Every public record we have for Menlo Digital Charlotte Drive data center, San Jose
San Jose, Santa Clara County, CaliforniaIn permittingFirst public 2026Filing entity: Menlo Equities LLCLast checked Nov 8, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
2 of 2 records
2025
Recorded voteNov 18, 2025San Jose City Council
RES2025-394: Master Easements Agreement and Site Works Agreement with Microsoft Corporation and Valley Water (City Council, November 18, 2025)
10 yes, 1 recused. Anthony Tordillos (Councilmember): yes; Bien Doan (Councilmember): yes; David Cohen (Councilmember): yes; Domingo Candelas (Councilmember): yes; George Casey (Councilmember): yes; Matt Mahan (Mayor): yes; Michael Mulcahy (Councilmember): yes; Pamela Campos (Councilmember): yes; Pam Foley (Vice Mayor): recused, financial interest (as stated in the council record); Peter Ortiz (Councilmember): yes; Rosemary Kamei (Councilmember): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
City Council Minutes, November 18, 2025, item 8.1 (motion by Cohen, seconded by Candelas; 10-0-1; Recused: Foley)
Recorded voteApr 9, 2025San Jose Planning Commission
CP23-016 / V24-001: conditional use permit, development exception, and EIR certification for the Microsoft Alviso data center (Planning Commission, April 9, 2025)
9 yes. Anthony Tordillos (Chair): yes; Carlos Rosario (Commissioner): yes; Charles Cantrell (Vice Chair): yes; Dilpreet Bhandal (Commissioner): yes; Justin Lardinois (Commissioner): yes; Louis Barocio (Commissioner): yes; Melissa Bickford (Commissioner): yes; Michael Young (Commissioner): yes; Pierluigi Oliverio (Commissioner): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Planning Commission Action Minutes, April 9, 2025, item 5a (motion by Oliverio, seconded by Cantrell, passed 9-0)
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Land and zoning rules
Zoning, setbacks, height limits, rezonings, development agreements. Usually held by: City or county planning department.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Power and utility
Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1San Jose Planning Commission Action Minutes, April 9, 2025 (Microsoft CP23-016 conditional use permit, 1657 Alviso-Milpitas Rd)
City of San JoseTier 1 · Captured 2026-11-08 · Open the source - 2City Council Meeting Minutes, Tuesday, November 18, 2025
City of San Jose (City Clerk, via Legistar)Tier 1 · Captured 2026-11-09 · Open the source - 3Massive San Jose Data Center Could Begin Operations by 2029
GovTech (Mercury News reporting)Tier 3 · Captured 2026-11-08 · Open the source - 4Data center developers share plans at San Jose town hall
San Jose SpotlightTier 3 · Captured 2026-11-08 · Open the source