Every public record we have for Meta Mesa Data Center

Mesa, Maricopa County, ArizonaOperatingFirst public 2021Filing entity: Redale LLCLast checked Nov 8, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

7 of 19 records · showing power and utility only ·

2024

  • Utility proceedingDecidedDec 2, 2024Board of Directors, Salt River Project Agricultural Improvement and Power District

    Proposed Adjustments to SRP's Standard Electric Price Plans Effective with the November 2025 Billing Cycle

    SRP's elected Board, not the Arizona Corporation Commission, sets its prices through a public pricing process. This process raised overall net revenue 2.4 percent from the November 2025 billing cycle and rewrote the E-67 large load plan: new large load customers must take E-67 and are billed on a minimum demand of 80 percent of their forecasted demand. Management committed to put security requirements in place for new E-67 customers, lasting for the duration of the customer's service agreement.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    SRP Notice of Changes, opening paragraph (Board concluded the process February 27, 2025; +2.4 percent net) and item 5 (E-67 changes); Management Recommendations memorandum, 2025-02-21, item 6 (Credit Provisions for E-67 Customers)

  • Utility proceedingIn effectJan 1, 2024Board of Directors, Salt River Project Agricultural Improvement and Power District

    Buy-Through Program

    A large customer arranges its own generation supply from an eligible third party and SRP delivers it for a Buy-Through Charge, $4.03 per kW from November 1, 2025. The customer needs a minimum annual peak demand of 5 MW and a minimum average monthly load factor of 60 percent, and must be on plan E-63, E-65, or E-67. Total program participation is capped at 200 MW of customer demand.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    SRP Buy-Through Program page, About the program (200 MW cap, 5 MW and 60 percent minimums) and Buy-Through Program Updates (November 1, 2025 charge change)

2022

  • Utility commission decisionApprovedAug 16, 2022Arizona Corporation Commission

    Arizona Corporation Commission, Decision No. 78669; Docket No. L-00000B-22-0113-00204

    Certificate of Environmental Compatibility for SRP's Project Huckleberry approved

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    Decision No. 78669; SRP Notice of Filing Direct Testimony Summaries (Woolfolk), filed May 16, 2022

No date in the record(rules in force and undated records)

  • Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District

    E-67, Standard Price Plan for Large Load Substation Large General Service

    A Large Load Account is an account with a load of 20 MW or more, or reasonably expected to reach 20 MW within five years of first taking service. Accounts first taking service on or after November 1, 2025 must take E-67 and are billed per-kW charges on at least 80 percent of their forecasted demand, whether they use it or not; SRP may reduce the floor where the customer pays for load-serving resources itself, or for economic development reasons. The customer signs an Agreement for Electric Service that specifies the minimum billing demand, the maximum load, and forecasting requirements, and pays a customer-specific facilities charge for its substation on top of the $5,767.02 monthly service charge.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    E-67 rate book sheet (November 2025 billing cycle), Availability, Special Conditions A to H (Condition B, 80 percent minimum billing demand; Condition E, Agreement for Electric Service), Minimum Bill section

  • Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District

    E-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load

    For customers with maximum billing demand over 5,000 kW who also qualify for E-65 and keep at least 5,000 kW instantaneously interruptible, in exchange for lower charges. Load served under E-66 and the Customized Interruptible Rider together is capped at 205 MW, allocated as SRP decides.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    E-66 rate book sheet (November 2025 billing cycle), Availability (billing demand over 5,000 kW; 205 MW aggregate cap)

  • Utility proceedingIn effectNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District

    E-65, Standard Price Plan for Substation Large General Service

    Substation-level service with no MW threshold: a $5,767.02 monthly service charge (one meter) plus a customer-specific facilities charge and seasonal on-peak demand charges. Transmission-voltage service above 69 kV earns a 20.1 percent transmission charge reduction.

