Every public record we have for Microsoft Hickory Data Center (Hickory Lincolnton Highway)
Hickory, Catawba County, North CarolinaUnder constructionFirst public 2022Filing entity: Microsoft Corp.Last checked Nov 8, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
2 of 2 records
2026
Zoning ruleIn effectOct 19, 2026Catawba County
First county data center regulations: industrial zones only by rezoning
Catawba County adopted its first data center rules inside a rewritten Unified Development Ordinance: the old ordinance did not list the use at all; data centers may go only in industrial zones in unincorporated areas and only after a rezoning with a public hearing. Cities and towns and their extraterritorial areas follow their own rules.
Unified Development Ordinance (2026 UDO)
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Board of Commissioners agenda packet for 2026-10-19 (UDO adoption item) and Hickory-area news report of the 3-0 vote
Setback ruleIn effectOct 19, 2026Catawba County
1000-foot separation from homes and sensitive uses
Under the 2026 Unified Development Ordinance a data center in unincorporated Catawba County must sit at least 1000 feet from homes churches schools daycares and nursing homes.
Unified Development Ordinance (2026 UDO)
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Board agenda packet data center regulations item (setbacks among the standards considered) and the news report of the adopted buffer
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Power and utility
Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Votes and minutes
Council and board votes, resolutions, hearing minutes. Usually held by: Each public body's agendas and minutes.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Board of Commissioners agenda packet October 19 2026
Catawba County North CarolinaTier 1 · Captured 2026-11-08 · Open the source - 2Catawba County sets 1000-foot buffer between data centers and homes
WHKY / Go FoothillsTier 3 · Captured 2026-11-08 · Open the source - 3Microsoft to invest $1 billion in technology facilities in Catawba County
Catawba County Economic Development CorporationTier 2 · Captured 2026-11-08 · Open the source - 4Microsoft breaks ground on another North Carolina data center
DataCenterDynamicsTier 3 · Captured 2026-11-08 · Open the source - 5Microsoft begins acquiring land in North Carolina for data centers
DataCenterDynamicsTier 3 · Captured 2026-11-08 · Open the source - 6Joint Statement on Microsoft
Catawba County, the City of Conover, the City of Hickory, the Town of Maiden and the Catawba County EDC, via EIN PresswireTier 1 · Captured 2026-11-08 · Open the source