Skip to content

Project File · Public records

Every public record we have for Project Eagle data center and Project Baccara power plant

Glendale, Maricopa County, ArizonaApprovedFirst public 2025Filing entity: Montera InfrastructureLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

1 of 2 records · showing votes and minutes only ·

2026

  • Public decisionApprovedOct 27, 2026City of Glendale

    City of Glendale

    Council approved the project 6-1 on October 27 (2026 per the city's timeline as read); 12 stipulations including following the July 17 2026 submitted plan, traffic study, Luke AFB June 30 2026 letter conditions, continuous air monitoring, and funding specialized emergency services including hazmat response before the first building opens

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    City of Glendale Project Eagle/Baccara FAQ PDF, read firsthand: about 160 acres west of Litchfield Road and north of Olive Avenue; county already approved up to three data centers (about 1.1M sq ft), a natural-gas power plant, and an APS substation; water/sewer by EPCOR; pre-annexation development agreement approved April 28, consensus to proceed with annexation August 25, state-required public hearing September 22, Council approval October 27 by 6-1; 18 natural gas turbines feeding an APS substation; data center air quality permit in process

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Power and utility

    Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.

  • Tax breaks and payments

    Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Project Eagle/Baccara (city project page and FAQ)
    City of Glendale
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
    Maricopa County, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page