Project File · Public records
Every public record we have for NTT VA10 Gainesville
Prince William County, VirginiaOperatingFirst public 2023Filing entity: NTT Global Data Centers VA10, LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
10 of 10 records
2026
Zoning ruleIn effectSep 22, 2026Prince William County
Data Center Opportunity Zone Overlay District shrunk and closed to expansion; special use permit required outside the overlay
Prince William County adopted a zoning text amendment restructuring its Data Center Opportunity Zone Overlay District: the overlay boundary is reduced and redefined to parcels meeting one or more of five county eligibility pathways in Sec. 32-509.3(2), the overlay is closed to any future expansion, and new data center proposals outside the overlay in the B-1, O(L), O(M), O(H), O(F), M-1, M-2 and M/T districts (and designated office/industrial land bays in PBD and PMD districts) must proceed through the Special Use Permit process. Parcels remaining inside the overlay that meet an eligibility pathway keep by-right permission.
Zoning text amendment DPA2021-00020 amending County Code Sec. 32-509.01 et seq. (re-initiated by Res. No. 26-374, 2026-06-09)
Draft research, not yet verifiedLast checked Nov 10, 2026Where it says this
County DPA2021-00020 review page: ZTA restructure, five eligibility pathways, overlay closed to expansion, SUP districts list; Development Services memorandum 2026-10-16: adoption date, December 21 2026 effective date and grandfathering deadline
Utility proceedingPending before the commissionAug 25, 2026Virginia State Corporation Commission
Supplemental proceeding for Dominion Energy Virginia proposed amendments to its line extension policy (direct connect transmission facilities for large load customers)
New docket established by Commission order on August 25, 2026 to receive Dominion proposed amendments to its line extension policy, developed with Commission staff under the framework approved in PUR-2026-00056. The amendments are designed to ensure large load customers fund the costs of direct connect transmission facilities needed to serve new or expanding large loads, in situations where those facilities would not be built if not for the large load customer needs. The policy will apply prospectively. No amended policy text had been opened when this row was written, so the specific contribution in aid of construction terms, facility definitions, and any revenue credit are not stated here.
PUR-2026-00131
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
SCC Fact Sheet, Rider T1 2026 Decision, post date September 3, 2026, Background and direct assignment sections (order establishing this docket entered August 25, 2026; case number PUR-2026-00131; direct connect, but for, and prospective terms)
Utility proceedingDecidedMay 1, 2026Virginia State Corporation Commission
Application of Virginia Electric and Power Company for approval of a rate adjustment clause (Rider T1) pursuant to Section 56-585.1 A 4 of the Code of Virginia
Transmission cost recovery case (Rider T1) in which the Commission also decided how transmission costs are allocated as large load grows. It approved two changes to Dominion transmission cost allocation method: a forecast adjustment that aligns allocation with rapidly expanding large load growth, and an adjustment incorporating the 85 percent transmission minimum demand charge for certain large load customers from January 1, 2027 (the GS-5 minimum decided in PUR-2025-00058). On the Commission illustration, the amended method cuts the projected Rider T1 increase for a typical residential customer using 1,000 kWh from $2.90 to $0.94 a month. The final order also approved a staff framework to require large load customers to fund direct connect transmission facilities needed for new or expanding large loads, through amendments to Dominion line extension policy in a new supplemental docket, PUR-2026-00131.
PUR-2026-00056
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Order for Notice and Hearing, May 11, 2026 (application filed May 1, 2026 for Rider T1 under Section 56-585.1 A 4); SCC Fact Sheet, Rider T1 2026 Decision, post date September 3, 2026 (approved forecast adjustment and 85 percent transmission minimum demand adjustment; $2.90 to $0.94 illustration; direct assignment framework; new docket PUR-2026-00131)
Air permitIssuedApr 3, 2026Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, Registration No. 74260, permit action 74260-2
Issued (Article 6 minor New Source Review)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
DEQ issued-permits list (Oct. 26, 2026): NTT Global Data Centers VA10 LLC, Reg. 74260-2, 2026-04-03, us-va-prince-william
Utility proceedingPending before the commissionFeb 2, 2026Virginia State Corporation Commission
Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards
A batch queue for Delivery Point Requests from distribution companies seeking to serve data centers in the Dominion Zone, about 100 MW or more per request and capped at 300 MW. Requests move through Initiation, Feasibility (zoning conformance letter and 30 percent engineering site plan), Development (permits and 100 percent grading plan), and Execution stages. The filing states about 70,000 MW of requests in the queue.
