2 of 2 records · showing power and utility only ·
2025
Utility proceedingDecidedNov 7, 2025Indiana Utility Regulatory Commission
Verified Joint Petition of Northern Indiana Public Service Company LLC (NIPSCO) and NIPSCO Generation LLC (GenCo) for approval of a special contract (Data Center Customer #1 Special Contract), a power purchase agreement between NIPSCO and GenCo, and alternative regulatory plans
15-year special contract with Amazon Data Services, Inc. (unnamed in the caption as Data Center Customer #1), approved with its settlement and the NIPSCO to GenCo power purchase agreement. Contracted deliveries begin January 1, 2027 and rise to 2,400 MW by the end of 2032, on an estimated $7 billion of investment to serve Amazon. The settling parties put the fixed cost contributions passed back to other retail customers at an estimated $1.1 billion over the 15-year term. March and May 2026 amendments that would raise the commitment to 2,800 MW were still awaiting IURC and FERC approval at the last reporting and are not rowed as approved.
Cause No. 46322
Draft research, not yet verifiedLast checked Nov 11, 2026Where it says this
NiSource release, 2026-06-23, paragraphs 1-3 (June 17, 2026 full approval of the settlement, the Amazon special contract and the PPA; separate generation order the same day; about $1.4 billion in broader data center strategy savings)
No date in the record(rules in force and undated records)
Utility proceedingDecidedNo date in the recordIndiana Utility Regulatory Commission
Verified Petition of NIPSCO Generation LLC for Certain Determinations by the Commission with Respect to Its Jurisdiction Over Petitioner's Activities as a Non-Retail Generator of Electric Power
Framework order for NIPSCO’s data center generation affiliate. The Commission granted NIPSCO Generation LLC (GenCo) a limited declination of jurisdiction so it may purchase, construct, own and operate generation to serve NIPSCO megaload and data center customers, ring-fencing those generation costs from existing NIPSCO retail customers. For each megaload customer GenCo must make a Construction Compliance Filing at least 30 days before starting construction. Affiliate service agreements were filed as 30-Day Filing 50863, effective October 27, 2025. An order on reconsideration on November 19, 2025 removed GenCo’s eminent domain authority.
Cause No. 46183
Draft research, not yet verifiedLast checked Nov 11, 2026Where it says this
NiSource release, 2025-09-24 (IURC approval of the GenCo declination petition; GenCo to own, build and manage generation for the data center industry in northern Indiana, protecting existing NIPSCO retail customers)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Votes and minutes
Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1NiSource release: IURC approval of the NIPSCO GenCo declination of jurisdiction (Cause No. 46183)
NiSource Inc. (Business Wire)Tier 4 · Captured 2026-11-11 · Open the source - 2Regulatory Approvals Underscore Strength of NiSource's Customer-Focused Data Center Strategy Supporting Growth in Indiana (NiSource release, republished)
NiSource Inc. (Business Wire, republished)Tier 4 · Captured 2026-11-11 · Open the source · Archived copy - 3
- 4New Microsoft deal without abatement nets LaPorte 'unprecedented' money
South Bend TribuneTier 3 · Captured 2026-11-08 · Open the source - 5LaPorte Microsoft data center officially under construction
South Bend TribuneTier 3 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page