Project File · Public records
Every public record we have for Meta Huntsville Data Center
Huntsville, Madison County, AlabamaOperatingFirst public 2018Filing entity: Starbelt LLCLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
8 of 17 records · showing land and zoning rules only ·
2021
Development agreementApprovedDec 16, 2021City of Huntsville City Council
City of Huntsville City Council, Project Ferris project agreement
Approved (project agreement for the 250-acre second campus north of the current site)
- Tax exemption percent:
- 100 percent of noneducational State, County and City ad valorem taxes, construction-related transaction taxes, and mortgage and recording taxes abated by the Industrial Development Board
- Estimated cost:
- $750 million second-campus expansion investment
- Buildings:
- 3 data center buildings under construction
- Stated in the filing:
- 590 acres, combined area of the Project Starbelt Site (about 340 acres) and the Project Ferris Site (about 250 acres)
- Stated in the filing:
- 250 acres (second-campus expansion site)
- Stated in the filing:
- 2,500 linear feet of 16-inch water main, Liberty Hill North Water Main Extension, from Routt Road to the proposed Project Ferris water meter location (Company funded; final ownership Huntsville Utilities; scheduled completion April 1, 2023)
- Stated in the filing:
- 1,400 GPM peak design flow, Ferris wastewater lift station, built by the Company and dedicated to the City (scheduled completion April 1, 2023)
- Stated in the filing:
- 5,000 GPM, Water Booster Pump Station transferring water within the City pressure zone to the Liberty Hill Tank, at Bob Wade Lane and Pulaski Pike (Huntsville Utilities; scheduled completion June 1, 2025)
- Exemption term years:
- 30 years, the maximum period allowed under Ala. Code Section 40-9B-3(a)(12); the agreement recital on Act No. 2012-210 states the IDB may cause noneducational ad valorem and construction-related transactional taxes to be abated for a period of up to 30 years
- Stated in the filing:
- 50 new full-time jobs at an average annual compensation of not less than $80,000, stated in the agreement as Company Estimates
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
City of Huntsville article, December 30, 2021
2018
Development agreementApprovedMay 30, 2018City of Huntsville and Industrial Development Board of the City of Huntsville
City of Huntsville and Industrial Development Board of the City of Huntsville
Project Development Agreement (the Project Starbelt Agreement) for the original 340 acre campus, with incentives and abatements, as recited in the December 2021 Project Ferris agreement
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Project Development Agreement (2021), Recital 1 (agreement p. 1)
2005
Development ruleIn effect2005Madison County
State law authorizes a county noise ordinance outside city limits; no county ordinance with limits located
State law lets the Madison County Commission enact a noise ordinance for areas outside any city limits, with a violation treated as a public nuisance and a civil fine of not more than 1,000 dollars per day. The statute sets no decibel limits itself, and it bars ordinances that restrict state or federally permitted mining noise or train noise. No enacted Madison County noise ordinance with numeric limits was located in this pass, so the only citable county noise rule is this enabling authority.
Alabama Code Section 45-45-174 (Act 2005-104)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Code of Alabama Section 45-45-174(a), Noise Control (ALISON)
1963
Zoning ruleIn effectMar 21, 1963Huntsville
Computer and data processing services are also a permitted use in the Research Park Applications district
The Research Park Applications district also lists computer and data processing services as a permitted use, alongside telecommunications, communication services, laboratories, and research uses. The Heavy Industry district at Section 41.1 separately permits any use permitted under the Light Industry district at Section 40.1, but the Light Industry list read does not name computer and data processing services.
Huntsville Zoning Ordinance, Article 52 (Research Park Applications District), Section 52.1 Uses Permitted
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Article 52, Section 52.1, use list entry "Computer and data processing services"; Article 41, Section 41.1 cross reference to Section 40.1
Zoning ruleIn effectMar 21, 1963Huntsville
Computer and data processing services are a permitted use in the Planned Industrial district
The Planned Industrial district permits computer and data processing services by right, on a district meant for basic industries on large tracts. The ordinance never uses the term data center anywhere in its text, so a data center is handled through this older computer and data processing services category rather than a data center specific rule.
