S 724: Requires large data centers to report water use annually
Official title: TO AMEND THE SOUTH CAROLINA CODE OF LAWS BY ADDING SECTION 58-27-835 SO AS TO REQUIRE COMMERCIAL DATA CENTERS THAT CONSUME THREE MILLION GALLONS OF WATER ON A MONTHLY BASIS TO ANNUALLY REPORT THEIR WATER USAGE TO THE DEPARTMENT OF ENVIRONMENTAL SERVICES, TO PROVIDE PENALTIES, AND TO DEFINE NECESSARY TERMS
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Died or failed as of Jan 13, 2026. The official record says: Currently residing in the Senate Committee on Judiciary.
- Filed (done)
- In committee (not reached)
- Passed one chamber (not reached)
- Passed both chambers (not reached)
- Signed into law (not reached)
- In effect (not reached)
- Died or failed (current stage)
What it does
We have not quoted its provisions yet. The official text has them.
Who it touches
No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.
Other projects we track in South Carolina (9), not affected
- 300 Jones Road data center (Spartanburg)Proposed
- AIB CLT1 data center (Tyger River Industrial Park)Proposed
- Google data center campus (Berkeley County)Expanding
- Google Pine Hill Business Campus data center (Ridgeville)Under construction
- Google Winding Woods Commerce Park data center (St. George)Under construction
- QTS data center campus (York County)Under construction
- QTS York County (York County; listed as in development)Under construction
- Savannah River Site AI data center and energy projectProposed
- Valara Holdings high-performance computing center (Spartanburg)Under construction
Who acted
- CosponsorSenator SuttonSenate
- Primary sponsorSenator BlackmonSenate
More from South Carolina
- H 5286 · Died or failedBlocks approvals and incentives for new data centers until 2028
- S 902 · Died or failedRequires state certificate before a data center can operate
- S 784 · Died or failedSets data center power terms and limits tax exemptions
- H 4583 · Died or failedSets responsibility rules for data centers operating in South Carolina
Sources
- 12025-2026 Bill 724: Commercial Data Center Water Usage Report
South Carolina General AssemblyTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "S 724: Requires large data centers to report water use annually." Bill Watch. Updated 2026-11-13. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/sc-126-s-724
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page