Skip to content

Project File · Public records

Every public record we have for Microsoft data center campus (Boydton)

Boydton, Mecklenburg County, VirginiaOperatingFirst public 2010Last checked Nov 8, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

16 of 16 records

2026

  • Development ruleIn effectMay 11, 2026Mecklenburg County

    Data center noise limit of 70 dBA at the property line, with sound studies on demand

    Noise from all activities at a data center development may not exceed 70 dBA measured at the property line shared with non data center uses. The limit does not apply to demolition work, to sudden unforeseen events that require emergency vehicles or temporary emergency generator use, or to generator testing inside the allowed testing window. The Zoning Administrator may require a sound study at any time, due within 15 days and taken during peak cooling operations, and the operator must act at once to comply if the study shows an exceedance.

    Mecklenburg County Zoning Ordinance (2026), Section 7.1-7.4

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Section 7.1-7 Data Center, subsection 4 (Noise Standards), ordinance pp. 116-118 of the draft

  • Zoning ruleIn effectMay 11, 2026Mecklenburg County

    Data center is a special exception use, not a by right use

    In the county use table, Data center is listed as SE, meaning a special exception permit is required, in two district columns, and the supplemental standards at Section 7.1-7 are written around that special exception process. Data center does not appear as a permitted by right use in the table rows read. The table text extraction jumbles column order, so the two districts carrying the SE marking are not named here; the M-1 Industrial district is the district applied to the Boydton campus area.

    Mecklenburg County Zoning Ordinance (2026), Section 6.4-4 Use Table, Industrial Uses

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Use Table, Industrial Uses rows, "Data center SE SE"; district columns A-1, A-C, R-1, R-2, R-3, PUD, MU1, M-1

  • Development ruleIn effectMay 11, 2026Mecklenburg County

    Extra application studies for data centers that are high energy use facilities

    A data center that qualifies as a high energy use facility must add two items to its special exception application: an acoustical site assessment covering homes and schools within 500 feet of the property line, and a formal statement from the electric utility on substations and transmission voltage needed to serve the site. County staff may also require a site impact assessment covering water use and water sources, prime farmland, forest cover loss, and visibility from parks and historic sites within a half mile.

    Mecklenburg County Zoning Ordinance (2026), Section 7.1-7.5

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Section 7.1-7 Data Center, subsection 5 (Special Exception Permit Application Requirements and Review Criteria), ordinance pp. 117-118 of the draft

  • Development ruleIn effectMay 11, 2026Mecklenburg County

    Data center buffers, fencing, and equipment screening standards

    Data center sites must be buffered from public roadways and from natural and managed resource areas such as parks, wildlife areas, forestland, and timberland, using at least a Buffer Type A planting, with walls, fences, or berms allowed only as a supplement to landscaping. Chain link fencing visible from a street is prohibited, barbed wire and razor wire may not be visible from the public right of way or nearby homes, and electrical substations and mechanical equipment must be screened under the landscaping and screening section.

    Mecklenburg County Zoning Ordinance (2026), Section 7.1-7.C

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Section 7.1-7 Data Center, subsection C (Site Design and Layout Standards), ordinance pp. 116-117 of the draft

  • Development ruleIn effectMay 11, 2026Mecklenburg County

    Generator testing window and sound attenuating enclosures for data centers

    Generator testing at a data center is covered by the 70 dBA property line limit only when it runs between 10:00 a.m. and 4:00 p.m., unless the Department of Environmental Quality requires testing outside that window. All generators must be housed in sound attenuating enclosures or use other sound mitigation the Zoning Administrator approves.

