  1. Filing

    Filed with Virginia Department of Environmental Quality: air permit for Microsoft data center campus (Boydton)

    Registration No. 21527; Permit No. PRO-21527

  2. Filing

    Filed with Virginia Department of Environmental Quality: air permit for Microsoft data center campus (Boydton)

    Registration No. 21527, permit action 21527-15

  3. Tax deal

    Tax agreement approved: Economic stimulus grants (rebates of taxes paid)

    A grant of 90 percent of the company's personal property tax for 20 years, plus a grant of 100 percent of the county machinery and tools tax for 5 years.

Sources on this page

  1. 1
    Final Order, Case No. PUR-2025-00014 (Nebula-Raines Line 2399, Nebula Switching Station, Cloud-Nebula Line 2402)
    Virginia State Corporation Commission
    Tier 1 · Open the source
  2. 2
    Initial Title V Permit, Microsoft Corp, East Coast Data Center (Permit No. PRO-21527)
    Virginia Department of Environmental Quality
    Tier 1 · Open the source
  3. 3
    Stationary Source Permit to Construct and Operate, significant amendment (permit action 21527-15), Microsoft Corporation, East Coast Data Center
    Virginia Department of Environmental Quality
    Tier 1 · Open the source
  4. 4
    Board of Supervisors Minutes, August 10, 2020
    Mecklenburg County
    Tier 1 · Open the source
  5. 5
    County lines up incentive package, The Mecklenburg Sun, July 14, 2010
    The Mecklenburg Sun (SoVaNow)
    Tier 3 · Open the source
  6. 6
    Governor McAuliffe Announces 44 New Jobs and More than $251 Million Investment in Mecklenburg County
    Virginia Economic Development Partnership
    Tier 1 · Open the source