Skip to content

Data center court cases and dockets in Louisiana

A docket is a case's public file. These are the lawsuits and the utility commission proceedings (rate cases, large-load rules, agreements) that touch data centers, newest activity first. Each links to its source.

See this week's Docket Drop

3 dockets

Cases and proceedings

  1. Utility commissionPending before the commissionLarge loads

    Application of Cleco Power LLC for authorization of certain contracts, including a site specific contract, as well as certification of transmission interconnection, new generation, and associated waivers for a large load customer pursuant to the Commission’s Lightning Initiative

    Louisiana Public Service Commission · Docket U-38035 · Cleco Power LLC · Louisiana

  2. Utility commissionPending before the commissionLarge loads

    Application of Entergy Louisiana, LLC for certification of generation and transmission resources and for other relief (Lightning Initiative)

    Louisiana Public Service Commission · Docket U-37882 · Entergy Louisiana LLC · Louisiana

  3. Utility commissionDecidedLarge loads

    Application of Entergy Louisiana, LLC for Approval of Generation and Transmission Resources Proposed in Connection with Service to a Significant Customer Project in North Louisiana, Including Proposed Rider, and Request for Timely Treatment

    Louisiana Public Service Commission · Docket U-37425 · Entergy Louisiana LLC · Louisiana

Sources on this page

  1. 1
    Order No. U-38035 (October 15, 2026), procedural order under the Lightning Initiative
    Louisiana Public Service Commission
    Tier 1 · Draft research, not yet verified · Open the source
  2. 2
    Referral of Interlocutory Ruling to Commissioners for Review, Docket No. U-37882
    Louisiana Public Service Commission
    Tier 1 · Draft research, not yet verified · Open the source
  3. 3
    Order No. U-37425 (issued August 29, 2025)
    Louisiana Public Service Commission
    Tier 1 · Draft research, not yet verified · Open the source