PUR-2026-00011
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Application filed 2026-02-02 (Submission ID 36180), pages 1-2 (applicability to DP Requests of approximately 100 MW or more; PUR-2025-00058 Final Order at 22-23 directive)
2025
Recorded voteJul 29, 2025Prince William County Board of County Supervisors
Ordinance No. 25-47, Proffer Amendment/Rezoning REZ2024-00025 (Manassas Corporate Center MCC-7)
7 yes. Andrea Bailey (Prince William County Board of County Supervisors): yes; Deshundra Jefferson (Prince William County Board of County Supervisors): yes; Kenny Boddye (Prince William County Board of County Supervisors): yes; Margaret Franklin (Prince William County Board of County Supervisors): yes; Tom Gordy (Prince William County Board of County Supervisors): yes; Victor Angry (Prince William County Board of County Supervisors): yes; Yesli Vega (Prince William County Board of County Supervisors): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Votes block printed on the ordinance: Ayes: Angry, Bailey, Boddye, Franklin, Gordy, Jefferson, Vega; Nays: None; Absent from Vote: None
Recorded voteJul 29, 2025Prince William County Board of County Supervisors
Ordinance No. 25-48, Rezoning REZ2024-00041 (VA 8/9 Rezoning, Iron Mountain)
7 yes. Andrea Bailey (Prince William County Board of County Supervisors): yes; Deshundra Jefferson (Prince William County Board of County Supervisors): yes; Kenny Boddye (Prince William County Board of County Supervisors): yes; Margaret Franklin (Prince William County Board of County Supervisors): yes; Tom Gordy (Prince William County Board of County Supervisors): yes; Victor Angry (Prince William County Board of County Supervisors): yes; Yesli Vega (Prince William County Board of County Supervisors): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Votes block printed on the ordinance: Ayes: Angry, Bailey, Boddye, Franklin, Gordy, Jefferson, Vega; Nays: None; Absent from Vote: None
Utility proceedingDecidedMar 31, 2025Virginia State Corporation Commission
Application of Virginia Electric and Power Company for a 2025 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
The Final Order created Schedule GS-5, a rate class for customers demanding 25 MW or more with a load factor of at least 75 percent, effective January 1, 2027. Large customers pay minimum demand charges of 85 percent of contracted distribution demand, 85 percent of contracted transmission demand, and 60 percent of contracted generation demand. The filed GS-3 and GS-4 tariff pages confirm the same minimums reach 25 MW customers on other schedules through Terms and Conditions Section XXVII from January 1, 2027.
PUR-2025-00058
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
SCC news release, case summary paragraph (GS-5, 25 MW, 85/85/60 minimums, January 1, 2027); Entire Filed Tariff revised 2026-06-01, GS-4 paragraphs I.F, II.B and VIII and GS-3 paragraphs I.G and II.B (high load minimums from 2027-01-01)
2023
Utility proceedingDecidedJul 3, 2023Virginia State Corporation Commission
Application of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
This review approved the Contract Dollar Minimum policy now in Terms and Conditions Section XXII.Q: when net distribution investment for new service exceeds $350,000, Dominion may require a written revenue guarantee with a monthly minimum of 50 percent of the customer's lowest anticipated monthly bill, secured by cash deposit, surety bond, or irrevocable letter of credit. The minimum ends when the term expires or revenues collected exceed the net investment.
PUR-2023-00101
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Entire Filed Tariff revised 2026-06-01, Terms and Conditions Section XXII.Q (effective 2026-01-01)
2016
Zoning ruleIn effectMay 17, 2016Prince William County
Data Center Opportunity Zone Overlay District
Prince William County created a Data Center Opportunity Zone Overlay District to steer data centers to areas with existing infrastructure: inside the overlay data centers are permitted by right under design standards and outside it they need a special use permit; data centers are prohibited outright in the agricultural residential PMR B-2 B-3 and V districts.
County Code Sec. 32-509.01 et seq. (Part 509) Ord. No. 16-21
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
County Code Part 509 Secs. 32-509.01 to 32-509.06; Board resolution Res. No. 26-374 (2026-06-09) reciting the 2016 adoption and 2019 standards amendment
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Issued Air Permits for Data Centers, as of Oct. 26, 2026
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source · Archived copy - 2Res. No. 26-374 initiating the DCOZOD text amendment with the Part 509 text attached
Prince William CountyTier 1 · Captured 2026-11-08 · Open the source - 3Ordinance approving DPA2026-00006 (DCOZOD text amendment) 2026-09-22
Prince William CountyTier 1 · Captured 2026-11-08 · Open the source - 4Data Center Opportunity Zone Overlay District comprehensive review page (DPA2021-00020)
Prince William County Planning OfficeTier 1 · Captured 2026-11-10 · Open the source - 5Data Center Site Plan Submissions Memorandum, October 16, 2026
Prince William County Development ServicesTier 1 · Captured 2026-11-10 · Open the source - 6Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Captured 2026-11-07 · Open the source - 7SCC Issues Order on DEV Biennial Review 2025
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 8Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
Virginia Electric and Power CompanyTier 1 · Captured 2026-11-07 · Open the source - 9How the SCC Rider T1 Decision Protects Ratepayers
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 10Order for Notice and Hearing, Case No. PUR-2026-00056
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 11Ordinance No. 25-47, Proffer Amendment/Rezoning REZ2024-00025, Manassas Corporate Center MCC-7 (adopted July 29, 2025)
Prince William County Board of County SupervisorsTier 1 · Captured 2026-11-09 · Open the source - 12Ordinance No. 25-48, Rezoning REZ2024-00041, VA 8/9 Rezoning (adopted July 29, 2025)
Prince William County Board of County SupervisorsTier 1 · Captured 2026-11-09 · Open the source - 13Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 14Factsheet: VA10 Data Center, Gainesville, Virginia
NTT DATA, Inc.Tier 4 · Captured 2026-11-13 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page