Huntsville Zoning Ordinance, Article 42 (Planned Industrial District), Section 42.1 Uses Permitted
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Article 42, Section 42.1, use list entry "Computer and data processing services"; full text search of the ordinance returned no hit for "data center"
Setback ruleIn effectMar 21, 1963Huntsville
In the Light and Heavy Industry districts, a 25 foot yard is required only where a lot abuts a residential district
Both the Light Industry and Heavy Industry districts require a front yard of 50 feet from major arterials and 30 feet from other streets. No rear or side yard is required unless the lot line abuts a residential district, in which case a 25 foot yard is required on that side.
Huntsville Zoning Ordinance, Sections 40.2 and 41.3 (Light Industry and Heavy Industry density controls)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Section 40.2.2 to 40.2.4 (Light Industry) and Section 41.3.2 to 41.3.4 (Heavy Industry)
Setback ruleIn effectMar 21, 1963Huntsville
Planned Industrial required yards: 100 foot front yard, 50 foot other yards, 4 acre minimum tract
In the Planned Industrial district, front yards must be at least 100 feet deep and all other yards at least 50 feet, with yards kept clear of parking, loading, and storage, and a 25 foot utility easement along each side and rear lot line. Tracts must be at least 4 acres with at least 200 feet of width at the building line, buildings may cover at most 70 percent of the tract, and height is unlimited except near the airport. Side and rear yards also need a planted strip at least 30 feet wide, or 70 feet where the yard faces a street.
Huntsville Zoning Ordinance, Article 42 (Planned Industrial District), Sections 42.3 and 42.4
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Article 42, Sections 42.3 (Required Yards), 42.4 (Density Controls), 42.5 (Street Access and Frontage), 42.7.4 (landscaping strips)
No date in the record(rules in force and undated records)
Development ruleIn effectNo date in the recordHuntsville
Citywide decibel limits by land use category, measured at the property line
The City of Huntsville explains its noise ordinance as three land use categories with decibel limits measured from the property line of the site. Residential areas, including open space and agricultural land, are capped at 55 decibels in the day and 50 decibels at night, commercial areas at 62 decibels, and industrial areas at 70 decibels. The ordinance carries more than a dozen exemptions, including aircraft, animals, church bells, and vehicles, and domestic power equipment and construction work are exempt in the daytime hours.
City of Huntsville noise ordinance (Code of Ordinances; the section number is not stated in the city source read)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Passage "The decibel limits, as measured from the property line of the site"
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Power and utility
Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.
Sources
- 1Notice of Public Comment Period Regarding Issuance of a Major Source Operating Permit for a Data Center in Huntsville, Alabama
City of Huntsville, Natural Resources DivisionTier 1 · Captured 2026-11-08 · Open the source - 2Resolution and Project Development Agreement (Project Ferris), City of Huntsville, Industrial Development Board of the City of Huntsville, and Starbelt LLC (City Council agenda attachment, December 16, 2021)
City of Huntsville, AlabamaTier 1 · Captured 2026-11-09 · Open the source - 3Data center expansion to benefit North Huntsville, local schools (City article, December 30, 2021)
City of Huntsville, AlabamaTier 1 · Captured 2026-11-08 · Open the source - 4Huntsville Utilities Community Energy Resource Plan, Final Report (January 19, 2026)
Huntsville UtilitiesTier 1 · Captured 2026-11-09 · Open the source - 5Governor Ivey Announces Facebook to Invest $750 Million in New Data Center in Huntsville
Office of the Governor of AlabamaTier 1 · Captured 2026-11-07 · Open the source - 6Complaint, Slade-Miller v. Facebook, Inc. et al., Case 4:22-cv-00001-CLM (N.D. Ala.)
U.S. District Court, Northern District of Alabama (copy via archive.org)Tier 3 · Captured 2026-11-08 · Open the source - 7Memorandum Opinion, Johnson Contractors, Inc. v. Starbelt, LLC et al., Case No. 5:23-cv-28-CLM, Document 163 (N.D. Ala., December 9, 2025)
U.S. District Court for the Northern District of Alabama (opinion as published on govinfo, U.S. Courts Opinions collection)Tier 1 · Captured 2026-11-09 · Open the source - 8City of Huntsville Zoning Ordinance, updated to April 1, 2026
City of Huntsville, AlabamaTier 1 · Captured 2026-11-07 · Open the source - 9Code of Alabama, Section 45-45-174, Noise Control
Alabama Legislature (ALISON)Tier 1 · Captured 2026-11-08 · Open the source - 10Noise pollution: what you need to know about the City ordinance
City of Huntsville, AlabamaTier 1 · Captured 2026-11-07 · Open the source - 11Facebook opens Huntsville, Alabama data center