Draft research. Every default and project value comes from our research files and has not passed verification yet.
How many homes use as much electricity as a data center?
Short answer: about 62,600 average U.S. homes for every 100 MW running at a typical 75 percent. The real number depends on the site and its neighbors.
Read: Your tornado warning starts in two data centers: Manassas, Virginia and Phoenix, Arizona
Pick data centers we track, or enter your own numbers. We compare with homes served by the same utility when we have that data, and show how precise the estimate is.
About as much electricity in a year as
105,800 to 148,400 homes
Most likely about 139,100 homes in Tennessee, for xAI Colossus (Memphis) at 300 MW.
Yearly electricity: about 1,971 GWh (range 1,498 to 2,102 GWh).
Precision: Fair2 of 4
- Capacity: From our records, with a source.
- Local homes: State average. Utility data would be sharper.
- What kind of facility: Facility type and what the MW figure measures narrow the range.
- Measured use: The operator's own reported yearly electricity for this site would replace our estimate. None in our records yet.
Estimated range. Not a forecast, and not a bill.
Your data centers, side by side
Sites with the operator's reported use show that measured figure; the others use the same settings as above. Each is compared with the most local homes we have for that site. Where we have neither, enter a capacity to include it.
| Data center | Capacity | Homes (likely) | Yearly GWh | Compared with |
|---|---|---|---|---|
| xAI Colossus (Memphis)Main | 300 MW | 139,100 | 1,971 | Tennessee |
| Together | 139,100 | 1,971 | Each site against its own local homes. |
How it works
- Total facility power: if the number covers computer equipment only, multiply by the overhead multiplier.
300 MW × 1 = 300 MW (likely) - Yearly electricity: facility power times 8,760 hours times how hard it runs.
300 MW × 8,760 h × 75% = 1,971,000 MWh - Homes: that total divided by what one home uses in a year.
1,971,000 MWh ÷ 14.165 MWh = 139,146 homes (shown rounded)
This does not capture ramp-up over years, peak demand at the hottest hour, or anything about bills.
Sources
- 1Form EIA-861 final 2025 detailed data files
U.S. Energy Information AdministrationTier 1 · Open the source - 2EIA Form 861 2025, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Open the source - 3Greater than 100 MW firm power arrangement with CTC Property LLC (xAI), TVA Board of Directors presentation, November 7, 2024
Tennessee Valley AuthorityTier 1 · Open the source - 42025 xAI Update (MLGW published briefing, May 2025)
Memphis Light, Gas and WaterTier 1 · Open the source - 5Construction Permit No. 01156-01PC, CTC Property LLC (Colossus Data Center), issued July 2, 2025
Shelby County Health DepartmentTier 1 · Open the source - 6xAI - Greater Memphis Chamber (project page: Pidgeon Industrial Park, 552 acres, live 2024-08-08, about 300 MW)
Greater Memphis ChamberTier 1 · Open the source - 7xAI Colossus: the Memphis AI supercomputer explained (built from xAI, MLGW, and Chamber statements)
The Model PressTier 3 · Open the source - 8Velocity Meets Potency: xAI Announces Memphis as New Home (press release, June 5, 2024)
Greater Memphis ChamberTier 2 · Open the source - 9xAI Phase One Substation #63 Providing 150MW of Power to Facility (press release, May 1, 2025)
Greater Memphis ChamberTier 2 · Open the source - 10TVA Board Resolution and Memorandum, Exhibit 11/07/24G: Greater than 100 MW firm power arrangement with CTC Property LLC (xAI)
Tennessee Valley AuthorityTier 1 · Open the source - 11TVA Board Resolution (Power Availability), February 11, 2026, Exhibit 02/11/26E
Tennessee Valley AuthorityTier 1 · Open the source - 12Minutes, Meeting of the City Council, City of Memphis, August 19, 2025
City of MemphisTier 1 · Open the source - 13Memphis City Council Regular Agenda, June 24, 2025 (council roster)
City of MemphisTier 1 · Open the source - 14Shelby County Commission resolution urging a public hearing before approval or denial of the permit submitted by CTC Property LLC (as amended in committee, March 25, 2025)
Shelby County CommissionTier 1 · Open the source - 15Higher limits and a new compute partnership with SpaceX (Anthropic news post, May 6, 2026)
AnthropicTier 2 · Open the source - 16
- 17Annual and Peak Electricity Use: History and Future Projections (Powering Intelligence 2026)
EPRITier 2 · Open the source - 18Uptime Institute Global Data Center Survey 2024: regional view (UII Data Report 154)
Uptime InstituteTier 2 · Open the source
Questions people ask
- How many homes use as much electricity as a data center?
- About 62,600 average U.S. homes for every 100 MW running at a typical 75 percent. The real number depends on the site and its neighbors.
- How many homes does 1 MW of data center power equal?
- About 630 average U.S. homes for each megawatt, if the site runs at 75 percent of its capacity all year and a home uses 10,491 kWh a year (2025). Pick a site to compare with homes on its own utility.
- Is a data center's MW figure what it actually uses?
- No. Announced capacity is the most a site can draw, and many sites ramp up over years. Where an operator reports its yearly electricity use, this calculator uses that measured figure instead.
- Why does the answer change by utility?
- Homes use different amounts of electricity in different places, mostly because of climate and heating. Comparing with homes on the same utility, then the same state, gives the most local answer we have data for.
Embed this calculator
Paste this code where your page accepts HTML. The calculator runs on this site, so it stays current when the method or the defaults change. Set the height to fit your page.
<iframe src="https://datacenterfactcheck.org/calculators/mw-to-homes/embed" title="MW to homes calculator" width="100%" height="640" loading="lazy"></iframe>