jeffry E. Dence (Chairman): yes; John W. Palmer (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Roll call (p. 1); Item # 5 (pp. 4-5): motion by Chairman Dence, seconded by Member Galloway, all board members were in favor (3-0)
Recorded voteMar 24, 2025Falls Township Board of Supervisors
Resolution 2025-12: NP Falls Township Industrial, LLC, Phase 2, Building 6, amended final land development, 1 Ben Fairless Drive, TMP 13-051-001
3 yes, 2 absent. Brian M. Galloway (Secretary): yes; Erin M. Mullen (Vice-Chairperson): absent; Jeffrey M. Boraski (Supervisor): absent; Jeffry E. Dence (Chairman): yes; John W. Palmer (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Roll call (p. 1); Item # 6 (p. 5): motion by Member Galloway, seconded by Member Palmer, all board members were in favor (3-0)
No date in the record(rules in force and undated records)
Tax agreementNo date in the recordFalls Township
Keystone Opportunity Improvement Zone (KOIZ) designation
The initial 15-year tax abatement period took effect on Jan. 1, 2021, and is set to continue through Dec. 31, 2035. The designation covers the former U.S. Steel Fairless Works site developed as the Keystone Trade Center, which includes the Amazon campus parcels (TMP 13-051-001). In September 2023 the Board of Supervisors unanimously approved a resolution to redraw the KOIZ boundaries at the trade center, removing KOIZ benefits from 112.86 acres and adding benefits to 105.24 acres (net 7.64 acres back on the tax rolls); per the township, that change takes effect only if Bucks County, the Pennsbury School District and the Commonwealth also approve, and state legislation that was then pending is enacted. The township article does not state whether those approvals followed.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Article body: 'The initial 15-year tax abatement period took effect on Jan. 1, 2021, and is set to continue through Dec. 31, 2035'; boundary change figures (112.86 acres removed, 105.24 acres added)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Power and utility
Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Minor Plan Approval Modification of 09-0261
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 2Plan Approval 09-0261 (Phase 1), Amazon Data Services Inc, Falls Township
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 3Proposed Plan Approval 09-0261A (Phase 2)
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 4Information Sheet: Amazon Falls Township Data Center
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 5NPDES Permit PAD090088 A-3 (Amendment No. 2), Keystone Trade Center-Area 3 Development Part A.3
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 6Township of Falls Board of Supervisors Meeting Minutes, March 24, 2025
Falls TownshipTier 1 · Captured 2026-11-09 · Open the source - 7Falls OKs Data Centers at Keystone Trade Center
Falls TownshipTier 1 · Captured 2026-11-09 · Open the source - 8Falls Supervisors Remove Nearly 8 Acres from KOIZ Designation
Falls TownshipTier 1 · Captured 2026-11-09 · Open the source - 9Meetings, Falls Township (Board of Supervisors agendas and minutes)
Township of Falls, PennsylvaniaTier 1 · Captured 2026-11-09 · Open the source - 10Southeast Regional Office, Data Centers: Amazon Data Center - Falls Township
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-08 · Open the source - 11Governor Josh Shapiro Announces Amazon Plans to Invest $20 Billion in Pennsylvania for AI Infrastructure
Pennsylvania Department of Community and Economic DevelopmentTier 1 · Captured 2026-11-08 · Open the source