Project File · Public records
Every public record we have for Gregory Road Data Center
Covington, Newton County, GeorgiaProposedFirst public 2025Filing entity: John B. WilliamsLast checked Nov 8, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
8 of 13 records · showing land and zoning rules only ·
2026
Development ruleIn effectOct 6, 2026Newton County
Extension of the data center application moratorium to December 16 2026
Newton County extended its moratorium on accepting any application request or submission that proposes developing a data center in the county including rezoning special use and conditional use permits development and building permits and site plans while the county finishes studying a data center ordinance.
Resolution R-100626A
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Resolution R-100626A full text printed in the Board of Commissioners minutes for 2026-10-06 (zoning agenda item 2)
Development ruleExpiredApr 7, 2026Newton County
Limited moratorium on acceptance of data center applications
The resolution continues the county's moratorium chain (the February 17, 2026 emergency moratorium ran to March 18, and a March 3 revision extended it to April 8) by barring acceptance of data center applications until October 7, 2026, while the county drafts data center standards. Resolution R-100626A later extended the moratorium to December 16, 2026.
Resolution R-040726b
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, April 7, 2026, zoning agenda item 4
Development ruleExpiredFeb 17, 2026Newton County
Emergency moratorium on acceptance of data center applications
The resolution bars the county, until March 18, 2026, from accepting applications, requests, or submissions that propose data center development in whole or in part, including rezoning, special use and conditional use permits, development permits, site plans, and building permits. Its stated purpose is to give the county time to study and draft an ordinance on data center development. By its own terms it ended on the earliest of March 18, 2026, Board approval of an additional moratorium after a public hearing, or Board action ending it; no extension was found in the sources read.
Resolution #R021726
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Minutes item 11, Resolution #R021726, operative paragraphs 2 and 4
2009
Setback ruleIn effectFeb 17, 2009Newton County
Setbacks, height, and buffer standards in the Stanton Springs district
Development standards for the Stanton Springs district set minimum front, side, and rear setbacks, a maximum building height, and a wide transitional buffer where district property abuts residential property. Utilities must be placed underground except major electric transmission lines and substations, and occupied buildings must use public water and sewer.
Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance, Sec. 285-060 (Stanton Springs Business Park District)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance pp. 86-96, Sec. 285-060 (Standards of Development)
Development ruleIn effectFeb 17, 2009Newton County
Screening of cooling towers and mechanical and electrical equipment in Stanton Springs
In the Stanton Springs district, cooling towers and rooftop or ground mounted mechanical and electrical units that are visible from a road parcel or any public road must be built into the building design or screened from public view, and landscaping may serve as the screen. Building facades on front and street sides must use durable permanent architectural materials, and unfaced concrete block, structural concrete, corrugated metal, and pole buildings are not permitted.
Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance, Sec. 285-060.L.3 (Stanton Springs Business Park District)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Sec. 285-060.L.3 and the building standards at Sec. 285-060
Zoning ruleIn effectFeb 17, 2009Newton County
Data Management or Processing Center is a permitted use in the Stanton Springs Business Park District
The Stanton Springs district is written for large mixed use business park tracts, and its purpose section names data centers among the uses the district is well suited to. Both use tables for the district, Tier 1 inside the Business Parkway and Tier 2 outside it, list Data Management or Processing Center as P, a permitted use. County staff told the Board of Commissioners in February 2026 that the county data center rules apply only to the Stanton Springs area.
Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance, Sec. 285-010 and Sec. 285-030 (Stanton Springs Business Park District, Division 285)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance pp. 86-96, Division 285; Sec. 285-010 (purpose) and Sec. 285-030 (Tier 1 and Tier 2 use tables)
No date in the record(rules in force and undated records)
Zoning ruleProposedNo date in the recordNewton County
Unified Development Ordinance update with proposed data center standards
The ordinance would update the county's Unified Development Ordinance, carrying the proposed data center standards. On October 20, 2026 the Board voted 5-0 to defer it to December 15, 2026; it has not been adopted.
Ordinance O-102026
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, October 20, 2026, zoning new business item 1
Zoning ruleProposedNo date in the recordNewton County
Data center overlay district and map amendments
Companion ordinance to O-102026: an overlay district with future land use map and zoning map amendments for data centers. On October 20, 2026 the Board voted 5-0 to defer it to December 15, 2026; it has not been adopted.
Ordinance O-102026A
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, October 20, 2026, zoning new business item 2
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Power and utility
Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance
Newton County, GeorgiaTier 1 · Captured 2026-11-07 · Open the source - 2Board of Commissioners Regular Meeting Minutes, February 17, 2026
Newton County, GeorgiaTier 1 · Captured 2026-11-07 · Open the source - 3Board of Commissioners regular meeting minutes 2026-10-06 (full text of Resolution R-100626A)
Newton County Board of CommissionersTier 1 · Captured 2026-11-08 · Open the source - 4Board of Commissioners regular meeting minutes 2026-10-20 (UDO update ordinance O-102026 deferred)
Newton County Board of CommissionersTier 1 · Captured 2026-11-08 · Open the source - 5Newton County Board of Commissioners regular meeting minutes, April 7, 2026
Newton County Board of CommissionersTier 1 · Captured 2026-11-09 · Open the source - 6DRI #4428 Initial Information Form: Gregory Road Data Center
Georgia Department of Community AffairsTier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page