    Draft research, not yet verifiedLast checked Nov 7, 2026
    Where it says this

    E-65 rate book sheet (November 2025 billing cycle), Availability and monthly service charge table

  • Utility proceedingDecidedNo date in the recordBoard of Directors, Salt River Project Agricultural Improvement and Power District

    Temporary Decrease to SRP's Fuel and Purchased Power Adjustment Mechanism (FPPAM) Prices, May Through October 2026 Billing Cycles

    The Board cut FPPAM prices by $0.0038 per kWh for the summer and summer peak 2026 seasons, an overall temporary price decrease of about 3 percent, worth about $5.57 a month to the average residential customer. The decrease applied to all price plans, which includes the large general service plans E-65, E-66 and E-67 whose bills carry the FPPAM component, so large load customers received it on the same per-kWh terms as every other customer. It ran only for the May through October 2026 billing cycles and then reverted to the November 2025 price levels with the November 2026 billing cycle. Management proposed it because the FPPAM balance, the difference between fuel and purchased power costs and what customers have paid toward them, was projected to sit above its Board-approved target range (a surplus of more than $50 million at the end of April 2026).

    Draft research, not yet verifiedLast checked Nov 8, 2026
    Where it says this

    District Board packet for April 13, 2026, minutes of March 26, 2026, consent agenda item B (approval to temporarily decrease FPPAM prices by $0.0038 per kWh effective with the May 2026 billing cycle, summer and summer peak 2026, all price plans); FY26 Annual Report, Electricity Pricing section (Board approved a 3 percent overall summer price decrease through an FPPAM reduction for the May through October 2026 billing cycles, reverting to November 2025 levels)

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Environmental permits

    Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    Decision No. 78669, Certificate of Environmental Compatibility for Project Huckleberry (Docket No. L-00000B-22-0113-00204)
    Arizona Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Notice of Filing Direct Testimony Summaries, Project Huckleberry CEC application (filed May 16, 2022)
    Arizona Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Notice of Changes to SRP Standard Electric Price Plans
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  4. 4
    Development Agreement, City of Mesa, Arizona and Redale LLC (2021)
    City of Mesa (Legistar)
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Resolution No. 11680 (Development Agreement and Sustainable Water Service Agreement with Redale LLC)
    City of Mesa
    Tier 1 · Captured 2026-11-07 · Open the source
  6. 6
    Sustainable Water Service Agreement between the City of Mesa, Arizona and Redale LLC (2021)
    City of Mesa (Legistar)
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Board Approves Modernized Zoning Ordinance (news release, December 10, 2025)
    Maricopa County, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source
  8. 8
    Arizona Technology Council article on the Mesa data center standards
    Arizona Technology Council
    Tier 3 · Captured 2026-11-07 · Open the source
  9. 9
    Examples of Local Zoning (resource quoting Mesa City Code Section 11-31-36 verbatim)
    Lincoln Institute of Land Policy
    Tier 2 · Captured 2026-11-07 · Open the source
  10. 10
    Development Community Newsletter, September 2025 (data center ordinance summary)
    City of Mesa, Arizona
    Tier 1 · Captured 2026-11-07 · Open the source
  11. 11
    Mesa, Arizona noise ordinance, Title 6, Chapter 12
    Noise Pollution Clearinghouse (law library copy of City of Mesa code text)
    Tier 2 · Captured 2026-11-07 · Open the source
  12. 12
    Buy-Through Program for large businesses
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  13. 13
    E-67, Standard Price Plan for Large Load Substation Large General Service (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  14. 14
    Management Recommendations for the February 27, 2025 Special Board Meeting
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  15. 15
    E-66, Standard Price Plan for Substation Large General Service with Instantaneously Interruptible Load (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  16. 16
    E-65, Standard Price Plan for Substation Large General Service (November 2025 billing cycle)
    Salt River Project
    Tier 1 · Captured 2026-11-07 · Open the source
  17. 17
    SRP District Board packet, April 13, 2026 (including the minutes of the March 26, 2026 Special Board meeting)
    Salt River Project
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    SRP Annual Report, Fiscal Year 2026 (including Five-Year Operational and Statistical Review and Financial Summary)
    Salt River Project
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    Council Minutes, Regular Council Meeting, May 17, 2021
    City of Mesa, Office of the City Clerk
    Tier 1 · Captured 2026-11-08 · Open the source
  20. 20
    Mesa we are online!
    Meta Data Centers
    Tier 4 · Captured 2026-11-07 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page