Project File · Public records
Every public record we have for Yondr Northern Virginia campus (Aldie)
Loudoun County, VirginiaExpandingFirst public 2023Filing entity: Yondr JK 2 LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
9 of 26 records · showing votes and minutes only ·
2025
Recorded voteAug 11, 2025Loudoun County Board of Equalization
Affirm the County's 2025 real estate tax assessment of 21673 Beaumeade Circle LLC, 21745 Beaumeade Circle, Ashburn (PIN 060189720000, Appeal ID 6824)
4 yes, 2 absent. Bob Saltzman (Alternate Member): yes; Chrissie Goodrum (Member): absent; Cliff Keirce (Vice Chairman/Secretary): yes; John Fuog (Member): yes; Kevin Kuesters (Chairman): yes; Sharad Tandale (Member): absent.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
2025 Board of Equalization Annual Report, minutes of the Board of Equalization Hearings, August 11, 2025 (attendance roll, p. 1 of the day's minutes, and the 21673 BEAUMEADE CIRCLE LLC case, Appeal ID 6824)
Recorded voteMar 18, 2025Loudoun County Board of Supervisors
Grandfathering Resolution for ZOAM-2024-0001, as amended
5 yes, 4 no. Caleb Kershner (Supervisor): yes; Juli Briskman (Supervisor): no; Koran Saines (Supervisor): yes; Kristen Umstattd (Supervisor): yes; Laura TeKrony (Supervisor): no; Matthew Letourneau (Supervisor): yes; Michael Turner (Vice Chair): no; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): no.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Item 7, p. 9 (Grandfathering Resolution passed 5-4)
Recorded voteMar 18, 2025Loudoun County Board of Supervisors
Adoption of CPAM-2024-0001 and ZOAM-2024-0001, Data Center Standards and Locations, Phase 1 (main motion)
7 yes, 2 no. Caleb Kershner (Supervisor): no; Juli Briskman (Supervisor): yes; Koran Saines (Supervisor): yes; Kristen Umstattd (Supervisor): no; Laura TeKrony (Supervisor): yes; Matthew Letourneau (Supervisor): yes; Michael Turner (Vice Chair): yes; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Item 7, pp. 9-10 (main motion passed 7-2; Supervisors Kershner and Umstattd opposed)
2024
Recorded voteFeb 6, 2024Loudoun County Board of Supervisors
Resolution approving Loudoun County entering into a Voluntary Settlement Agreement of Annexation and Related Issues with the Town of Leesburg (Compass Creek annexation)
8 yes, 1 absent. Caleb Kershner (Supervisor): yes; Juli Briskman (Vice Chair): yes; Koran Saines (Supervisor): absent; Kristen Umstattd (Supervisor): yes; Laura TeKrony (Supervisor): yes; Matthew Letourneau (Supervisor): yes; Michael Turner (Supervisor): yes; Phyllis Randall (Chair): yes; Sylvia Glass (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Appendix, Exhibit B (Item A p. 31): motion by Chair Randall, seconded by Vice Chair Briskman; voting list: Supervisors Briskman, Glass, Kershner, Letourneau, Randall, TeKrony, Turner, and Umstattd - Yes; None - No; Supervisor Saines - Absent for the vote
2022
Recorded voteApr 13, 2022Loudoun County Board of Supervisors
Forward ZCPA-2020-0003, True North Data, to the May 17, 2022 Board of Supervisors Business Meeting for action
5 yes, 2 no, 2 absent. Caleb A. Kershner (Supervisor): yes; Juli E. Briskman (Supervisor): absent; Koran T. Saines (Supervisor): yes; Kristen C. Umstattd (Supervisor): yes; Matthew F. Letourneau (Supervisor): absent; Michael R. Turner (Supervisor): yes; Phyllis J. Randall (Chair): no; Sylvia R. Glass (Supervisor): yes; Tony Buffington (Supervisor): no.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Action Report of the April 13, 2022, Board of Supervisors Public Hearing, Item 10 (p. 3)
2020
Recorded voteDec 10, 2020Loudoun County Planning Commission
Forward ZCPA-2020-0003, True North Data, to the Board of Supervisors with a recommendation of approval
5 yes, 3 no, 1 absent. Ad Barnes (Member): no; Eric Combs (Chair): yes; Forest Hayes (Vice Chair): yes; Jane Kirchner (Member): no; Jeff Salmon (Member): yes; John Merrithew (Member): absent; Mark Miller (Member): yes; Michelle Frank (Member): yes; Roger Vance (Member): no.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, Loudoun County Planning Commission Work Session, December 10, 2020, Item 3 (pp. 5-6) and the meeting roster (p. 1)
No date in the record(rules in force and undated records)
Public decisionFiledNo date in the recordVirginia Department of Environmental Quality
Virginia Department of Environmental Quality, 22-001685
Virginia Water Protection Non-Permit record for 'Yondr JK Substation', Loudoun County, Northern region; status Active in the layer. Non-Permit records are the water program's records of projects reviewed without an individual or general VWP permit; the layer publishes no impact or acreage figures for this record