    Mecklenburg County Zoning Ordinance (2026), Section 7.1-7.4.a.iii and Section 7.1-7.4.b

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Section 7.1-7 Data Center, subsection 4.a.iii and 4.b, ordinance p. 117 of the draft

2025

  • Utility commission decisionApprovedOct 3, 2025Virginia State Corporation Commission

    Virginia State Corporation Commission, Case No. PUR-2025-00014

    Certificate of Public Convenience and Necessity granted (Final Order)

    Stated in the filing:
    2028-11-01 desired in-service date for the Nebula transmission project
    Estimated cost:
    $129.5 million 2024 dollars, estimated conceptual cost
    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Final Order: application of Virginia Electric and Power Company for the 230 kV Nebula-Raines Line 2399, Nebula Switching Station, and Cloud-Nebula Line 2402

  • Utility proceedingPending before the commissionAug 29, 2025Virginia State Corporation Commission

    Petition of Mecklenburg Electric Cooperative for approval to implement a new Large Power Service Rate Schedule (Schedule LPS-U)

    The default tariff for large loads without a negotiated service agreement: consumers whose annual kW demand averages 5,000 kW or more per month. Demand delivery charge $8.00 per kW on existing facilities or $3.00 per kW on new dedicated facilities, which require a 100 percent advance contribution in aid of construction. Billing demand ratchets at 50 percent of the maximum billed kW in the preceding 12 months. At 25 MW average or more, all wholesale supplier charges allocated to the delivery point pass through directly. Bills are rendered weekly and due within 7 days.

    PUR-2025-00160

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Schedule LPS-U (accepted for filing 2026-09-16, effective for bills on or after 2026-09-09), Availability and rate sections; Order for Notice and Comment, 2025-09-05 (interim effectiveness)

2024

  • Air permitIssuedApr 24, 2024Virginia Department of Environmental Quality

    Virginia Department of Environmental Quality, Registration No. 21527; Permit No. PRO-21527

    Issued; initial Title V federal operating permit, effective April 24, 2024 through April 23, 2029

    Permitted run hours:
    50 hours per year, non-emergency operation, per engine
    Backup generators:
    165 engine-generator sets
    Buildings:
    15 buildings
    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Facility Information, page 2 of 40; run-hour limit at page 27

2023

  • Air permitIssuedSep 19, 2023Virginia Department of Environmental Quality

    Virginia Department of Environmental Quality, Registration No. 21527, permit action 21527-15

    Issued; significant amendment to the New Source Review permit, superseding the permit dated September 23, 2022

    Generator capacity:
    408.05 MW
    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Permit letter and Equipment List (page 3)

2021

  • Utility proceedingDecidedApr 14, 2021Virginia State Corporation Commission

    Application of Mecklenburg Electric Cooperative for approval of a special rate (Schedule RTO)

    Created Schedule RTO, a single-customer large power contract rate for one new customer with data center load, because none of the cooperative's tariffs fit the size of the load. Supply charges pass through the wholesale supplier, Old Dominion Electric Cooperative, including true-ups. Delivery charges track the customer's three-phase load ramp at the Boydton and Coleman Creek substations. First-year gross revenues were stated at $4.7 million, rising to $120 million at full capacity.

    PUR-2021-00059

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Order Granting Approval, 2021-12-14 (case caption, Schedule LP - Contract - RTO, revenue figures, findings)

2020

  • RezoningApprovedAug 10, 2020Mecklenburg County Board of Supervisors

    Mecklenburg County Board of Supervisors, County Tax Number 090000-((A))-033

    Approved unanimously

    Stated in the filing:
    310.83 acres rezoned Agriculture to Industrial M-1
    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Minutes, public hearing item 1: Mecklenburg County Industrial Development Authority application to rezone 310.83 acres from a 442.3-acre tract, Agriculture to Industrial M-1

  • RezoningApprovedAug 10, 2020Mecklenburg County Board of Supervisors

    Mecklenburg County Board of Supervisors, County Tax Number 090000-((A))-033C

    Approved unanimously

    Stated in the filing:
    335.38 acres rezoned Agriculture to Industrial M-1
    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Minutes, public hearing item 2: Microsoft Corporation application to rezone 335.38 acres from Agriculture to Industrial M-1

  • Zoning ruleIn effectAug 10, 2020Mecklenburg County

    Rezoning of about 646 acres near Boydton from agriculture to M-1 industrial for data center expansion

    The Board of Supervisors rezoned two tracts near the existing Microsoft data center in Boydton from agriculture to M-1 industrial to allow future data center expansion. One tract of 310.83 acres was owned by the Mecklenburg County Industrial Development Authority and the other, 335.38 acres, by Microsoft, near Old Cox and Ridge Roads.

