Project File · Public records
Every public record we have for Aligned Data Centers SLC-03 (West Jordan)
West Jordan, Salt Lake County, UtahOperatingFirst public 2026Last checked Nov 14, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
1 of 13 records · showing votes and minutes only ·
2025
Recorded voteJan 7, 2025West Jordan Planning and Zoning Commission
Preliminary Major Subdivision for Novva West Jordan Power Generation (2-lot plat, 27.65 acres), 6524 West Old Bingham Highway, application #33294
5 yes, 1 recused, 1 absent. Ammon Allen (Commissioner): yes; Emily Gonzalez (Commissioner): absent; Jay Thomas (Commissioner): yes; Jimmy Anderson (Commissioner): recused, Disclosed conflict of interest: Novva is a client of his law firm; John Roberts (Commissioner): yes; Tom Hollingsworth (Commissioner): yes; Trish Hatch (Commissioner): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Item 7, MOTION: "Trish Hatch moved to approve ... The motion was seconded by Tom Hollingsworth and passed 5-0 in favor with Commissioner Anderson abstaining. Emily Gonzalez was absent."
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Schedule 48T, Large General Service, Metered Time of Use, 1,000 kW and Over (Tariff WN U-76)
PacifiCorp d/b/a Pacific Power & Light CompanyTier 1 · Captured 2026-11-08 · Open the source - 2Settlement Stipulation, Docket No. 26-035-05, Application of Rocky Mountain Power for Approval of Large-Load Service Contract between PacifiCorp and a Large-Load Customer
Public Service Commission of Utah (filing by Rocky Mountain Power with the Division of Public Utilities and the Office of Consumer Services)Tier 1 · Captured 2026-11-08 · Open the source - 3Notice of Decisions on UAE motion and approval of the Settlement Stipulation, Docket No. 26-035-05
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 4Rocky Mountain Power advances Utah's Operation Gigawatt through landmark energy agreement
Rocky Mountain Power (PacifiCorp)Tier 4 · Captured 2026-11-08 · Open the source - 5Notice of Comment Period, Docket Nos. 25-R318-01 and 24-035-43 (large load flexible tariff guidance; R746-318 New Rule)
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 6Rocky Mountain Power Idaho Electric Service Schedule No. 400, Special Contract (I.P.U.C. No. 1, Thirteenth Revision of Sheet No. 400.1)
Rocky Mountain Power (PacifiCorp)Tier 1 · Captured 2026-11-08 · Open the source - 7Final Order No. 35277, Case No. PAC-E-21-07 (Rocky Mountain Power Idaho rate case)
Idaho Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 8Order No. 23-472, PacifiCorp Revision of Rule 13 Line Extension Policy, Docket UE 424
Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 9Rocky Mountain Power Wyoming Electric Service Schedule No. 400, Special Contracts (P.S.C. Wyoming No. 19, Original Sheets 400-1 to 400-3)
Rocky Mountain Power (PacifiCorp)Tier 1 · Captured 2026-11-08 · Open the source - 10Public notice of Rocky Mountain Power application to establish Tariff Schedule 400, Special Contracts, Docket No. 20000-602-ET-21 (legal notice as published July 13, 2021)
Wyoming Public Service Commission (notice published in the Kemmerer Gazette)Tier 1 · Captured 2026-11-08 · Open the source - 11PacifiCorp Reply Testimony of Craig M. Eller, Oregon Docket No. UE 463, Exhibit PAC/200
PacifiCorpTier 1 · Captured 2026-11-08 · Open the source - 12Memorandum to service list in Docket No. 25-R318-01 with Charles River Associates clarification and guidance on the initial SB 132 rules
Public Service Commission of UtahTier 1 · Captured 2026-11-08 · Open the source - 13Utah Code Title 54, Chapter 26, Part 1, General Provisions (Large-Scale Electric Service Requirements), effective May 7, 2025
Utah State LegislatureTier 1 · Captured 2026-11-08 · Open the source - 14Utah Code Section 54-26-301, Large load contract requirements, effective May 7, 2025
Utah State LegislatureTier 1 · Captured 2026-11-08 · Open the source - 15PUC Cuts PacifiCorp's Requested January 1 General Rate Increase (UE 433 decision release)
Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 16Staff Opening Testimony (Staff/100), Docket UE 463
Staff of the Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 17Data Center Coalition Opening Testimony of Bieber, Docket UE 463
Data Center Coalition (filed in Public Utility Commission of Oregon Docket UE 463)Tier 1 · Captured 2026-11-08 · Open the source - 18Staff Report, Portland General Electric Investigation into New Load Connection Costs, Docket UE 430 / Advice No. 24-38
Staff of the Public Utility Commission of OregonTier 1 · Captured 2026-11-08 · Open the source - 19Schedule 48, Large General Service 1,000 kW and Over, Delivery Service (P.U.C. OR No. 36)
PacifiCorp d/b/a Pacific PowerTier 1 · Captured 2026-11-08 · Open the source - 20UTC Case Docket Detail Page, Docket UE-231037 (PacifiCorp, Advice 23-06)
Washington Utilities and Transportation CommissionTier 1 · Captured 2026-11-08 · Open the source - 21PacifiCorp Advice 23-06 cover letter and Rule 14 tariff sheets, Docket UE-231037
PacifiCorp d/b/a Pacific Power & Light Company (filed with the Washington Utilities and Transportation Commission)Tier 1 · Captured 2026-11-08 · Open the source - 22Alliance of Western Energy Consumers filing in Docket No. UE 463
Public Utility Commission of OregonTier 1 · Captured 2026-11-07 · Open the source - 23PacifiCorp Surrebuttal Testimony of Robert M. Meredith, Docket No. UE 463, with Exhibit PAC/301 (Revised Schedule 401)
Public Utility Commission of OregonTier 1 · Captured 2026-11-07 · Open the source - 24Stipulation, Docket No. UE 463, Advice No. 25-015, Schedule 401
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source - 25ALJ Ruling, Docket UM 2410 (Amazon Data Services, Inc. v. PacifiCorp)
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 26Third Joint Status Report and Motion to Extend Suspension of Procedural Schedule, Docket UM 2410
Public Utility Commission of OregonTier 1 · Captured 2026-11-11 · Open the source - 27Minutes of the Regular Meeting of the West Jordan Planning and Zoning Commission, January 7, 2025
City of West Jordan (filed on the Utah Public Notice Website)Tier 1 · Captured 2026-11-09 · Open the source - 28Aligned Data Centers data center locations (operator’s own list)
Aligned Data CentersTier 2 · Captured 2026-11-10 · Open the source - 29Salt Lake City Data Centers (SLC-01 to SLC-04)
Aligned Data CentersTier 4 · Captured 2026-11-08 · Open the source - 30Aligned Expands Campus with New Salt Lake Data Center (SLC-03)
Aligned Data Centers (release carried by Utah Business)Tier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page