Utility commission

Application of Cleco Power LLC for authorization of certain contracts, including a site specific contract, as well as certification of transmission interconnection, new generation, and associated waivers for a large load customer pursuant to the Commission’s Lightning Initiative

Where it stands: Pending before the commission as of Oct 15, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Application to serve an Applied Digital data center in Rapides Parish, planned at about 430 MW by 2028 (the customer’s public description; no capacity is certified yet). Cleco seeks authorization of a site specific (Electric Service Agreement) contract, including a Tenaska capacity agreement running through May 31, 2037, certification of transmission interconnection and new generation, and waivers, under the Lightning Initiative. The ESA’s minimum bill, term, and security terms are not public in the order read; Order No. U-38035 (October 15, 2026) sets the procedural schedule only (hearing February 1-2, 2027; Commission consideration no later than the March 2027 Business and Executive Session).

The facts

Regulator
Louisiana Public Service Commission
Docket number
U-38035
Type
Other
Utility
Cleco Power LLC
State
Louisiana
Filed
Jul 1, 2026
Status date
Oct 15, 2026
Large-load rules
Yes

Related cases and proceedings

In the record

  1. Utility case, Jul 1, 2026. Utility case filed: Application of Cleco Power LLC for authorization of certain contracts, including a site specific contract, as well as certification of transmission interconnection, new generation, and associated waivers for a large load customer pursuant to the Commission’s Lightning Initiative Louisiana Public Service Commission, U-38035

Sources

  1. 1
    Order No. U-38035 (October 15, 2026), procedural order under the Lightning Initiative
    Louisiana Public Service Commission
    Tier 1 · Order No. U-38035 (October 15, 2026): application contents (site specific contract, Tenaska capacity agreement through May 31, 2037, interconnection and generation certification, waivers); hearing and March 2027 consideration dates; application filed July 1, 2026 · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Cleco Power LLC for authorization of certain contracts, including a site specific contract, as well as certification of transmission interconnection, new generation, and associated waivers for a large load customer pursuant to the Commission’s Lightning Initiative." Last activity 2026-10-15. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-cleco-power-u38035