Project File · Public records
Every public record we have for Microsoft data center campus (Boydton)
Boydton, Mecklenburg County, VirginiaOperatingFirst public 2010Last checked Nov 8, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
16 of 16 records
2026
Development ruleIn effectMay 11, 2026Mecklenburg County
Data center noise limit of 70 dBA at the property line, with sound studies on demand
Noise from all activities at a data center development may not exceed 70 dBA measured at the property line shared with non data center uses. The limit does not apply to demolition work, to sudden unforeseen events that require emergency vehicles or temporary emergency generator use, or to generator testing inside the allowed testing window. The Zoning Administrator may require a sound study at any time, due within 15 days and taken during peak cooling operations, and the operator must act at once to comply if the study shows an exceedance.
Mecklenburg County Zoning Ordinance (2026), Section 7.1-7.4
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Section 7.1-7 Data Center, subsection 4 (Noise Standards), ordinance pp. 116-118 of the draft
Zoning ruleIn effectMay 11, 2026Mecklenburg County
Data center is a special exception use, not a by right use
In the county use table, Data center is listed as SE, meaning a special exception permit is required, in two district columns, and the supplemental standards at Section 7.1-7 are written around that special exception process. Data center does not appear as a permitted by right use in the table rows read. The table text extraction jumbles column order, so the two districts carrying the SE marking are not named here; the M-1 Industrial district is the district applied to the Boydton campus area.
Mecklenburg County Zoning Ordinance (2026), Section 6.4-4 Use Table, Industrial Uses
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Use Table, Industrial Uses rows, "Data center SE SE"; district columns A-1, A-C, R-1, R-2, R-3, PUD, MU1, M-1
Development ruleIn effectMay 11, 2026Mecklenburg County
Extra application studies for data centers that are high energy use facilities
A data center that qualifies as a high energy use facility must add two items to its special exception application: an acoustical site assessment covering homes and schools within 500 feet of the property line, and a formal statement from the electric utility on substations and transmission voltage needed to serve the site. County staff may also require a site impact assessment covering water use and water sources, prime farmland, forest cover loss, and visibility from parks and historic sites within a half mile.
Mecklenburg County Zoning Ordinance (2026), Section 7.1-7.5
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Section 7.1-7 Data Center, subsection 5 (Special Exception Permit Application Requirements and Review Criteria), ordinance pp. 117-118 of the draft
Development ruleIn effectMay 11, 2026Mecklenburg County
Data center buffers, fencing, and equipment screening standards
Data center sites must be buffered from public roadways and from natural and managed resource areas such as parks, wildlife areas, forestland, and timberland, using at least a Buffer Type A planting, with walls, fences, or berms allowed only as a supplement to landscaping. Chain link fencing visible from a street is prohibited, barbed wire and razor wire may not be visible from the public right of way or nearby homes, and electrical substations and mechanical equipment must be screened under the landscaping and screening section.
Mecklenburg County Zoning Ordinance (2026), Section 7.1-7.C
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Section 7.1-7 Data Center, subsection C (Site Design and Layout Standards), ordinance pp. 116-117 of the draft
Development ruleIn effectMay 11, 2026Mecklenburg County
Generator testing window and sound attenuating enclosures for data centers
Generator testing at a data center is covered by the 70 dBA property line limit only when it runs between 10:00 a.m. and 4:00 p.m., unless the Department of Environmental Quality requires testing outside that window. All generators must be housed in sound attenuating enclosures or use other sound mitigation the Zoning Administrator approves.
Mecklenburg County Zoning Ordinance (2026), Section 7.1-7.4.a.iii and Section 7.1-7.4.b
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Section 7.1-7 Data Center, subsection 4.a.iii and 4.b, ordinance p. 117 of the draft
2025
Utility commission decisionApprovedOct 3, 2025Virginia State Corporation Commission
Virginia State Corporation Commission, Case No. PUR-2025-00014
Certificate of Public Convenience and Necessity granted (Final Order)
- Stated in the filing:
- 2028-11-01 desired in-service date for the Nebula transmission project
- Estimated cost:
- $129.5 million 2024 dollars, estimated conceptual cost
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Final Order: application of Virginia Electric and Power Company for the 230 kV Nebula-Raines Line 2399, Nebula Switching Station, and Cloud-Nebula Line 2402
Utility proceedingPending before the commissionAug 29, 2025Virginia State Corporation Commission
Petition of Mecklenburg Electric Cooperative for approval to implement a new Large Power Service Rate Schedule (Schedule LPS-U)
The default tariff for large loads without a negotiated service agreement: consumers whose annual kW demand averages 5,000 kW or more per month. Demand delivery charge $8.00 per kW on existing facilities or $3.00 per kW on new dedicated facilities, which require a 100 percent advance contribution in aid of construction. Billing demand ratchets at 50 percent of the maximum billed kW in the preceding 12 months. At 25 MW average or more, all wholesale supplier charges allocated to the delivery point pass through directly. Bills are rendered weekly and due within 7 days.