    Board of Supervisors rezoning action of 2020-08-10 (agriculture to M-1 industrial; case numbers not stated in the sources read)

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Article text reporting the 2020-08-10 Board of Supervisors vote (unanimous)

  • Recorded voteAug 10, 2020Mecklenburg County Board of Supervisors

    Mecklenburg County Industrial Development Authority application to rezone 310.83 acres from Agriculture to Industrial M-1 (Boydton District)

    9 yes. Barbour (Supervisor): yes; Brankley (Supervisor): yes; Hargrove (Supervisor): yes; Jennings (Supervisor): yes; Jones (Supervisor): yes; Lundy (Supervisor): yes; Spain (Supervisor): yes; Tanner (Supervisor): yes; Wilkinson (Supervisor): yes.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Rezoning item, Industrial Development Authority (motion by Jennings; unanimous)

  • Recorded voteAug 10, 2020Mecklenburg County Board of Supervisors

    Microsoft Corporation application to rezone 335.38 acres from Agriculture to Industrial M-1 (Boydton District)

    9 yes. Barbour (Supervisor): yes; Brankley (Supervisor): yes; Hargrove (Supervisor): yes; Jennings (Supervisor): yes; Jones (Supervisor): yes; Lundy (Supervisor): yes; Spain (Supervisor): yes; Tanner (Supervisor): yes; Wilkinson (Supervisor): yes.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Rezoning item, Microsoft Corporation (motion by Jennings; unanimous)

2010

  • Tax agreementJul 12, 2010Mecklenburg County

    Economic stimulus grants (rebates of taxes paid)

    A grant of 90 percent of the company's personal property tax for 20 years, plus a grant of 100 percent of the county machinery and tools tax for 5 years. Tied to the project locating in the county.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    Article text reporting the two unanimous motions of July 12, 2010

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Board of Supervisors Minutes, August 10, 2020
    Mecklenburg County
    Tier 1 · Captured 2026-11-07 · Open the source
  2. 2
    Initial Title V Permit, Microsoft Corp, East Coast Data Center (Permit No. PRO-21527)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Final Order, Case No. PUR-2025-00014 (Nebula-Raines Line 2399, Nebula Switching Station, Cloud-Nebula Line 2402)
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Stationary Source Permit to Construct and Operate, significant amendment (permit action 21527-15), Microsoft Corporation, East Coast Data Center
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    County lines up incentive package, The Mecklenburg Sun, July 14, 2010
    The Mecklenburg Sun (SoVaNow)
    Tier 3 · Captured 2026-11-07 · Open the source
  6. 6
    Mecklenburg County Planning Commission agenda packet, March 19, 2026 (includes Zoning Ordinance Draft 3-3-2026)
    Mecklenburg County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  7. 7
    Mecklenburg County rezones near Microsoft site
    SoVaNOW (The News & Record and The Mecklenburg Sun)
    Tier 3 · Captured 2026-11-07 · Open the source
  8. 8
    Schedule LPS-U, Large Power Service
    Mecklenburg Electric Cooperative
    Tier 1 · Captured 2026-11-07 · Open the source
  9. 9
    Order for Notice and Comment, Case No. PUR-2025-00160 (Mecklenburg Electric Cooperative Schedule LPS-U)
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-07 · Open the source
  10. 10
    Order Granting Approval, Case No. PUR-2021-00059 (Mecklenburg Electric Cooperative special rate, Schedule RTO)
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-07 · Open the source
  11. 11
    Governor McAuliffe Announces 44 New Jobs and More than $251 Million Investment in Mecklenburg County
    Virginia Economic Development Partnership
    Tier 1 · Captured 2026-11-07 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page