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
DEQ EDMA Virginia Water Protection Non-Permit layer (layer 191), record 22-001685, queried 2026-11-09 by facility name and by site envelope
Public decisionFiledNo date in the recordLoudoun County Board of Equalization
Loudoun County Board of Equalization
2025 Annual Report, table 'Commercial Appeals Settled by COR before BOE Hearing': the campus parcel's 2025 assessment appeal (YONDR JK 2 LLC, 24171 YOUNGWOOD LN ALDIE VA 20105, printed PIN 093365404005, 34.03 acres) was settled with the Commissioner of the Revenue before a Board of Equalization hearing: original total $603,971,030 (land $46,855,100; improvements $557,115,930), COR-reduced total $470,981,580 (land $46,855,100; improvements $424,126,480), decision code NOC, -22%
- Assessed total value:
- $471 million
- Assessed total value:
- $604 million
- Parcel acres:
- 34.03 acres
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
2025 Board of Equalization Annual Report, table 'Commercial Appeals Settled by COR before BOE Hearing' (YONDR JK 2 LLC row), p. 6
Public decisionFiledNo date in the recordLoudoun County, Virginia
Loudoun County, Virginia, MCPI 203371445000
County Existing Data Center Parcels layer record for the campus parcel: Project EVERGREEN MEADOWS, owner of record YONDR JK 2 LLC, 34.034 legal acres, one building permit (B20600690100) totaling 335,638 sq ft, status Existing, built status BUILT, zoned IP under the 2023 ordinance with underlying Zoning Case ZMAP-2005-0036, planning subarea DULLES, election district DULLES
- Floor area:
- 335,638 square feet of data center building on the parcel (Overall_SQ_FT; building permit B20600690100; built status BUILT)
- Parcel acres:
- 34.034 acres
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
County Existing Data Center Parcels layer (FeatureServer layer 1), record for MCPI 203371445000, queried 2026-11-09 on the owner name; name queries for YONDR, JK and EVERGREEN return this parcel only
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Stationary Source Permit to Construct and Operate, Yondr JK 2 LLC, Registration No. 74265, August 13, 2026 (combined minor New Source Review permit, with transmittal letter)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 2Stormwater Permits (Daily), EDMA MapServer layer 303
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 3EDMA Virginia Water Protection Non-Permit layer (MapServer layer 191), record 22-001685 (Yondr JK Substation) and statewide Yondr name queries of layers 191, 192 and 193
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 4Loudoun County Board of Equalization 2025 Annual Report
Loudoun County Board of EqualizationTier 1 · Captured 2026-11-09 · Open the source - 5Existing Data Center Parcels (county GIS layer), records for MCPI 044261032000 (Pacific Boulevard, Sterling) and MCPI 234371847000 (Compass Creek, Leesburg)
Loudoun County, VirginiaTier 1 · Captured 2026-11-09 · Open the source - 6Loudoun County Zoning Ordinance (official text, eReader)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 7Land Use Considerations (county data center page)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 8Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Captured 2026-11-07 · Open the source - 9SCC Issues Order on DEV Biennial Review 2025
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 10Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
Virginia Electric and Power CompanyTier 1 · Captured 2026-11-07 · Open the source - 11How the SCC Rider T1 Decision Protects Ratepayers
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 12Order for Notice and Hearing, Case No. PUR-2026-00056
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 13Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
Loudoun County Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 14Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 15Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Captured 2026-11-09 · Open the source - 16Board of Supervisors Business Meeting Minutes, March 18, 2025
Loudoun CountyTier 1 · Captured 2026-11-07 · Open the source - 17Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 18EDMA Active Air Sites layer (MapServer layer 294), facility record for Registration No. 74265 and statewide Yondr name query
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 19Yondr Group's first Northern Virginia data center is ready for service
Yondr GroupTier 4 · Captured 2026-11-09 · Open the source - 20Yondr Group completes first RFS milestone for second building at 96MW Northern Virginia campus
Yondr GroupTier 4 · Captured 2026-11-09 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page