PUR-2025-00160
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Schedule LPS-U (accepted for filing 2026-09-16, effective for bills on or after 2026-09-09), Availability and rate sections; Order for Notice and Comment, 2025-09-05 (interim effectiveness)
2024
Air permitIssuedApr 24, 2024Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, Registration No. 21527; Permit No. PRO-21527
Issued; initial Title V federal operating permit, effective April 24, 2024 through April 23, 2029
- Permitted run hours:
- 50 hours per year, non-emergency operation, per engine
- Backup generators:
- 165 engine-generator sets
- Buildings:
- 15 buildings
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Facility Information, page 2 of 40; run-hour limit at page 27
2023
Air permitIssuedSep 19, 2023Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, Registration No. 21527, permit action 21527-15
Issued; significant amendment to the New Source Review permit, superseding the permit dated September 23, 2022
- Generator capacity:
- 408.05 MW
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Permit letter and Equipment List (page 3)
2021
Utility proceedingDecidedApr 14, 2021Virginia State Corporation Commission
Application of Mecklenburg Electric Cooperative for approval of a special rate (Schedule RTO)
Created Schedule RTO, a single-customer large power contract rate for one new customer with data center load, because none of the cooperative's tariffs fit the size of the load. Supply charges pass through the wholesale supplier, Old Dominion Electric Cooperative, including true-ups. Delivery charges track the customer's three-phase load ramp at the Boydton and Coleman Creek substations. First-year gross revenues were stated at $4.7 million, rising to $120 million at full capacity.
PUR-2021-00059
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Order Granting Approval, 2021-12-14 (case caption, Schedule LP - Contract - RTO, revenue figures, findings)
2020
RezoningApprovedAug 10, 2020Mecklenburg County Board of Supervisors
Mecklenburg County Board of Supervisors, County Tax Number 090000-((A))-033
Approved unanimously
- Stated in the filing:
- 310.83 acres rezoned Agriculture to Industrial M-1
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Minutes, public hearing item 1: Mecklenburg County Industrial Development Authority application to rezone 310.83 acres from a 442.3-acre tract, Agriculture to Industrial M-1
RezoningApprovedAug 10, 2020Mecklenburg County Board of Supervisors
Mecklenburg County Board of Supervisors, County Tax Number 090000-((A))-033C
Approved unanimously
- Stated in the filing:
- 335.38 acres rezoned Agriculture to Industrial M-1
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Minutes, public hearing item 2: Microsoft Corporation application to rezone 335.38 acres from Agriculture to Industrial M-1
Zoning ruleIn effectAug 10, 2020Mecklenburg County
Rezoning of about 646 acres near Boydton from agriculture to M-1 industrial for data center expansion
The Board of Supervisors rezoned two tracts near the existing Microsoft data center in Boydton from agriculture to M-1 industrial to allow future data center expansion. One tract of 310.83 acres was owned by the Mecklenburg County Industrial Development Authority and the other, 335.38 acres, by Microsoft, near Old Cox and Ridge Roads.
Board of Supervisors rezoning action of 2020-08-10 (agriculture to M-1 industrial; case numbers not stated in the sources read)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Article text reporting the 2020-08-10 Board of Supervisors vote (unanimous)
Recorded voteAug 10, 2020Mecklenburg County Board of Supervisors
Mecklenburg County Industrial Development Authority application to rezone 310.83 acres from Agriculture to Industrial M-1 (Boydton District)
9 yes. Barbour (Supervisor): yes; Brankley (Supervisor): yes; Hargrove (Supervisor): yes; Jennings (Supervisor): yes; Jones (Supervisor): yes; Lundy (Supervisor): yes; Spain (Supervisor): yes; Tanner (Supervisor): yes; Wilkinson (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Rezoning item, Industrial Development Authority (motion by Jennings; unanimous)
Recorded voteAug 10, 2020Mecklenburg County Board of Supervisors
Microsoft Corporation application to rezone 335.38 acres from Agriculture to Industrial M-1 (Boydton District)
9 yes. Barbour (Supervisor): yes; Brankley (Supervisor): yes; Hargrove (Supervisor): yes; Jennings (Supervisor): yes; Jones (Supervisor): yes; Lundy (Supervisor): yes; Spain (Supervisor): yes; Tanner (Supervisor): yes; Wilkinson (Supervisor): yes.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Rezoning item, Microsoft Corporation (motion by Jennings; unanimous)
2010
Tax agreementJul 12, 2010Mecklenburg County
Economic stimulus grants (rebates of taxes paid)
A grant of 90 percent of the company's personal property tax for 20 years, plus a grant of 100 percent of the county machinery and tools tax for 5 years. Tied to the project locating in the county.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Article text reporting the two unanimous motions of July 12, 2010
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Board of Supervisors Minutes, August 10, 2020
Mecklenburg CountyTier 1 · Captured 2026-11-07 · Open the source - 2Initial Title V Permit, Microsoft Corp, East Coast Data Center (Permit No. PRO-21527)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 3Final Order, Case No. PUR-2025-00014 (Nebula-Raines Line 2399, Nebula Switching Station, Cloud-Nebula Line 2402)
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 4Stationary Source Permit to Construct and Operate, significant amendment (permit action 21527-15), Microsoft Corporation, East Coast Data Center
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 5County lines up incentive package, The Mecklenburg Sun, July 14, 2010
The Mecklenburg Sun (SoVaNow)Tier 3 · Captured 2026-11-07 · Open the source - 6Mecklenburg County Planning Commission agenda packet, March 19, 2026 (includes Zoning Ordinance Draft 3-3-2026)
Mecklenburg County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 7Mecklenburg County rezones near Microsoft site
SoVaNOW (The News & Record and The Mecklenburg Sun)Tier 3 · Captured 2026-11-07 · Open the source - 8Schedule LPS-U, Large Power Service
Mecklenburg Electric CooperativeTier 1 · Captured 2026-11-07 · Open the source - 9Order for Notice and Comment, Case No. PUR-2025-00160 (Mecklenburg Electric Cooperative Schedule LPS-U)
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 10Order Granting Approval, Case No. PUR-2021-00059 (Mecklenburg Electric Cooperative special rate, Schedule RTO)
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 11Governor McAuliffe Announces 44 New Jobs and More than $251 Million Investment in Mecklenburg County
Virginia Economic Development PartnershipTier 1 · Captured 2026-11-07 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page