Middlesex Township, Cumberland County, PennsylvaniaUnder constructionFirst public 2025Filing entity: Carlisle Development Partners, LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
2 of 47 records · showing power and utility only ·
2026
Utility proceedingPending before the commissionOct 2, 2026Pennsylvania Public Utility Commission
Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation (formal complaint on large load and data center costs)
The Office of Consumer Advocate alleges existing customers are paying new and higher costs caused by data center additions on PPL’s system and in PJM, and are receiving service frequently interrupted or curtailed because of data center interconnection. It says Rate Schedule LP-6 does not protect enough and asks the Commission to make its model tariff guidelines mandatory for PPL: mandatory interruptible rates for data centers; pre-emergency and emergency load shed plans; classification of computational loads as critical or non-critical; affordability protections including ongoing contributions to the Universal Service Program; classification by end use (computational load) instead of only by connection above 69 kV; binding generator commitments or matching capacity from computational customers; a battery storage network for peaks; a definition of but-for costs for transmission and distribution upgrades; and a test of whether capacity and transmission rate design, including Reliability Backstop Procurement and Interim Resource Adequacy Service costs, protects other customers. The model tariff threshold is 50 MW for a single load or 100 MW in aggregate. Governor Shapiro intervened on October 16, 2026; Amazon Data Services and the Data Center Coalition intervened on November 3, 2026.
C-2026-3065756
Draft research, not yet verifiedLast checked Nov 11, 2026Where it says this
PUC docket page, Case Summary (docket, Active, Date Filed 10/2/2026) and Daily Actions, 11/10/2026 (consolidated Scheduling Order); PPLICA Petition to Intervene, filed 2026-10-22, complaint summary at pages 1-2 and relief at pages 3-4 and 77-79
Utility proceedingPending before the commissionSep 14, 2026Pennsylvania Public Utility Commission
Petition of PPL Electric Utilities Corporation for Approval of Its Non-Bypassable Customer Protection Transmission Rider, Elimination of Its Transmission Service Charge, Changes to Its Generation Supply Charges, Changes to Its Retail Tariff, and Changes to Its Electric Generation Supplier Coordination Tariff
PPL proposes a non-bypassable Customer Protection Transmission Rider recovering NITS and certain other transmission costs, elimination of its Transmission Service Charge, and moving the remaining transmission costs into Generation Supply Charges. Certain network upgrade costs are allocated to Rate LP-6 large load customers, and the petition creates a mechanism for future Reliability Backstop Procurement and Interim Resource Adequacy Service charges or credits ultimately assigned to PPL and properly attributable to LP-6 customers. It changes how transmission costs are allocated, recovered and billed for shopping and default service customers.
P-2026-3065185
Draft research, not yet verifiedLast checked Nov 11, 2026Where it says this
PUC docket page, Case Summary (Date Filed 9/14/2026, full case description) and Daily Actions, 11/10/2026 (consolidated Scheduling Order); RESA Prehearing Memorandum, 2026-10-30, Section I Background
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Middlesex Township Board of Supervisors meeting minutes, September 2, 2026 (with attachments)
Middlesex TownshipTier 1 · Captured 2026-11-09 · Open the source - 2Middlesex Township Board of Supervisors meeting minutes, July 1, 2026
Middlesex TownshipTier 1 · Captured 2026-11-09 · Open the source - 3PAG-02 NPDES General Permit Coverage Approval, Permit No. PAC210079 A-4, Pennsylvania Digital 1 (PAX-1)
Cumberland County Conservation DistrictTier 1 · Captured 2026-11-09 · Open the source - 4Notice of Appeal (Dymski and Shivell v. Cumberland County Conservation District and PA DEP; Carlisle Development Partners, LLC, permittee)
Pennsylvania Environmental Hearing Board (appellants' filing)Tier 1 · Captured 2026-11-09 · Open the source - 5Middlesex Township Board of Supervisors meeting minutes, May 6, 2026
Middlesex TownshipTier 1 · Captured 2026-11-09 · Open the source - 6Middlesex Township Board of Supervisors meeting minutes, July 31, 2026
Middlesex TownshipTier 1 · Captured 2026-11-09 · Open the source - 7Environmental Impact Assessment, Pennsylvania Digital 1 (PAX-1), Project No. 1258-01, project narrative excerpt (May 2026)
Livic Civil, for Carlisle Development Partners, LLCTier 4 · Captured 2026-11-09 · Open the source - 8General Permit Acknowledgment, Pennsylvania Digital 1 (PAX-1) - Water Main Relocation, DEP General Permit File No. GP052103225-003
Pennsylvania Department of Environmental ProtectionTier 1 · Captured 2026-11-09 · Open the source - 9Middlesex Township Board of Supervisors meeting minutes, March 4, 2026
Middlesex TownshipTier 1 · Captured 2026-11-09 · Open the source - 10Middlesex Township Planning Commission meeting minutes, June 22, 2026
Middlesex Township Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 11Subdivision and Land Development Review Report, Plan No. P26-147, Pennsylvania Digital (PAX-1) Final Subdivision Plan
Cumberland County Planning DepartmentTier 1 · Captured 2026-11-09 · Open the source - 12Middlesex Township Board of Supervisors meeting minutes, January 5, 2026
Middlesex TownshipTier 1 · Captured 2026-11-09 · Open the source - 13Petition for Stay of the Actions Appealed Pursuant to 53 P.S. 11003-A(d), No. 2026-06465 Civil Term
Court of Common Pleas of Cumberland County (appellants' filing)Tier 1 · Captured 2026-11-09 · Open the source - 14Motion to Quash Land Use Appeal, Gerber et al. v. Board of Supervisors of Middlesex Township, No. 2026-06465 Civil Term
Court of Common Pleas of Cumberland County (intervenor filing)Tier 1 · Captured 2026-11-09 · Open the source - 15Response in Opposition to Petition to Confirm and Enforce Stay, No. 2026-08758 Civil Term
Court of Common Pleas of Cumberland County (intervenor filing)Tier 1 · Captured 2026-11-09 · Open the source - 16Petition to Confirm and Enforce the Stay of Proceedings Under 53 P.S. 10915.1(a), No. 2026-08758 Civil Term
Court of Common Pleas of Cumberland County (appellants' filing)Tier 1 · Captured 2026-11-09 · Open the source - 17Middlesex Township Board of Supervisors workshop meeting minutes, February 27, 2026
Middlesex TownshipTier 1 · Captured 2026-11-09 · Open the source - 18Middlesex Township Board of Supervisors workshop meeting minutes, May 30, 2025
Middlesex TownshipTier 1 · Captured 2026-11-09 · Open the source - 19PUC docket page, P-2026-3065185 (PPL Customer Protection Transmission Rider petition)
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source - 20RESA Prehearing Memorandum, P-2026-3065185
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 21PUC docket page, C-2026-3065756 (Pennsylvania Consumer Advocate v. PPL Electric Utilities Corporation)
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 22PPLICA Petition to Intervene, C-2026-3065756
Pennsylvania Public Utility CommissionTier 1 · Captured 2026-11-11 · Open the source · Archived copy - 23Middlesex Township Planning Commission workshop meeting minutes, February 23, 2026
Middlesex Township Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 24Middlesex Township Planning Commission workshop meeting minutes, April 27, 2026
Middlesex Township Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 25Pennsylvania Data Center Partners and PowerHouse Data Centers Launch Joint Venture to Build Next-Gen 1.35 GW Hyperscale Data Center Campus in Carlisle, Pennsylvania
PowerHouse Data CentersTier 4 · Captured 2026-11-08 · Open the source